Sales & Launch Momentum

Pirojsha Godrej: "None of the projects we're adding, do we think of as like a future land bank that we're expecting to wait many years, but you do sometimes have situations particularly in some of the larger projects that they end up taking a little bit longer than one hopes to launch."

Margins & Cost Inflation


Project Additions & Business Development

Pirojsha Godrej: "I don't think it's out of reach to get to that 0.5 kind of number this year, but again, it depends on us getting the right quality and quantity of deals. At the same time, we don't want to let this cash burn a hole in our pocket. We want to wait for the right deals and do the right quality of deals."

Deliveries, Cash Flows & PAT Trajectory

Mohit Malhotra: "I think next year is going to be a spectacular year for us on PAT and FY '24 is where we should be able to hit our original guidance which we had given to the investors."

City-Level Dynamics

Mohit Malhotra: "Actually, if you ask me, if you see our Shivam project, the Kandivali project is by a local developer, and they came back and asked us to do the second phase as well. So, people see value in cleaning up the land but at the time of sales and launches, they would like to partner with bigger companies like us and some of the other players."

Capital Allocation & Growth Philosophy

Pirojsha Godrej: "I always like to say the whole top management team, just before the pandemic had spent a little bit of time in China meeting with the top developers there and if I recall correctly, I think we have done about 0.6 crore square feet of sales that year and the big Chinese developers were doing 60 crore square feet. So, with a 2% or so share of the market currently, we don't see any sort of market-imposed constraint on our growth."

Guidance & Commitments

CommitmentSpecificsTimeline
Residential bookingsGrow to over INR 10,000 croreFY23
Project deliveriesAt least cross 1 crore sq ft (vs ~0.65 crore sq ft in FY22)FY23
PAT trajectory"Spectacular year" for PAT; original investor guidance hitFY23 spectacular; FY24 guidance hit
PAT levelINR 1,000 odd crore visible on 1 crore sq ft delivery2–3 year timeframe
Gearing ratioReach 0.5x, contingent on right quality and quantity of dealsDuring FY23
Business development cash deploymentINR 1,000–1,500 crore in milestone outflows on tied-up deals; rest depends on new BDComing quarters
Ashok Vihar launchPositive outcome expectedQ1 or Q2 FY23
Wadala launchBig launch, all approvals receivedQ1 FY23
Bangalore BD turnaroundStrategy correction to yield resultsNext 6 to 9 months
Construction timeline target24 months as almost consistent average for all projectsOngoing
DividendsNone expectedNext few years

Key Metrics

MetricQ4 FY22
Booking value₹3,248 cr, +111% QoQ and +23% YoY
Homes sold3,699 homes, 0.42 crore sq ft
FY22 annual booking value₹7,861 cr, 5th consecutive record year
Residential cash collections₹2,678 cr, highest ever
Net operating cash flow₹1,045 cr, highest ever
FY22 residential collections~₹7,000 cr, +57% YoY
Total income₹1,476 cr, +191%
EBITDA₹403 cr, +611%
Net profit₹260 cr, +236%
FY22 total income₹2,397 cr, +97%
FY22 EBITDA₹705 cr
FY22 net profit₹352 cr
New project additions3 projects, 0.61 crore sq ft saleable area, >₹4,100 cr revenue potential
Deliveries0.58 crore sq ft across 5 cities
FY23 booking value guidance>₹10,000 cr
FY23 delivery target>1 crore sq ft
Blended price hike taken~5% across portfolio
Cost inflation impact~5% of booking value
Average borrowing cost5.95% YTD
Net debt positionZero net debt currently
Gearing target0.5
FY22 operating cash flow₹1,750 cr
Cash available for deployment₹4,000 cr
Sustenance sales (FY22)₹4,826 cr, +6%
New launch sales (FY22)>₹3,000 cr, +40%
Blended average margin on sales>20%
Company EBITDA margin~30%
Plotted projects margin~40%
Group housing margin20% to 25%
Best-ever OC timeline22.5 months, Pune project
Average flat cycle12 days
Mumbai BD capital committed in FY22>₹1,000 cr
JV loss reported (G2 project impact)~₹80 cr, from unleased commercial project interest expensing