Order Book & Naval Pipeline

Cmde P.R. Hari: "So, right now we have enough in our hand to last us for the next five years. That is, mid of 2023 to at least mid of 2028."

Project Execution & Delivery Schedule


Diversification & New Capabilities

Cmde P.R. Hari: "some of the nations like Norway has already given a dictate that they must grow 100% green by 2030, so it is that kind of impact and opportunity, we didn't want to miss out the first most advantage"

Capacity & Infrastructure

Cmde P.R. Hari: "we always keep around 25 to 30% for dock captive and available with us. This is the current status. We have adequate berth and dock capacity."

Margins & Financial Profile

Cmde P.R. Hari: "Ours is not a routine industry. Ours is a highly specialized industry where the PAT margin above 7.5 is considered healthy."

Guidance & Commitments

CommitmentSpecificsTimeline
Survey Vessel Large first deliveryFirst ship ready and deliveredDecember 2023
ASW Shallow Water Craft first deliveryFirst ship deliveredWithin 4 months (by ~Mar 2024)
ASW Shallow Water Craft full deliveryAll 8 ships deliveredBy 2026
Bangladesh patrol vessels completionProject completedCurrent financial year (FY24)
Electric ferry (West Bengal) deliveryVessel deliveredJanuary 2024
DRDO unmanned surface vessel deliveryVessel deliveredMarch 2024
P17 Alpha frigate deliveriesAll 3 ships deliveredMid-2025 to mid-2026
Rolls Royce license agreementCo-production agreement signedWithin one month
Oceanographic research vessel LOI conversionRs. 840 cr order finalizedNot specified; LOI received recently
Next Generation Corvette RFPRFP issuedTowards end of next calendar year (Q3 FY25)
Next Generation Destroyer RFPRFP issuedEarly to mid-2025

Key Metrics

MetricQ2 FY24
Revenue from operations₹897.97 cr, +32% YoY
Total income₹969 cr, +34% YoY
Profit after tax₹80.74 cr, +37% YoY
PAT margin8% to 8.99%, maintained; above 7.5% considered healthy
Order book₹23,739.59 cr as on 30 Sep 2023
P17 Alpha order outstanding₹13,132.46 cr
ASW Shallow Water Craft order outstanding₹5,319 cr
NGOPV order outstanding₹3,404 cr
Survey Vessel Large order outstanding₹1,291.79 cr
Ship repair order book₹80 cr
Bailey Bridges executed in FY24~₹60 cr; outstanding order book ~₹79 cr
Bank balance₹4,397 cr; owned fund ₹270 cr, project related fund ₹4,127 cr
Dock capacity utilization70% occupied, ~30% spare capacity maintained
P17 Alpha 1st ship physical progress>60%; 2nd ship 51%, 3rd ship crossed 40%
Survey Vessel Large 1st ship physical progress>90%; 2nd ship 76%, 3rd ship 66%, 4th ship 52%