MetricQ4 FY25YoY ChangeFull Year FY25YoY Change
RevenueINR9,087 crores+20%INR34,083 crores+18%
EBITDAINR4,816 crores+32%INR17,465 crores+28%
EBITDA margin53%~+500 bps——
PATINR3,003 crores+47%INR10,353 crores+33%

Market Position & Demand Thesis


Growth Projects & Expansion

Modi: "So I think for the FY '26 guidance, we have not factored anything outcome of this technology because we have to appreciate this is the first time out of the European side, we have first time implementing and we don't want to have any negative surprise later on."

Silver: The Strategic Variable

Misra: "This is a new technology, which is to recover lead and silver cake from jarosite instead of doing it in the fumer route that we do... it will form the future of all fuming processes in Hindustan Zinc."

Mine Lease & Regulatory Confidence

Misra: "1 kilometer below ground, we have invested, developed the mine. Is that possible for us to let it go or anybody else to come and just take it over and operate? Not possible."

Guidance & Commitments

CommitmentSpecificsTimeline
Mine metal production1,125,000 tons (±10,000 tons)FY26
Refined metal production0.11 crore tons (±10,000 tons)FY26
Refined silver production700–710 tonsFY26
Zinc cost of production$1,025–$1,050 per tonFY26
Growth capex$225–$250 million (approved projects only; changes if board approves further projects)FY26
Roaster commissioning160,000-ton-per-annum roaster first productionMid-Q1 FY26 (May 10–12 target)
Smelter debottleneckingDariba: Q2 FY26; Chanderiya: Q3 FY26FY26
Jarosite recovery technology commissioningAdditional 27 tpa silver, 6,000 tpa leadQ4 FY26
Fertilizer plant commissioningChanderiya plantQ4 FY26
Renewable energy share30% (up from 13% in FY25)FY26
Expansion announcement (first phase)0.12 to 0.15 crore tons; board approval then public disclosureWithin ~1 month
Full expansion disclosureAll 0.1 crore-ton increments announcedWithin 3–4 months
Bamnia Kalan first productionPortal formation underway~24 months
Zinc alloy plant full capacity28 KT, EBITDA of INR250–275 croresNo date given

Key Metrics

MetricQ4 FY25
Revenue from operations₹9,087 cr, up 20% YoY
Full year revenue₹34,083 cr, up 18% YoY, second highest annual revenue
EBITDA₹4,816 cr, up 32% YoY, second highest fourth quarter
EBITDA margin53%, up around 500 bps YoY
Full year EBITDA₹17,465 cr, up 28% YoY, second best annual EBITDA
Full year EBITDA margin51%, industry-leading, 400 bps improvement YoY
Profit after tax₹3,003 cr, up 47% YoY, highest-ever fourth quarter
Full year PAT₹10,353 cr, up 33% YoY, second highest annual PAT
Zinc cost of production$994 per ton, 16-quarter low
Full year zinc cost of production$1,052 per ton, 4-year low, better 6% YoY
Mined metal production310,000 tons, highest-ever Q4 since underground transition, up 17% QoQ
Refined metal productionUp 4% QoQ
Silver productionUp 10% QoQ
Domestic primary zinc market share77%, highest-ever domestic zinc sales this year
Value-added products share22% of portfolio in the year
Zinc alloy plant production10,000 tons in the year
Free cash flow from operations₹13,784 cr during the year
Return on capital employed58%, best return across the industry
Dividend distributed₹12,053 cr to shareholders during the year
Total shareholder return68% for the year, 13x of Nifty 50 returns and 7x of Nifty Metal Index
Renewable power share15% in Q4, targeting 30% to 35% in FY26
Domestic coal mix46% in Q4, 44% for full year
Strategic hedging gains₹55 cr in Q4, ₹150 cr for full year; no outstanding position
Total capex₹4,300 cr for the year (growth ₹1,500 cr, sustaining ₹2,800 cr)
Mine metal production guidance (FY26)1,125,000 tons per annum, ±10,000 tons
Refined silver production guidance (FY26)700 to 710 tons
Zinc cost of production guidance (FY26)$1,025 to $1,050 per ton
Growth capex guidance (FY26)$225 million to $250 million for approved projects
Metal reserves1.3 crore tons, milestone crossed for first time since underground transition
Total reserves and resources (ore)45.32 crore tons, mine life more than 25 years