Hindustan Oil Exploration Company Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/kc6r8mdamie8t59nnhjzvmf5.pdf

Key Takeaways


B-80: The Core Asset in Repair

Mishra: "We believe our 2P reserves are still there, 2.6 crore, of which 0.15-0.2 crore has been produced so far. So there are reserves to be produced."

Dirok: The Nearest Catalyst

Mishra: "There isn't a reservoir in India, and in large parts of the world, where your production header pressure from six wells is 3,000 PSI. That speaks to the prospectivity of this reservoir."

PY-1: Drilling Now Conditional on Gas Buyers

Mishra: "So this time, we are trying to get it right. As far as possible, we'll have a take-or-pay agreement either with GAIL or with IOCL and only then we will spud the wells."

Kharsang & Cambay: The Working Assets

Mishra: "The problem remains that if we find gas, then we don't have a buyer and in fact, we have found virgin gas in two of the wells in Kharsang. That's a good problem to have, but the only thing is it delays the monetization of reserves because we don't have a pipeline."

Financials & Funding

Mishra: "Now how much? I would put my number to around 7% to 10%, but please don't take it as a guidance."

HPCL Relationship & Crude Sales

Mishra: "We would like to preserve it and keep it that way rather than having double barrel guns at each other and fighting."

Guidance & Commitments

CommitmentSpecificsTimeline
B-80 workoversTwo existing wells (D1 and D2) worked over, water zones shut off, new zones openedRig award this month; mobilization by October; production by November–December 2026
B-80 drillingThree wells brought on productionBy June of next year
B-80 crude inventory clearanceEntire crude inventory cleared from HPCL refinery in Chembur, MumbaiEnd of October / early November
Dirok pipeline completionDNPL line tied back, hot taps completed by AGCLDecember
PY-1 drillingTwo new wells spudded only after take-or-pay agreement with GAIL or IOCLContingent on gas sales agreement; no date
Kharsang second phase drillingNine wells drilled; rig identified, tubulars orderedAward imminent; tubulars in one to two months
Kharsang pipeline24-km pipeline laid, tied into Oil India line at Bordumsa6–8 months for right of way, 6–8 months to lay; ideal completion December 2027
Cambay production increase20%–30% increase from Cambay assetsGoing forward; no specific date
B-15 drillingFDP under preparation; drilling plannedFY28
Asset-wise realization disclosureOffshore and onshore realizations reported separatelyNext presentation

Key Metrics

MetricQ1 FY27
Standalone revenue from operations₹117.5 cr, compared with negative ₹194 cr in Q4 FY26
Net standalone revenue₹107.6 cr, after profit petroleum and revenue share of ₹9.83 cr
Consolidated revenue from operations₹124 cr, net consolidated revenue of ₹114.17 cr after profit petroleum and revenue share
Standalone profit before tax and exceptional items₹12.54 cr, compared with ₹30.4 cr in Q4 FY26
Consolidated profit before tax and exceptional items₹6.5 cr, compared with ₹9.01 cr in Q4 FY26
Other income₹19.37 cr standalone, ₹20 cr consolidated
Standalone total expenses₹114 cr, including depletion of ₹51 cr, royalty and statutory dues of ₹13 cr, stock adjustments of ₹41 cr
Consolidated total expenses₹128 cr, including depletion of ₹58 cr, royalty/cess/statutory dues of ₹15 cr, stock adjustments of ₹41 cr
Kharsang production17,400 BOE, up from approximately 12,300 barrels of oil in Q4 FY26
Average crude and condensate realization$95.5 per barrel, compared with approximately $70.8 per barrel in Q4 FY26, standalone
Average gas price realization$12 per MMBTU, compared with $9.8 per MMBTU in Q4 FY26
B-80 gas realization$16.5 per MMBTU average, approximately $15–16 per MMBTU on the exchange
Dirok gas realization$12.5 per MMBTU average, pegged at $10–12 per MMBTU
B-80 crude inventory soldRoughly 15% sold as of the call, with losses incurred of ₹4–6 cr so far
B-80 2P reserves2.6 crore barrels, of which 0.15–0.2 crore has been produced so far
Gearing0.04, with ₹20 cr bank loan as the only debt on the books
DNPL pipeline capacity0.25 crore standard cubic meters per day target at 90 bar, up from current degraded capacity of 1–1.5 MMSCMD
Dirok production capability utilization50%–70% of capability from existing well stock due to lack of evacuation route
B-80 workover target500 to 800 barrels per well, and 3 to 0.5 crore scuffs per day from worked-over wells
B-80 new well production range1,000 to 1,500 barrels per well, could be 700 or 1,400 based on reservoir models
PY-1 new well potential1.5 to 2 crore standard cubic feet per day from two new wells, per PetroVietnam analysis
Kharsang gas pipeline timeline14 to 18 months total, 6 to 8 months for right of way plus 6 to 8 months to lay 24 km pipeline
Cambay production increase expected20% to 30% going forward, with 5% to 6% increase already seen in Q4 FY26