Key Takeaways
- Production hit by external shocks, not the reservoir: Dirok gas offtake halved as floods shut four major customer plants for weeks, while B-80 lost 35 days to hawser repair. Both issues are resolved, and management expects a sharp Q4 rebound.
- The grid unlock is now dated, not just promised: GAIL connection to Guwahati by December, DNPL line by March '25, and IGGL by year-end. Once connected, Dirok offtake can jump from ~13 mmscfd to 40+ mmscfd, a 3x volume lever on largely fixed costs.
- B-80 pricing pivot is working: The shift to selling >50% of gas at exchange prices linked to LNG (vs. a Brent percentage) is delivering better realizations right now, and three new wells in FY26-27 target a 40% production uplift to >3,500 boepd.
- A new offshore growth vector is taking shape: HOEC declared sole bidder for the B-15 Mumbai Offshore block, targeting production in <30 months, and is advancing PY-1 drilling plans for mid-2025. Both add material resource optionality beyond the current producing assets.
- What to watch next quarter: Whether the December GAIL connection actually lifts Dirok offtake to the promised 25+ mmscfd, the pace of B-80 crude stock drawdown, and formal award of the B-15 block.
Dirok: The Grid Unlock Thesis
- Q2 was a demand shock, not a well problem: Dirok workover successfully increased production from wells 1 and 2, but offtake collapsed from 2.27 crore scf/day to 1.5 crore scf/day because four major consumer plants shut down: Numaligarh refinery (19 days), Brahmaputra Fertilizer (~28 days), Namrup thermal (24 days), and NECO (~61 days). The root cause was flooding in Assam, not any reservoir or productivity issue.
- Price stacking works against Dirok today: Gas from nominated blocks (OIL/ONGC) at a US$6.5 ceiling is sold first; Dirok JV gas at the PPAC price of ~US$8.2 gets only residual demand. This structural disadvantage persists until grid connectivity gives Dirok access to buyers beyond the local pool.
- The connections are now sequenced: GAIL line to Guwahati expected by December; DNPL connection by March '25; IGGL line (Numaligarh to Duliajan) by year-end. Once the first layer of national grid connections is in place by 31st March 2025, management expects "better offtake from FY25-26."
- Volume ramp is a fixed-cost leverage story: Dirok costs are largely fixed: at low volumes cost runs ~$1/mmbtu, but at full volume of 40-45 mmscfd it would drop to $0.5-$0.6/mmbtu. After the DNPL connection in March '25, management expects to reach above 40 mmscfd, and after the December connection, at least 25+ mmscfd (a 50%+ improvement from the current ~13).
- Q3/Q4 trajectory: Management expects Q3 to be "a little better" and Q4 "much better than Q3," based on discussions with Oil India. The majority of the closed Assam factories restarted in October, with only BBSL still down but expected back the following week.
Jeevanandam: "We are expecting the DNPL line will get connected in March '25. So with that, we will be able to increase our offtake, that's what we believe."
B-80: Pricing Shift and Production Reset
- Hawser repair cost 35 days of production: Both wells were shut in for over 35 days for repair and replacement of the hawser, dropping oil production to 58,906 barrels (vs. 67,351 last quarter) and gas to 0.38 bcf (vs. 0.4 bcf). Both wells are now back on production.
- Gas price softened but the mix improved: Realized gas price fell from US$10.34 to US$9.89 per mmbtu quarter-on-quarter. However, management has shifted the sales mix: more than 50% of gas is now sold at exchange prices linked to LNG (with a small discount), which is "much better than the percentage on Brent at the moment." The prior model was 22% of Brent, now down to 12.2% on the remaining volume.
- Crude quality supports Brent parity: B-80 crude is equivalent to Brent based on analysis and receives Brent pricing. The quarter's EBITDA and PAT took a hit from an NRV reduction in crude stock as oil prices moved from US$82.55 to US$73.69 per barrel.
- Three-well program targets 40% uplift: Management plans to drill three additional wells in FY26-27 at a capex of $50-$60 million, aiming to ramp production from the current ~2,500 boepd to >3,500 boepd. The gas decline observed is from a gas-top well where earlier years were naturally higher; additional wells will bring the block back to optimum potential using existing facilities.
- Economics are robust at the low end: With government revenue share (minimum 12% plus royalty ~10%, totaling ~25-30% of revenues) and owned facilities (FPSO, MOPU), the block's breakeven sits at US$50 oil.
- Stock drawdown coming: Management expects to draw down the current ~250,000 barrels of crude stock by Q1 FY26.
Jeevanandam: "If you take the net cost of all those things we can sustain even at an oil price of $50."
New Ventures: Offshore and Exploration Optionality
- B-15 Mumbai Offshore, sole bidder: HOEC bid for Block B15 (332.4 sq km, water depth ~40 feet) in the DSF Special Bid Round 2024 and was declared the sole bidder. Management expects formal award and PSC signature within a month. The target is to put the block on production in less than 30 months, using a cost-optimized model that may involve additional borrowing.
- PY-1 offshore drilling mid-2025: The company plans to engage experts in basement reserves from Vietnam to review the study and reserve estimations. If studies proceed as planned, drilling of the first well will commence between April and June 2025.
- Cambay blocks finally moving: Environmental clearance was secured after four years for North Balol and Asjol. The company is securing a rig and tangibles to commence drilling two wells in North Balol, followed by Asjol. Final clearance of the ring-fenced R2 PSC is awaited for signature.
