Key Takeaways
- A pivotal quarter, but execution is everything: Management framed FY26 as an inflection point, yet the quarter was defined by delayed workovers, a crude sale reversal, and infrastructure bottlenecks. The production ramp-up story is intact on paper but unproven on the ground.
- The HPCL reversal consumed the quarter: An invoice reversal on a crude sale tied up INR260 crores in working capital, delaying the B-80 workover program and forcing a slow, discounted resale to third-party buyers.
- A bold 3-year production target now hangs on multiple dependencies: Management laid out a path to 32,000 boe/day by 2029, but the near-term step to 10,000-11,000 boe/day by June 2026 requires rigs in a tight market, pipeline connections not yet complete, and financing not yet arranged.
- The Dirok gas story is a call option on infrastructure: Production is choked to a fraction of potential, and while all stakeholders are now talking, management cannot put a date on when the evacuation pipeline will be available or how capacity will be shared.
- What to watch next quarter: Whether the 55-km pipeline connection is physically completed, the pace of the HPCL crude liquidation and any associated loss, and the concrete capex and debt plan management promised to share.
The HPCL Crude Sale Disruption
- What happened: A crude sale to HPCL was canceled by mutual agreement, the invoice reversed, and a credit note issued. The crude, still stored at HPCL's refinery, is now being sold to third-party buyers on an "as is where is" basis, with trucks picking up weekly against advance payments.
- The working capital hit: INR260 crores was tied up in invoices for crude sales, a constraint management directly cited as the reason the B-80 workover of two subsea wells was delayed from last quarter. The workover is now pushed to post-monsoon.
- Pricing and realization risk: The resold crude was initially sold at a firm price, then linked to Brent minus a confidential discount. Management said the price is "almost near" the original HPCL sale price, but the final outcome, including any loss, will only be known in 2-3 months when all crude is sold. Buyers are also bearing additional diesel and transportation costs, a pain point management acknowledged could "show up in some costs."
- No compensation, conciliation pending: No further commercial interaction with HPCL; a conciliation process per the COSA will happen in the next few months, with the outcome uncertain.
- Inventory valuation: Inventory was valued at a discount to Brent, which management said covers the downside risk, with a "reasonable expectation of value" for the crude.
Baroruchi Mishra: "Realize though that the buyers are going through a situation where they're not getting diesel and transportation trucks, etcetera. So, there is a level of pain in that exercise also, which might show up in some costs, etcetera, which we'll have to talk about."
Production Ramp-Up: The Plan vs. The Dependencies
- The headline target: Management aims for 10,000-11,000 boe/day by June 2026, 22,000 by 2028, and 32,000 by 2029, backed by a 20-well drilling campaign across multiple assets. The "line of sight" is "definitely above 8,000 barrels," with a plan to reach 11,000.
- B-80 (offshore oil): The flagship asset, targeting 4,000-5,000 bbl/day if all work is completed by June. The program includes workovers on two existing subsea wells (delayed, now post-monsoon), three additional development wells, production optimization via suction pressure reduction, reservoir management improvements, and facility debottlenecking. Core infrastructure is already in place.
- PY-1 (offshore gas): A two-decade-old development project with significant redevelopment potential. Targeting 1.2-1.5 crore SCF/day via new wells, reservoir activation, and production optimization. PetroVietnam was engaged to assess remaining potential from the basement reservoir, with positive results. One exploration well and two firm development wells are planned, with a fourth contingent on results.
- Kharsang (onshore): The largest medium-term growth opportunity. Production has already doubled after nine wells; nine more are planned, which management expects will double production again from the current 700-plus barrels. Significant gas was discovered, but evacuation needs to be figured out.
- The rig and financing overhang: Rigs are in short supply globally due to high oil prices. Management acknowledged the risk of drilling timeline delays but declined to quantify it, saying only "we'll go full prepared with all uncertainties." Financing for the capex program is not yet arranged; management is looking at internal accruals and bank facilities and will provide a concrete plan next quarter.
