Orient Green Power Company Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/1aez2bsmkooa6gjtc66yrujn.pdf

Key Takeaways


Q1 Performance: The Wind Shortfall

Shivaraman: "We are hoping that we will exceed, but that depends on Vayu Bhagawan."

Capacity Build-Out: What Is Actually Under Construction

Shivaraman: "When you repower a turbine which is say giving you 15%, 16%, 17% PLF, you are losing that PLF. You may get 35%, 37% PLF from a new turbine, but then putting the new turbine somewhere else, even if you get 33%, it is still better because you have lost this 15%."

The 1 GW Target: Ambition Without a Timeline

Shivaraman: "We did have some serious conversations, which unfortunately did not proceed the way we wanted. But there is a lot of stuff happening at our end, and we are hopeful that something will start moving during the course of this year."

Balance Sheet & Debt: Gradual Improvement


Solar, Hybrid & Battery Storage: Early-Stage Optionality


Guidance & Commitments

CommitmentSpecificsTimeline
Greenfield solar + repowering commissioning17.6 MW solar and 7.8 MW repoweringBy end of September 2026
Q2 wind recoveryQ2 looks better than Q1; significant portion of Q1 shortfall recoverableQ2 FY27
Full-year revenueEqual to or better than last year, likely exceeding on additional capacityFY27
Full-year EBITDABetter than last yearFY27
Net debtAround ₹535 croresEnd of FY27
Debt repayment (net of new drawals)~₹100 crores net reduction in existing debtFY27
Next repowering phase (Gamma)~17.5 MWEnd of FY28
Tamil Nadu battery storage regulatory clarityOpen issues resolvedNext 2–3 months
Promoter share pledge retirementFull release, if repayment pace holdsEnd of calendar year
Strategic trigger for expansionFundraising or partnership conversations to yield somethingDuring this year

Key Metrics

MetricQ1 FY27
Revenue from operations₹81.43 cr, lower by 7% YoY
EBITDA₹60.01 cr, lower by 9% YoY
PAT₹23.94 cr, 16% lower YoY
Average interest rate9.1%, blended across all projects
Interest cost per quarter~₹14 cr, expected to remain at this level for the current year
Net debt₹535 cr expected by year-end, up ₹70 cr from last year
Debt repayment planned for FY27~₹100 cr
Incremental wind capacity commissioned9.9 MW available for operation this quarter
Solar capacity commissioned7 MW, commissioned December 2025
Solar capacity under implementation17.6 MW, expected commissioning by end of September 2026
Repowering capacity under implementation7.8 MW of old wind assets, expected commissioning by end of September 2026
FY27 planned capacity additions~11 MW wind and ~15 MW solar
Provision for Andhra Pradesh interest receivable₹6.5 cr provided on ~₹20 cr outstanding, ~30% provisioned
Carry-forward tax losses₹800–850 cr across group
Promoter share pledge~40% of promoter loan repaid, final due September 2027