Hindustan Oil Exploration Company Ltd Q4 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/pv7kbzka621u9vt9n3d09ywi.pdf

Key Takeaways


B-80: The Wax Problem and the Recovery Plan

Jeevanandam: "We are not worrying too much about the below-the-ground reserves. And above-the-ground facilities are hammering us, which we are trying to solve one by one." [10-11]

Dirok: Demand-Starved, Waiting for the Grid

Jeevanandam: "Though this field can produce about 5 crore standard cubic feet per day, we have to restrict the production due to lack of demand."

The Drilling Program: A Three-Year, ~₹1,000 Crore Bet

Jeevanandam: "To be abundantly cautious, you know the status, you know what has happened in the block in the past, we don't want to repeat it."

Margins: Volume-Levered and Currently Squeezed

Jeevanandam: "Luckily, we have got the MOPU and FSO is owned by HOEC subsidiaries. If it is some third-party contractor, B-80 wouldn't have been there at all."

Reserves and Resource Growth

Jeevanandam: "We don't want to create a sensation into it, because the reserves are upgraded. We wanted to make it as an annual exercise, and we will give it in the balance sheet as such."

Guidance & Commitments

CommitmentSpecificsTimeline
B-80 flow line cleanupSteam-cleaning shutdown of 7–10 days; both wells tested for sustained flow afterwardImminent (equipment on board)
B-80 wax management routineContinuous chemical injection; cleaning repeated once every three monthsOngoing from cleanup completion
Dirok gas grid connectionConnection to North-east Gas Grid, enabling production ramp to 6–7 crore scf/dayWithin six months
Dirok workover programDirok-1 workover underway; Dirok-2 and Dirok-4 to follow; two additional producers plannedSequential, no end-date given
Kharsang drilling15 development wells + 1 exploration well; starts immediately on environmental clearancePending EC (delayed, no date)
Cambay drillingTwo wells each in Asjol and North BalolPending EC (expected June 2024)
Block-19 exploration wellOne well with seven seismic signatures; 1-in-5 chance of successOn RSC extension registration
PY-1 first development wellFirst of three wells; subsea tie-back to existing infrastructureJune 2025
B-80 additional drillingThree more wells to fully exploit the block; ~$50 million expenditure2027-28
Capex fundingAll capital expenditure through internal accruals; no further borrowingsOngoing
Reserve disclosureUpdated reserves in annual report; no interim updatesAnnually

Key Metrics

MetricQ4 FY24
Consolidated revenue₹330 cr, vs ₹193 cr in Q3 FY24
Standalone revenue₹254 cr, vs ₹109 cr in Q3 FY24
Consolidated EBITDA₹77.67 cr, vs ₹80.14 cr in Q3 FY24
Standalone EBITDA₹29.45 cr, vs ₹16.74 cr in Q3 FY24
Consolidated PAT₹70.61 cr, vs ₹40.57 cr in Q3 FY24; includes exceptional item of ₹32.87 cr from GeoEnpro fair value adjustment
Standalone PAT₹19.1 cr, vs ₹4.82 cr in Q3 FY24
B-80 crude realizationUS$80.27 per barrel
B-80 gas price renegotiated12.2% of Brent, down from ~22% previously; duration about one year
Dirok gas price realized (PPAC)8.82 per MMBTU; May 2024 PPAC price 8.9 per MMBTU
B-80 production (oil)83,000 barrels, vs 95,000 barrels in Q3 FY24; reduction due to export flowline blockage
B-80 production (gas)0.32 BCF, vs 0.45 BCF in Q3 FY24
Dirok gas sales0.55 BCF, vs 0.59 BCF in Q3 FY24
Dirok condensate sales10,917 barrels, vs 10,841 barrels in Q3 FY24
B-80 revenue₹203.57 cr, vs ₹48.43 cr in Q3 FY24; includes oil sales of ₹172.42 cr
Dirok revenue₹47 cr, vs ₹57 cr in Q3 FY24
Standalone field operating expenses₹67.93 cr, vs ₹76.23 cr in Q3 FY24
Consolidated total operating costs₹241.54 cr, vs ₹137.2 cr in Q3 FY24
Value in stock in FSO₹33 cr as on 31st March 2024, vs ₹73 cr previous year
Outstanding loan (standalone)₹75 cr as on 31st May 2024; company repaid ₹242 cr in FY24
Outstanding loan (subsidiary)₹58 cr as on 31st May 2024
B-80 facility uptime86% in FY24, improved from 60% in FY23
B-80 first offloading430,000 barrels of oil sold; total revenue of ₹287.37 cr realized in Q1 FY25
Revenue share paid to GoI for B-80₹160.5 cr cumulative as on 31st March 2024
Royalty paid to GoI₹88.53 cr cumulative as on 31st March 2024
Capital program planned₹1,000 cr over next 3 years; annual exposure roughly ₹300 cr per annum
Eastern region capex (next 2 years)₹250 cr, further added if sustained gas demand
B-80 additional development wells3 wells planned, expenditure about $50 million; five-well production expected by FY28
B-80 target production (post-cleanup)2,500–3,000 BOE per day wishful projection
Dirok potential production capacity5 crore standard cubic feet per day, restricted by lack of demand
PY-1 drilling plan3 development wells; first well planned June 2025
PY-1 evacuation capacity5.5 crore cubic feet per day of gas and ~2,000 barrels of condensate; current wells produce only ~0.1 crore cubic feet
Kharsang drilling plan15 wells in Upper Girujan plus 1 exploration well for deeper formations
B-80 Q1 FY25 operational days~25 days on production in the last month of Q4; 91 days total except ~5 days intermittent shutdown
B-80 export flowline flush rate<40 barrels per hour currently; previously reached 162 barrels per hour after flushing
Dirok net revenue before finance cost (FY24)₹117 cr, down from ₹191 cr in FY23; lost ~₹73 cr YoY
B-80 revenue (FY24)₹259–260 cr, up from ₹175 cr in FY23
Dirok revenue (FY24)₹161 cr, down from ₹250 cr in FY23
Consolidated revenue (FY24)₹830.27 cr, vs ₹592.2 cr in FY23
Consolidated EBITDA (FY24)₹326.82 cr, vs ₹320.98 cr in FY23
Consolidated PAT (FY24)₹226.43 cr, vs ₹194 cr in FY23
Standalone revenue (FY24)₹544.28 cr, vs ₹411.1 cr in FY23
Standalone EBITDA (FY24)₹133.05 cr, vs ₹223.17 cr in FY23
Standalone PAT (FY24)₹84 cr, vs ₹163 cr in FY23
B-80 production (FY24)320,887 barrels of oil and 2.13 BCF of gas
Dirok production (FY24)1.95 BCF of gas and 36,618 barrels of condensate
HOEC participating interest in B-8060%
HOEC participating interest in PY-321%
GeoEnpro group participating interest in Kharsang35%
Credit rating'A' stable for ₹500 cr bank loan from India Rating
Reserve life estimate15–20 years minimum