Baroruchi Mishra: "I'm not differentiating it here that the date of 31st of March 2027 because that is not how the oil and gas fields work. I'm trying to tell you before June of 2026 because the drilling goes on all the way up to May – June of the next year."
The Dirok Gas Bottleneck
- The asset vs. the pipe: Dirok in Assam has strong reservoir quality across three zones, an established production facility, and existing market demand. Yet production is choked to 0.03-0.04 crore SCM/day, versus 1+ million SCM a few years ago, because the evacuation pipeline is at capacity. Management believes it could triple production to 4.5 crore SCF/day on short notice if the pipeline constraint were lifted.
- The 55-km pipeline replacement: The new pipeline has been laid and now needs to be connected back to the main DNPL line. Management's best estimate is 1-2 months, maybe 2 months, to complete the connection, but could not put a firm date on when gas would start flowing.
- The National Gas Grid connection: NRL is working on a short 300-400 meter connection at its facility to link IGGL to the National Gas Grid. Some connections already exist and might be activated. This is a critical enabler but outside HOEC's direct control.
- Capacity sharing risk: Even when the DFL-to-Duliajan pipeline is completed in 2-3 years, HOEC will not get all the capacity. Assam Gas Company Limited, the pipeline owner, will determine HOEC's pro-rated portion, and there will be other claimants. Management's long-term target is 7 crore SCF/day once that line is complete, with upsides from North Dirok and Greater Dirok.
Baroruchi Mishra: "We'll all have to take away our individual company hats. We have to put on the India hat and make things happen."
New Development Projects: B-15 and Exploration Upside
- B-15 award: The government awarded the B-15 field to HOEC, a significant addition adjacent to the flagship B-80 block. The field development plan is being matured, with 2-3 concepts under evaluation and one about to be selected. Front-end engineering design will take a few months, followed by FID and execution. Long-lead procurement and reservoir modeling are running in parallel.
- B-15 scale and concept: Targeting 4,000-5,000 barrels of oil and roughly 1 crore SCF of gas per day, requiring 3-5 wells. The field is 50-60 km from the existing B-80 facility; management is evaluating a tie-back versus a separate export line, with the potential to bring B-15 crude to B-80's infrastructure.
- Greater Dirok and Umatara: 100% HOEC exploration and appraisal blocks with disciplined, infrastructure-led, capital-efficient development pathways. Greater Dirok offers an opportunity to drill more wells.
- Cambay: Legacy assets held for 40 years, now being revisited with a focus on workovers, production enhancement, secondary recovery, and low-cost incremental production growth.
Financials, Reserves, and the Exceptional Gain
- Stand-alone performance: Net sale was INR274 crores after stripping unusual impacts, down from INR344 crores the prior year, driven by lower production. Lifting cost held nearly flat at $28.4/barrel versus $28.6, which management pointed to as evidence of financial discipline.
- Reserves value: 1P to 2P reserves are valued at USD300-500 crore depending on oil price, certified by independent global agencies, with substantial upsides beyond booked reserves. Realizing that value depends on drilling infill wells, optimizing existing wells, and enhancing infrastructure.
- The INR32 crore exceptional gain: This non-cash profit arose from the fair value estimate of the 40% stake acquisition in Adbhoot, as required by Ind AS for business combinations. No cash was exchanged. The disclosure was made after extensive discussion with auditors KPMG. An analyst questioned why the gain was not reduced from profit before tax in the cash flow statement, noting a discrepancy with September 2025 treatment; management gave a technical explanation and then cut off further discussion.
- FSO storage sale optionality: HOEC is looking at options to sell crude from FSO storage, where over 150,000 barrels are held. Management stated this crude can be sold at Brent without a discount, though a daughter tanker would incur demurrage costs. The right buyers and vessels are needed.
Baroruchi Mishra: "The crude can be sold at Brent. We don't need to discount it. The only thing is you might have to have a tanker, which will get the daughter tanker might have to pay some demurrage to the daughter tanker."
