Highway Infrastructure Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/cmqq8wmijgbr3iiabxji5uh4.pdf

Key Takeaways


Geopolitical Impact & Traffic Recovery

Jain: "But on the Western Front, I still feel that substantially it will take some time to resume to what the earlier trend was because additionally a lot of factories were impacted and a lot of trade was impacted."

Toll Portfolio: Expansion & Mix

Jain: "The risk appetite and the understanding of some toll plazas on these large scale, people outside of this industry do not understand the risks involved."

EPC: Beverly Hills & Bid Strategy

Jain: "It is very important, there are thousands of contracts out there, millions and millions of rupees contracts, but it is important to say no to the ones you know which will not work."

Technology & AI Strategy

Jain: "It is just safe to say that technology will be the next forefront on how do we execute and manage our projects while our main core business will be infrastructure."

Financial Outlook & Seasonality

Mittal: "Actually, this won't have a significant impact on the full-year results because, based on past trends, we tend to hover around the break-even point during the first and second quarters, while seeing a rapid recovery in the third and fourth quarters."

Guidance & Commitments

CommitmentSpecificsTimeline
Western Front traffic recoverySubstantially resume to earlier trend, contingent on no new geopolitical developmentNo date; "will take some time"
Full-year impactNo significant impact on FY27 results due to H2 recoveryFY27
FY27 turnoverAlmost ₹850 crores: ₹700 crores toll, remainder EPCFY27
FY28 turnover₹1,200 croresFY28
Beverly Hills EPC contribution40–45% of EPC revenueNext 15–16 months
Technology announcementFormal disclosure of technology developments"Soon enough"
Larger sole EPC bidsBid for larger tenders on sole basis once PQ increases after executing pipeline projectsConditional on PQ increase
Eastern belt entryWest Bengal and Assam opportunities under researchNo date; "right opportunities in the right time"

Key Metrics

MetricQ1 FY27
Total income₹304.3 crores, +170.6% YoY
EBITDA₹4.8 crores
PAT₹1.1 crores
Order book₹778 crores as of June 30, 2026
Total work order including new wins₹900 crores, EPC almost ₹500 crores and the rest toll segment
FY27 targeted turnover₹850 crores, of which ₹700 crores targeted for toll and the rest for EPC
FY28 targeted turnover₹1,200 crores
EPC revenue realization expected in FY27₹150 crores from 24 executable projects
EPC revenue realization expected in FY28₹200 crores
New toll projects secured in Tamil Nadu₹120 crores
Kozhinjipatti toll plaza contract value₹28.7 crores on NH-44, Tamil Nadu
Krishnagiri-Thumbipadi toll operations LOA value₹80 crores on NH-44
Beverly Hills project value₹70 crores approx., execution timeline 15 to 16 months
Beverly Hills expected EPC revenue contribution40–45% of EPC revenue in the next 15 to 16 months
Bid-to-win ratio, toll25% to 30%
Bid-to-win ratio, EPC25% to 30%