Garden Reach Shipbuilders & Engineers Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/as-65bfb0bc76ce53189d7d88f1.pdf

Key Takeaways


Revenue Trajectory: Peak and Thaw

Hari: "So yes, it is a very natural process. There will be a thaw, and our peak is, as I have been reiterating in multiple interactive sessions that we had before, FY '26 and '27. So this is where we stand as of date."

Order Pipeline: The ₹1,72,000 cr Opportunity

Hari: "The P-17 Bravo order -- the best-case scenario is GRSE being the L1 shipyard, where the order value would be definitely plus INR 40,000 crores. And the worst-case scenario, okay, we could be the L2 shipyard. But as a strategy, we will be bidding to win this project, considering our experience of currently executing and completing the P-17 Alpha project successfully."

Capacity Strategy: No Order Left Behind

Hari: "This is the strategy that we intend to continue because we would not like to miss any order for want of capacity."

NGC: Margins and Revenue Mechanics

Hari: "In shipbuilding, as you are aware, the shipbuilding cycle forms a very peculiar revenue recognition pattern, unlike several other industries... typically, in a warship production cycle, the maximum revenue recognition occurs when the physical progress of construction hovers between 40% to 65%."

Indigenization and Supply Chain

Hari: "Interestingly, nearly 70% of our procurement is from MSMEs -- one of the highest in the segment."

Robotics and Operational Efficiency


Guidance & Commitments

CommitmentSpecificsTimeline
P-17 Alpha 3rd ship deliveryAll trials completed, ready for deliveryThis month (Nov 2024)
ASW SWC 6th vessel delivery5 of 8 delivered, 6th intendedNext week
ASW SWC project completionRemaining vessels deliveredFirst half of CY2027
NGOPV 4th vessel launch3 of 4 launchedEarly 2027 (Q4 FY27)
Concurrent construction capacityIncrease from 28 to 32 shipsBy end of this year (next month)
P-17 Bravo L1 declarationBid closing in a weekIn about four months (current FY)
P-17 Bravo contract conclusionConservative timeline of one year from L1Q4 FY28
Closed-bid RFP results (~₹25,000 cr)Interceptor Boats, Waterjet FACs, OPVsNext few months
Pipeline contract conclusionAll contracts from ~₹1,72,000 cr pipelineDuring next financial year
NGC first vessel delivery~9-year projectLatter half of CY2032
Ocean Research Vessel deliveryMaturing projectEnd 2027
Acoustic Research Ship deliveryMaturing projectH1 CY2028
Coastal Research Vessels completionKeel laying completed, first vessel launchedFY29
Bangladesh dredger deliveryFinal outfitting commencedApril 2027
West coast and east coast expansion projectsBoard approval given, not part of clustersCompletion in 3.5 to 4 years
Revenue trajectoryPeak in FY26 and FY27, thaw thereafterFY28 onward
NGC revenue pickupSubstantial contributionFY29

Key Metrics

MetricQ2 FY27
Revenue from operations₹1,827 cr, up ~9% YoY from ₹1,677 cr
Profit after tax₹172 cr, up 12% YoY from ₹154 cr
H1 FY27 revenue from operations₹3,641 cr, up 26% YoY from ₹2,987 cr
H1 FY27 profit after tax₹345 cr, up 26% YoY from ₹274 cr
Order book (as of Sep 30)₹12,977.93 cr; with NGC contract, current order book ~₹44,846 cr
Order book composition (as of Sep 30)Shipbuilding ~96%; defense segment 70%, non-defense ~29%
Next Generation Corvette contract value₹32,000 cr+, contract signed Nov 2; ~9-year project
Current shipbuilding capacity28 platforms concurrent construction; moving to 32 platforms within a month
NGC first vessel delivery timelineLatter half of CY2032, then through 2035–36 for fifth vessel
NGC pre-production revenue recognition quantum~7.5% to 8% of project cost; moderate revenue recognition to commence from FY28
P-17 Alpha base and depot spares outstanding~₹1,700 cr, ~15% of project cost; ~10–12% of project cost remains post-delivery for ~1 year
Revenue CAGR (last few years)~20% to 25%
Warship indigenization content (last three completed projects)~85%
Commercial ship indigenization content (export)~40% to 45%
Procurement from MSMEs~70% of total procurement
P-17 Bravo best-case order value (GRSE as L1)₹40,000 cr+; L1 declaration expected in ~4 months, contract conclusion by Q4 FY28
Warship segment RFPs (closed + live)~₹1,72,000 cr approximately, across 7–8 projects
Raichak expansion project cost~₹2,900 cr; 200m dry dock, up to ~60,000 DWT commercial ships; completion in ~3.5–4 years