Key Takeaways
- Transformational year, revenue miss: FY26 was the pivot to an integrated clean energy company with the Giga factory commissioned, but 150–200 CR of revenue deferred to FY27 on policy changes and war-driven cost spikes.
- Manufacturing is now the engine: Manufacturing contribution jumped from 17% to 31% of revenue, and the FY27 target is 53%, making Invergy the dominant vertical.
- Working capital stretched sharply: Receivable days nearly doubled to 172 and inventory days to 63; channel financing for 75–80 partners by September is the fix.
- Order book is a black box: Management declined to disclose the current confirmed order book, deferring specifics to 30th September, leaving investors to take the 2–3X revenue growth target on trust.
- What to watch next quarter: Whether the September 30th order-book reveal validates the 2–3X growth claim, the pace of channel financing rollout, and any evidence that deferred FY26 projects have actually restarted.
The FY26 Revenue Miss
- Deferred, not lost: Approximately 150–200 CR of projects scheduled for FY26 were postponed to FY27 because policy changes and government challenges slowed execution, while war conditions drove raw material costs high enough that developers pushed projects into the next financial year.
- PBT growth preserved despite the top-line shortfall: Management stated that PBT growth of three to four times was maintained even as revenue fell short of the 550–600 CR guided range.
- First-half FY27 will stay lean: Management expects the first half to be one of the lowest in the revenue mix, though it will be better than the first half of FY26; substantial numbers are promised by September when orders are shared with the exchange.
Deepak Pandey: "If they don't take actions today, their cost of because they've already taken the tenders and their cost of BESS ownership will increase and that will reduce their ROIs. So there is a rush in the industry for getting the order placed and get the implementations done and because their timelines are also near to the closures."
The Manufacturing Pivot
- Revenue mix transformed in one year: Distribution fell from 76% to 53% of revenue while manufacturing rose from 17% to 31% and EPC from 7% to 16%, a deliberate shift toward higher-margin verticals.
- FY27 target locks in the pivot: Management guided for distribution at ~13%, Invergy manufacturing at ~53%, and GPS Green Projects (EPC) at ~33%, making manufacturing the dominant segment.
- Giga factory is the cornerstone: The Dasna facility commenced commercial operations on 30th May 2026, with the first phase of the 3 GW BESS factory commissioned by 15th June 2026; some containerized-solution machines are still in transit and will require 30 days of testing after arrival next month.
- Second phase by September: Full 3 GW operation is targeted by 30th September 2026, and the company will start working on expansion to 5 GW by 2027–28 based on this year's order accruals, expecting to supply 1.5–2 GW in that year.
- Solar panel manufacturing shelved: The plan has been postponed because the company is fully engaged in BESS and the subsidiary is handling EPC.
Deepak Pandey: "This is not the small factory in making, this is the world-class factory... and it will be the India's answer to global best manufacturing, and it is ours."
Product Portfolio & Market Positioning
- Full BESS range launched under Invergy: Invergy Home (residential, 5–30 kWh LFP), Invergy Pro (C&I, 50 kWh to 2 MWh containerized), and Invergy Grid (utility-scale, 3–5 MWh).
- PV string inverter line spans 3 kW to 350 kW: The 350 kW launch is a strategic milestone targeting a massive, import-dominated segment.
- Make-in-India differentiation: Management claims over 90% of BESS competitors import systems from China and operate as traders rather than manufacturers; Invergy positions itself as a genuine domestic manufacturer with BIS and IEC certifications received or expected next month.
- Early proof points: India's first Make-in-India 1.03 MWh utility-scale BESS container supplied, and India's biggest single-site 8 MW rooftop solar PV plant executed at Ludhiana through GPS Green Projects.
- Local content commitment: More than 50% local content targeted by December 2026.
Deepak Pandey: "The 350-kilowatt string inverter launch is a strategic milestone. It puts us in a segment where the market is massive and imports currently dominate."
