Key Takeaways
- A quarter defined by operational setbacks, not value destruction: Dirok revenue collapsed to ₹21.17 crores from ₹67.74 crores on customer shutdowns and pricing disadvantage, while B-80 suffered a 45-day shutdown and a paraffin-clogged export line that still constrains output. Management frames both as temporary.
- B-80 is the story, and it is fragile: The field restarted on 16th August but only one of two wells is flowing, the export line is choked to ~60 barrels per hour against a 250-barrel design, and management needs 6–9 months to reach stabilized operations.
- Dirok's demand problem has a structural fix arriving late: Offtake improved from a two-thirds reduction in Q1 to a one-third reduction in Q2, but full normalization waits on the National Grid connection, now expected next financial year.
- Management declined to quantify the near term: No revenue projection, no Q2 production direction, no timeline for the second B-80 well, and no gas rate until wells are fully on production. The refusal to guide was explicit and repeated.
- What to watch next quarter: Whether B-80 reaches its first 400,000-barrel parcel in November, the pace of export line remediation after monsoon, and any firming of the Dirok National Grid connection date.
B-80 Operational Status & Constraints
- Production restarted, but throttled: The D2 well (the major gas producer) was opened yesterday and is producing about 1,000 barrels of oil per day. The D1 well is ready but cannot be started because the export line cannot handle more volume.
- The export line is the bottleneck: Paraffin (wax) from the crude set on pipe walls during the 4-month shutdown (July 14 to November 1). When pumping exceeded 70–80 barrels per hour, the line progressively choked down to 30 barrels. It has been cleaned to ~60 barrels through different processes, against a design capacity of 250 barrels per hour.
- Remediation plan: After monsoon (October/November), the company will flush the line to return to the original 250-barrel-per-hour position. Further studies are being carried out to reflect the line fully clean, and remedial work will happen as soon as a fair weather window is obtained.
- Marine system strengthening: FSO, SPM and export line will be strengthened from October to December. The under-buoy hose will be replaced with a new 10-meter hose, Acroflex is studying the mooring system to weather the worst cyclone, and spares are being procured for immediate replacement.
- Stabilization timeline is long and non-committal: Management stated it will take at least another 6 to 9 months to get the plant operating in stabilized mode, with small shutdowns during monsoon. When pressed, they added "we cannot exactly quote the timeline, as whichever the way I say I will be incorrect."
- Normalized production target: Management expects to cross a threshold where the revenue model reaches around $300,000 per day (both oil and gas), but declined to give a date.
- First oil parcel: The company expects to reach a parcel size of 400,000 barrels in about 45–50 days, with the first parcel expected in November. Refineries now prefer this larger size via Mjunction auction, and HOEC has shifted strategy from continuous offtake of 200,000 barrels to pumping out the balance.
- Future drilling deferred: HOEC wants 2 years of uninterrupted continuous production first, then will drill the 3rd, 4th and 5th wells together, expected around FY26–27.
- Strategic investor ruled out: Considering the value in the block, management does not want to bring any more investors into the block.
P. Elango: "In the overall, at least it will take about another 6 to 9 months to get the plant to be operated in a stabilized mode and that too during the monsoon there will be a small shutdown, small changes will take place and we cannot exactly quote the timeline, as whichever the way I say I will be incorrect."
Dirok: Demand Collapse & Recovery Path
- Q1 revenue collapse: Dirok revenue fell to ₹21.17 crores from ₹67.74 crores (down ₹46.57 crores) because many consumer plants were shut down. The damage was compounded by differential pricing: Oil India sells nominated gas at $6.5/MMBtu while HOEC's private price is above $7.5/MMBtu, so OIL's production gets first priority and HOEC's gas becomes the fallback.
- Customer status improving: About 50% of customers have come back except NEEPCO. NRL came back after a 73-day shutdown, BCPL will come back, but BVFCL has not yet returned.
- Q2 offtake improving: Offtake moved from a two-thirds reduction in Q1 to a one-third reduction in Q2. Full offtake is expected only after the National Grid connection, now expected in the next financial year (not this one).
- National Grid connectivity: Two lines are supposed to be connected by February and March 2024. The Northeast gas grid Phase 1 is expected to be completed in Q4 FY24 by a GAIL-led consortium, with the 256 km IGGL line and around 401 km UrjaGanga project opening a new market for Eastern region gas effective next financial year.
