Garden Reach Shipbuilders & Engineers Ltd Q4 FY2022 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/des1c0hie4i4c79bpczy92vm.pdf

Key Takeaways


Execution & Financial Performance

Dash: "Our objective is not that other income. Our objective is only against the income from operating income because this is a manufacturing organization. Our main objective is our operating income."

Margin Dynamics & Material Cost Phasing

Hari: "Shipbuilding - in the industry of shipbuilding, I'm not talking about ship repair. In case of shipbuilding, the healthy profit margins are in the range of 7.5% to 8%. And as we have seen our own performance, this year, we have touched 10%."

Order Book & Pipeline Visibility

Hari: "Right now, the existing order book, excluding the next-generation OPVs will last us till FY27. And considering the build period of the next-generation OPVs, we will have orders in hand at least till 2029. And as I had mentioned, if the next-generation Corvette comes to us, it's a big project, ₹13,000 crore to ₹14,000 crore, that project will spill over up to 2032."

Project Milestones & Launch Calendar


Ship Repair & Diversification


Exports & International Orders

Hari: "We have identified certain countries having potential for exports, targeted these nations, and we already appointed the marketing representatives in these nations. And this is a long-term process. It's not that when we appoint an agent, the results will be immediate. We have to be patient."

Guidance & Commitments

CommitmentSpecificsTimeline
Revenue growth20-25% increase over FY22 (aspirational target)FY23
Peak executionFY23, FY24, FY25 to be peak years for current order book executionFY23-FY25
Next-gen OPV contractContract for 4 OPVs (~₹3,200 crore) to be concludedDuring FY23
Margin maintenanceMaintain similar PAT margins (~10% including other income)FY23, FY24, FY25 and beyond
Ship repair growthIncrease ship repair revenue ~10-15% every year after stabilizationFrom FY23 onward
Next-gen Corvette RFPRFP expected to be publishedThis year (FY23)
LPD RFPRFP expectedTowards end of current year or next year
P-17 Alpha second ship launchLaunch plannedJuly 2022
Guyana vessel launchLaunch planned15 June 2022
Bangladesh boats deliveryDelivery plannedBy August 2022

Key Metrics

MetricQ4 FY22
Revenue from operations (FY22)₹1,758 cr, highest ever, +54% YoY
Total income (FY22)₹1,918 cr, +45% YoY
PBT (FY22)₹257 cr, highest ever
PAT (FY22)₹190 cr, highest ever
PAT margin (FY22)10%, including other income
EBITDA growth (FY22)+24% YoY
EPS (FY22)₹16.55, up from ₹13.40, highest ever
Revenue per employee (FY22)₹98 lakh, up from ₹60 lakh YoY
Employee cost to VOP (FY22)16.61%, down from 23.78% YoY
Order book₹24,072 cr as of 31 Mar 2022
FY23 revenue growth target20%–25% increase over FY22, aspirational
Cost of materials as % of sales57% in Q4, up from 36% in the previous quarter
Operating profit (FY22)₹104 cr, up from ₹40 cr in FY21
Interest income drop (FY22)₹18 cr decline, rate fell from 4.7% to 4.2% on avg deposits of around ₹3,700 cr
Ship refits completed (FY22)4, 3 for Indian Coast Guard and 1 for Govt of Mauritius
Dry dock occupancy~90% during last 3 months