- Kharsang exploration well: Public hearing for environmental clearance is scheduled for November 26, 2024. On obtaining EC, the plan is to drill one exploration well to ~4,000 meters, with a broader plan to drill 18 wells for the Upper Girujan formation.
- North Dirok (ND-1): Assam PCB approval has been received to drill the ND-1 well up to the Barail formation.
- Block 19 (Greater Dirok): Extension granted up to February 1, 2025, with a request to MoP&NG for one more year. After the rainy season and harvest, construction of the approach road and drill pad will begin.
Jeevanandam: "We are an offshore operator, we are the only company producing from Mumbai High, other than ONGC. So we are very proud of it, we are comfortable doing a good job, and we will be able to do it."
Financial Position and Capital Allocation
- Standalone revenue and EBITDA declined on lower Dirok offtake and the B-80 crude stock NRV reduction. Consolidated expense movement was driven primarily by the crude stock price change in B-80.
- Cash position covers the plan: With current cash and continued production, management states it will meet all obligations including the planned capital program for the coming three years. India Ratings reaffirmed the IND A rating and revised the outlook from 'Stable' to 'Positive' for the ₹500 crores bank loan.
- Capex envelope: ₹250 crores allocated for the North-Eastern region over the next two financial years. The B-80 three-well program carries a separate $50-$60 million budget for FY26-27. Additional borrowing may be considered for B-15 development after PSC signing.
- Revenue ambition: Management's endeavor is to "comfortably reach" ₹1,000 crores revenue in FY25-26, with EBITDA margins expected to be "a little better" than current levels by leveraging fixed costs. The company is on target for a 50% uptake in production in fiscal 25, though the timing may slip by a couple of months.
- No management stake sale: Management stated there has been no stake sale by the promoter group in the recent past, noting that any transaction above 5% would require exchange disclosure.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Dirok offtake improvement | At least 25+ mmscfd (50%+ above current ~13) after GAIL connection; above 40 mmscfd after DNPL connection | GAIL: Dec '24; DNPL: Mar '25 |
| First-layer national grid connectivity | Better offtake from Dirok once connected | By 31st March 2025 |
| B-80 crude stock drawdown | Draw down current ~250,000 barrels | By Q1 FY26 |
| B-80 production ramp | Three additional wells, ramp from ~2,500 to >3,500 boepd; capex $50-$60 mn | FY26-27 |
| B-15 offshore block | Put on production in <30 months from PSC signing | PSC expected within a month; production <30 months thereafter |
| PY-1 offshore drilling | First well spud | April-June 2025 |
| Cambay drilling | Two wells in North Balol, followed by Asjol | After rig and tangibles secured (underway) |
| Revenue target | "Comfortably reach" ₹1,000 crores | FY25-26 |
| Production uptake | 50% increase in production | Fiscal 25 (may slip a couple of months) |
| Kharsang exploration well | One well to ~4,000 meters | After EC (public hearing Nov 26, 2024) |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Consolidated revenue from operations | ₹100 crores, compared to ₹143.41 crores in the previous quarter |
| Standalone revenue | ₹51.85 crores, compared to ₹71.79 crores in the previous quarter |
| Consolidated EBITDA | ₹36.47 crores, compared to ₹72.98 crores in the previous quarter |
| Standalone EBITDA | ₹9.73 crores, compared to ₹20.97 crores in the previous quarter |
| Consolidated profit before tax | ₹13.41 crores, compared to ₹48.5 crores in the previous quarter |
| Consolidated profit after tax | ₹10.81 crores, compared to ₹41.92 crores in the previous quarter (previous quarter included exceptional items) |
| Standalone profit after tax | ₹1.11 crore, compared to ₹11.39 crores in the previous quarter |
| Dirok gas sales volume (HOEC share) | 0.37 bcf, compared to 0.5 bcf in the previous quarter |
| Dirok condensate sold | 5,858 barrels, compared to 10,578 barrels in the previous quarter |
| Dirok gas price realized | US$8.2 per mmbtu (PPAC price), compared to OIL/ONGC nominated block ceiling of US$6.5 per mmbtu |
| B-80 oil production | 58,906 barrels, compared to 67,351 barrels in the previous quarter |
| B-80 gas production | 0.38 bcf, compared to about 0.4 bcf in the previous quarter |
| B-80 average gas price realized | US$9.89 per mmbtu, compared to US$10.34 per mmbtu in the previous quarter |
| B-80 crude oil inventory | 250,000 barrels (approximately) |
| B-80 current production rate | ~2,500 boepd (within +/-5% of reference production) |
| Term loan outstanding | ₹103 crores |
| India Ratings bank loan rating | IND A, outlook revised from 'Stable' to 'Positive' for ₹500 crores bank loan |
| North-Eastern region planned capital outlay (next two financial years) | ₹250 crores |
| B-80 planned three-well CAPEX | $50 to $60 million |
| B-80 breakeven oil price | $50 per barrel (management estimate) |
| B-80 government revenue share | ~25% to 30% of revenues (12% minimum plus royalty of ~10%, actual revenue share expected ~17% to 18%) |
| Dirok operating cost at full volume | US$0.5 to US$0.6 per mmbtu; at current lower volume approximately US$1 per mmbtu |
| B-15 target time to production | Less than 30 months from award |