- Pipeline progress: Construction in the difficult forest segment has progressed significantly, with about 70% of work in the critical forest segment already completed. The 18-inch pipeline will transport Dirok gas to the Duliajan Marketing Hub independently. A portion of the line in the mountain area is completed and will tie to the Oil India line until the balance gets connected.
- Production ramp-up potential: Once connected to the National Grid, HOEC can ramp up production by drilling three more wells to reach 7 crore cubic feet per day. Until then, normalized offtake is expected at around 20 to 2.5 crore standard cubic feet per day.
- E-bidding strategy shift: HOEC is moving to a new e-bidding structure where 50% will be on a firm basis and 50% on fallback/take-or-pay basis, with floor and ceiling prices, to protect the revenue stream.
Management: "You have to understand there is a price, one guy, Oil India is selling at $6.5 and our price is more than $7.5, the first priority goes for the Oil India production, so unless the overall demand is picked up, we will not be able to offtake our gas."
Financial Performance
- Standalone profit collapse: Profit fell from ₹107.03 crores to ₹21.34 crores, driven by the Dirok revenue reduction of ₹46.57 crores and a stock adjustment impact.
- Stock adjustment hit: Stock adjustment credit fell from ₹36.7 crores to ₹27.7 crores due to price variation (price per barrel dropped from 78.54 to 70.93) and quantity variation of about ₹5.27 crores.
- Operating cost base effect: Standalone operating expenses rose to ₹79.12 crores from ₹43.72 crores, but this was mainly because Q4 FY23 had a downward adjustment of ₹28.92 crores on MOPU and FSO revenue from a commercial settlement, which correspondingly reduced B-80 costs in that quarter. Normalized cost remains $140,000 per day.
- Consolidated EBITDA decline: EBITDA fell to ₹96.86 crores from ₹139.84 crores, mainly due to poor offtake by consumers and the sales revenue reduction of ₹46.57 crores.
- B-80 production volume correction: The previous quarter's reported 16 MMSCFD was an averaging error: 194 days of operation were divided by 194 days instead of 365 days. The correct number is 12 MMSCFD.
- Management declined all forward quantification: No revenue projections, no Q2 production direction versus Q1, no B-80 revenue projection at current prices, and no gas production rate until wells are fully on production.
Portfolio Updates & Drilling Plans
- Geoenpro acquisition: HOEC's subsidiary acquired the balance 50% share capital of Geoenpro Petroleum Limited at a cost of ₹50 crores, making Geoenpro a subsidiary. This increased participating interest in the Kharsang Oil Field to 35% both directly and indirectly, with operator rights.
- Kharsang PSC extension: The PSC addendum for 10 years and the mining lease have already been extended.
- Kharsang drilling plans: Plan to drill new wells to enhance production and authorize deeper formation by drilling to a depth of about 3,000 meters, after obtaining consent from JV partners. Reevaluation will take at least six months, then convincing the partner and drilling would take about one year.[10-11]
- PY-1 drilling timeline: Seismic processing studies are in progress for fine-tuning new well location. After reprocessing interpretation, HOEC plans to get a third-party specialist opinion before drilling. If everything goes as per plan, drilling will commence in Q2 of FY25. Initial capital of ~₹70 crores will come from internal accruals; total is less than ₹100 crores and manageable internally.
- Cambay drilling: Awaiting environmental clearance to drill two wells each in Asjol and North Balol in a single campaign. The possibility of increasing the number of wells will be decided after drilling the above wells for quick monetization. Associated natural gas that was previously flared is now being sold, achieving zero flaring.
- Seismic reprocessing underway: Being carried out in PY-1, Dirok, Block 19, and B-80 (raw 3D seismic data). On completion, HOEC will embark on PY-1 redevelopment. The Dirok geological model is also under review, with preliminary assessment indicating upside potential.
- Kherem block discontinuation: No one-time write-off; the very small expenditure has already been charged out.
Leadership Transition & Organizational Changes
- MD transition: The Board appointed Mr. Jeevanandam as Managing Director effective 1st October, as P. Elango retires on 30th September after 40 years in oil and gas. Mr. Elango stated he will remain a shareholder and be available on call.
- CFO appointment: An appointment order has been given to a gentleman; he will join once he accepts the order.