Organization and Stakeholder Alignment
- New leadership team: Three senior hires joined: Allen Joseph Andrade as CFO (40 years at British Gas and Shell India), Sanjay Kundu as Head of Offshore Operations (30 years at Shell and BG across UK and India), and Parthasarathy Bandopadhyay as Principal Reservoir Consultant (30 years across British Gas, PTTEP, Total in Thailand, and the World Bank). Krishnan Raghavan continues as CTO.
- Dirok stakeholder collaboration: Management emphasized a shift from company-specific interests to a collective "India hat" approach, working with the government, Oil India, and other stakeholders to find a credible technical evacuation path regardless of pipeline ownership. The urgency is framed around national gas paucity.
- Cost structure: Onshore production, particularly in Assam, carries the lowest opex per barrel. B-80 is the high-cost asset, with some costs controllable and others not, including MOPU running costs and tanker rentals. Company-wide opex is $28/boe.
Baroruchi Mishra: "It is no more, given the circumstances that we are in today as a country, the paucity of gas needs to be overcome. Therefore, whoever has gas and there is a credible technical path for flow of those gas molecules regardless of who owns it, will be explored and all parties are working towards that."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Production target | 10,000-11,000 boe/day, underpinned by drilling at PY-1, B-80, and Kharsang | By June 2026 |
| Production target | 22,000 boe/day | By 2028 |
| Production target | 32,000 boe/day | By 2029 |
| B-80 workover | Workover of 2 subsea wells, plus 3 additional development wells | Post-monsoon, liquidate entire program by June 2026 |
| 55-km pipeline connection | Pipeline laid; connection to DNPL line to be completed | 1-2 months, maybe 2 months |
| HPCL crude liquidation | Sell all crude stored at HPCL refinery to third-party buyers | 2-3 months |
| HPCL conciliation | Conciliation process per COSA to be completed | Next few months |
| Capex and debt plan | Concrete details on funding and debt/EBITDA outlook | Next quarter |
| Dirok gas flow | Start flowing gas once pipeline connection complete | No firm date; "hope in 1 or 2 months" |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue (standalone) | ₹288 cr, compared with ₹344 cr last year; net sale ₹274 cr after stripping unusual impacts |
| Revenue (consolidated, had HPCL sale not reversed) | ₹559 cr would have been the revenue |
| Profit after tax (consolidated) | ₹9 cr, includes ₹14 cr due to derecognition of HPCL revenue |
| Exceptional item | ₹32 cr gain, from fair value estimate of acquisition of 40% stake |
| Lifting cost | $28.4 per barrel, compared with $28.6 per barrel in the previous year |
| Return ratios | 4.5% and 2.5%, similar to the previous year |
| Current production | 1.5 thousand BOE, plus roughly 1,000 BOE locked in due to infrastructure constraints |
| Production target by mid-2027 | 10,000 to 11,000 BOE, line of sight to definitely above 8,000 BOE |
| Production target by 2028 | 22,000 BOE |
| Production target by 2029 | 32,000 BOE |
| 2P reserves | 6 crore barrels of oil equivalent; 1P reserves at 4 crore BOE, 3P reserves at 10.9 crore BOE |
| 1P to 2P reserves valuation | USD300 cr to USD500 cr, depending on oil price |
| B-80 2P reserves | 2.6 crore barrels of oil equivalent, of which approximately 1 crore has been produced |
| Dirok current production | 0.03 to 0.04 crore standard cubic meters per day (approx 1.5 crore SCF), with well potential of more than 0.11 to 0.12 crore SCM per day |
| Kharsang gross production | 700-plus barrels, production doubled from 9 wells drilled; 9 more wells planned to double again |
| HPCL crude sale reversal | ₹260 cr tied up in invoices; crude being resold to third parties, realization expected over 2 to 3 months |
| Last crude cargo sold price | USD109 per barrel |