Working Capital & Channel Financing
- Receivable days nearly doubled to 172 from 95, and inventory days rose from 27 to 63; management attributes the stretch to partner credit terms and is implementing channel financing to reduce fund lock-in.
- Channel financing system created for ~40 partners, with a target of 75–80 partners by September 2026; the system lets partners take credit from their own funding institutions instead of the company, which should reduce receivable days and make partners independent of company credit.
- CAPEX for FY27 is ~150 CR plus, funding the Giga factory's second phase and ongoing expansion.
Order Book & Revenue Visibility
- Current order book undisclosed: When asked for the confirmed order book, management declined to provide a number, stating orders are all in discussions and on final stages, with exact guidance to be given on 30th September.
- Over 12 project orders totaling 58 MW secured in FY26, including C&I and utility-scale BESS, which management cites as market validation.
- BESS pipeline described as active: Orders are in discussion with most top-notch companies, and the company is one of the few Make-in-India BESS manufacturers.
- IPP projects to contribute from September: Own IPP projects under Kusum and solar parks will be commissioned around September 2026 and will start contributing to revenue.
- BESS realization is dynamic: Management gave only a market range of 1–1.5 crores per MWh when asked for specifics, declining to provide a firm number.
- Oriana relationship status unclear: Management said Oriana is one of the top three companies with the biggest order book and is likely to be a customer, but provided no status update before cutting off further questions.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 2–3X revenue growth, 2–3X PBT growth vs FY26 | FY27 |
| EBITDA margin | Improvement of 8–10% from FY26 | FY27 |
| Revenue mix | Distribution ~13%, Manufacturing ~53%, EPC ~33% | FY27 |
| Giga factory full capacity | 3 GW operational | 30th September 2026 |
| Local content | More than 50% | December 2026 |
| Channel financing partners | Expand from ~40 to 75–80 partners | September 2026 |
| IPP project commissioning | Kusum and solar parks begin contributing | Around September 2026 |
| Order book disclosure | Exact guidance on progress toward targets | 30th September 2026 |
| 5 GW expansion work | Begin based on FY27 order accruals | 2027–28 |
| CAPEX | ~150 CR plus | FY27 |
Key Metrics
| Metric | FY26 |
|---|---|
| Revenue | ₹414 cr, restricted due to project deferrals of ₹150–200 cr |
| Revenue growth | 3–4X, achieved as per prior commitment |
| PBT growth | 3–4X, achieved as guided |
| Revenue mix: manufacturing | 31%, up from 17% in FY25 |
| Revenue mix: distribution | 53%, down from 76% in FY25 |
| Revenue mix: EPC | ~16%, up from 7% in FY25 |
| FY27 revenue growth guidance | 2–3X, on FY26 base |
| FY27 PBT growth guidance | 2–3X |
| FY27 EBITDA margin expansion guidance | 8–10% increase from existing FY26 level |
| FY27 indicative revenue mix: Invergy manufacturing | ~53% |
| FY27 indicative revenue mix: EPC | ~33% |
| FY27 indicative revenue mix: distribution | ~13% |
| Cumulative order pipeline: BESS | ₹300 cr |
| Cumulative order pipeline: inverter segment | ₹70 cr plus |
| Cumulative order pipeline: EPC segment | ~₹50 cr |
| BESS project orders won | 58 MW across more than 12 projects |
| Dasna Giga factory total investment | ~₹200 cr |
| Dasna Giga factory full capacity | 3 GWh, expected by 30 September 2026 |
| FY27 CAPEX | ~₹150 cr plus |
| Receivable days | 172 days, up from 95 in FY25 |
| Inventory days | 63 days, up from 27 in FY25 |
| Channel partners | ~40 currently, targeting 75–80 by September 2026 |
| BESS market projection for India by 2030 | ~₹2.6 lakh cr, contributing 47–61 GWh |
| Current market share addressed | less than 0.1% |
| BESS realization range | ₹1 cr to ₹1.5 cr per MWh, dynamic with raw material and forex |