Hindalco Industries Ltd Q3 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/1t681jn82gkl1p1bx1swwa8f.pdf

Key Takeaways


The Oswego Fire: Impact, Recovery & Insurance

Pai: "the next 6 to 8 months is our critical period, and I think that we will be out of the woods then."

Novelis: Cost Program, Bay Minette & Capital Structure

Ahuja: "had it been a situation where we were under these pricing conditions, had we been fully up and running, we would have seen some very, very nice impacts from the current metal prices and therefore the scrap spreads, but we are being impaired by that."

India Aluminum: Upstream Strength, Downstream Ramp-Up


Copper: Weak Quarter, Strong Rebound Expected


Balance Sheet & Leverage

Pai: "if we can or do get into trouble, we will take the decision so that the consol net debt to EBITDA does not go above 2. I think that is the best way I can answer."

ESG & Sustainability


Guidance & Commitments

CommitmentSpecificsTimeline
Oswego hot mill restartHot mill to start operationsLate Q1 FY27
Oswego volume recoveryOutage impact largely recoveredNext financial year
Novelis cost savings exit run rate$150 million annualizedFY26 exit
Novelis structural cost reduction$300 million cumulativeFY28 exit
Novelis long-term EBITDA per ton$600 per tonNo date; target intact
Bay Minette facility completion600 Kt greenfield rolling and recycling facilityThis year (second half for hot mill)
Consolidated net leverageMaintain around 2x; take decisions to prevent exceeding 2Ongoing
India capex~₹10,000 crore this year; ₹10,000–12,000 crore next yearFY26 and FY27
Renewable energy capacity522 MWFY26 end
Chakla coal mine box cutBox cut startApproximately April (first half FY27)
Precipitated hydrate facilityCommissioningQ1 FY27
Hedging~25% hedged at ~$3,000End of March
Copper Q4 EBITDA₹600 croreQ4 FY26
Additional Novelis debt raise$500 millionBetween now and mid-year
Bay Minette Phase 2 expansion0.6 to 0.12 crore tonsBy end of decade

Key Metrics

MetricQ3 FY26
Consolidated business segment EBITDA₹8,762 cr, up 6% YoY
Consolidated profit after tax₹2,049 cr, down 45% YoY; adjusted PAT (excluding exceptional items) ₹4,051 cr, up 8% YoY
Hindalco India business segment EBITDA₹5,660 cr, up 10% YoY
Hindalco India quarterly PAT₹3,581 cr (record), up 24% YoY
India Upstream Aluminum EBITDA₹4,832 cr, up 14% YoY
India Upstream Aluminum EBITDA per ton$1,572
India Upstream Aluminum EBITDA margin45%
India Downstream Aluminum shipments108 Kt, up 9% YoY
India Downstream Aluminum EBITDA₹233 cr, up 55% YoY
India Downstream Aluminum EBITDA per ton$241, up 35% YoY
Copper overall metal shipments122 Kt, up 1% YoY
Copper quarterly EBITDA₹595 cr, down 23% YoY
Novelis shipments881 Kt, down 3% YoY (adjusted for 72 Kt lower due to Oswego fires)
Novelis adjusted EBITDA$436 million, $495 per ton, up 22% YoY (excluding $54 million Oswego impact and $34 million tariffs)
Novelis FY26 exit cost savings run rate$150 million, raised from $125 million last quarter
Consolidated net debt to EBITDA1.73x at end-December 2025
India Upstream Aluminum shipments growth2% YoY
India Upstream Aluminum revenue growth6% YoY
Copper CCR volumes82 Kt, down 14% YoY
Hedging notional loss₹245 cr in Q3
FY27 hedging position21% hedged at $2,925 per ton
Q4 FY26 aluminum hedging64% on commodity at $2,807 per ton; 26% on currency at INR 88.18 per dollar
Q4 FY26 cost expectation~1% higher QoQ, driven by CP Coke
Q4 FY26 copper EBITDA guidance₹600 cr, comfortable
Q4 FY26 alumina sales expectation170 Kt to 180 Kt (Q3 was 160 Kt)
Novelis Q4 FY26 EBITDA impact from Oswego$60 million to $65 million
Novelis Q4 FY26 volume impact from Oswego~72 Kt net of mitigation
Novelis 3-year cost reduction goal$300 million by FY28 exit
Novelis long-term EBITDA per ton guidance$600 per ton
Bay Minette capacity600 Kt greenfield rolling and recycling facility
India CAPEX FY26~₹10,000 cr (₹8,000 cr plus ₹2,000 cr for Bandha Mine)
India CAPEX FY27 expectation₹10,000 cr to ₹12,000 cr
Net debt on India booksNegative ₹600 cr (net cash)
Novelis net debt~$6.2 billion
Novelis weighted average cost of debt~5.3%
Novelis cost of capitalMid-8s
AV Minerals equity infusion into Novelis$750 million in December 2025; additional $200 million upsized February 10, at SOFR plus 105 bps, 5-year tenure
Renewable energy capacity418 MW at quarter-end; target 522 MW by FY26 end
Aluminum specific GHG footprint19.11 tons CO2 per ton of aluminum produced
LTIFR0.22
Waste recycled or reused82% of total waste generated