- B-80 operating team strengthening: In the last couple of months, HOEC has added people with relevant experience and is recruiting more people and consultants for the operating team. The contractor Expro has reached an amicable settlement and is embarking on rectifying most things; there is no intention of changing the contractor immediately.
Mr. Elango: "Now when I began my career, one of the important principles that I at least follow is while every employee is valuable, no one is indispensable. That's the principle under which you need to operate a company."
Disclosure & Communication Approach
- B-80 shutdown not disclosed as material event: When asked why the 45-day B-80 shutdown was not disclosed, management answered that the job was expected to be completed within 6–7 days, and that they would inform the market immediately only if there were permanent damage of value to the company, such as wells not flowing or being impossible to open.
- Repeated refusal to guide: Management declined to provide revenue projections, Q2 production direction, B-80 gas rates, or a timeline for the second well restart, stating in each case that any number would be incorrect or that stabilization must come first.
- Production loss characterized as temporary: Management framed the production volatility as "temporary phenomena" that do not change the underlying value of the company, which is in "continuously increasing mode."
Management: "If you are going for a value degradation, suppose the wells are not flowing, the wells are not possible to open, there is a permanent damage of value to the company, then we will come back to the market and inform immediately."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| B-80 stabilized operations | Plant operating in stabilized mode | 6–9 months (no firm date) |
| B-80 first oil parcel | Reach 400,000-barrel parcel size | ~45–50 days; November |
| B-80 export line remediation | Flush line to return to 250 barrels per hour | After monsoon (October/November) |
| B-80 marine system strengthening | Replace under-buoy hose, study mooring, procure spares | October–December |
| B-80 future drilling | Drill 3rd, 4th and 5th wells together | After 2 years uninterrupted production (~FY26–27) |
| Dirok National Grid connection | Northeast gas grid Phase 1 and UrjaGanga project completion | Next financial year (FY25) |
| Dirok pipeline construction | 18-inch independent pipeline to Duliajan | 70% of critical forest segment complete; no final date |
| Kharsang drilling | Drill new wells to 3,000 meters after JV consent | ~18 months (6 months reevaluation + 1 year drilling) |
| PY-1 drilling | Drill exploration well after seismic reprocessing and third-party review | Q2 FY25 |
| Cambay drilling | Drill two wells each in Asjol and North Balol | After environmental clearance (no date) |
Key Metrics
| Metric | Q1 FY24 |
|---|---|
| Standalone revenue | ₹108.69 cr, down from ₹158.78 cr in Q4 FY23 |
| Consolidated revenue | ₹187.14 cr, down from ₹193.39 cr in Q4 FY23 |
| Standalone profit after tax | ₹21.34 cr, down from ₹107.03 cr in Q4 FY23 |
| Consolidated profit after tax | ₹66 cr, down from ₹106 cr in Q4 FY23 |
| Consolidated EBITDA | ₹96.86 cr, down from ₹139.84 cr in Q4 FY23 |
| Standalone operating expenses | ₹79.12 cr (incl. stock adjustment), up from ₹43.72 cr in Q4 FY23 |
| Consolidated operating expenses | ₹106.68 cr, up from ₹69.35 cr in Q4 FY23 |
| B-80 block revenue | ₹83.44 cr, down from ₹86.57 cr in Q4 FY23 |
| Dirok block revenue | ₹21.17 cr, down from ₹67.74 cr in Q4 FY23 |
| Dirok average gas production | 10.24 MMSCFD and 187 barrels of condensate per day, vs 29.9 MMSCFD and 577 barrels of oil in Q4 FY23 |
| B-80 oil in stock (FSO) | 2,92,000 barrels as of 30 Jun 2023, up from 1,87,000 barrels as of 31 Mar 2023 |
| Outstanding loans (standalone) | ₹137 cr; subsidiary books: ₹86 cr |
| Bank loan rating obtained | ₹500 cr from India Ratings |
| Kharsang block acquisition cost | ₹50 cr for balance 50% of Geoenpro, making it a subsidiary |
| Kharsang current production | ~350 barrels per day |
| B-80 normalized daily operating cost | $140,000 per day (standalone) |
| Dirok offtake July–August | 18–20 MMSCFD per day |
| B-80 production after restart | ~1,000 barrels per day from one well (D2) |