Key Takeaways
- Record year, safety shadow: FY26 delivered record revenue, EBITDA and net profit on all-time-high production, but a fatal contractor incident at Zawar in January underscores the operational risk that comes with scale.
- Costs hit a five-year low: Zinc COP fell to $903/ton in Q4 and $959/ton for the full year, beating the sub-$1,000 guidance, driven by higher grades, lower power costs and operating leverage.
- Silver is now 45% of profitability: The by-product stream has become a material earnings driver, and management is actively monetizing lead concentrate inventory to capture strong silver prices.
- A generational expansion is taking shape: The board will review a single-location 0.1 crore ton smelter feasibility by July, while the 250 KTPA Debari smelter moves toward order placement within a month.
- What to watch next quarter: Whether the Hot Acid Leaching plant commissions on its delayed Q2 timeline, the trajectory of the Q1 mining grade (historically 7.3-7.4%) against the full-year cost guide, and any board decision on the mega-smelter.
Production & Cost Performance
- Record mined metal: Full-year mined metal crossed 0.11 crore tons for the first time, with Q4 setting a quarterly record; refined metal stayed above 0.1 crore tons for the fourth consecutive year. Growth came from higher ore production, improved mined metal grades, debottlenecking at Chanderiya and Dariba, and better plant utilization.
- Grade tailwind: Q4 mining grade of 7.9% versus the full-year average of 7.5% was a significant cost benefit; every 10 bps of grade change moves costs by $7/ton. Management declined to give a quarterly COP trajectory but noted Q1 grades historically sit around 7.3-7.4%.
- Power cost shift: Domestic coal reached 64% of the mix in Q4 (53% for the full year) and is roughly 40% cheaper than imported coal. Renewable energy contributed 18% in FY26, with a target of 30-35% in FY27; every 2% RE increase cuts costs by $1/ton on a long-term coal price basis.
- Natural gas drag: A gas shortage added a marginal ~$11/ton to Q4 costs, with no production impact.
- By-product credits growing: Sulfuric acid sales (~₹1,400 cr in FY26) are linked to the sulfur index and reset quarterly; Q4 levels are expected to persist as long as input commodity prices hold. Scrap and residue sales added ~₹1,000 cr. As metal production rises from 1,048 KT to 1,100 KT, more acid and residues become available, so other income should rise year-on-year unless prices crash.
Sandeep Modi: "I think $975 to $1,000 is good enough. I'm sure we should be able to do much below than as the situation improves."
Silver: The Earnings Engine
- Profitability contribution: Silver contributed 45% to overall profitability in FY26, transforming what was once a by-product into a co-driver of earnings.
- Strategic inventory monetization: HZL sold 12,000 tons of lead concentrate in Q4 (and a similar quantity in Q3), yielding 37 tons of silver equivalent sales to capitalize on favorable silver prices. Lead concentrate revenue hit ₹500 cr in Q4 with EBITDA of ₹330 cr, up from ₹250 cr in Q3.
- Production vs price trade-off: Mines are zinc-rich, so when zinc LME is high (₹3,100-3,400), producing additional zinc is more profitable than chasing incremental silver. A spike in silver output to 700+ tons would only make sense if zinc prices fall to $2,800-$3,000/ton while silver stays around $60/oz.
- Capacity target: Silver capacity is targeted at 830 tons by 2029, driven by the 250 KTPA smelter expansion, a new LGLC circuit, a smelter fumer, and tailings recycling.
Arun Misra: "That can happen when the zinc prices fall to say $2,800 to $3,000 per ton. If the zinc prices fall, then and silver remains at say $60 at troy ounce, it will make much sense to produce more lead and silver than production of zinc."
Growth Projects & Capital Allocation
- 250 KTPA Debari smelter: Site mobilization is complete and detailed engineering is largely finalized. Order placement is expected in approximately one month, with mill expansion orders closing between the first and second week of June. The project carries a double-digit IRR, though management declined to disclose the exact figure.
- 0.1 crore ton smelter: Design has been finalized for a single location in Rajasthan where the 250 KTPA smelter is being built, a shift from the earlier plan of two or three smaller smelters at different sites. The complete conceptual plan, layout and engineering is expected by end-Q1, with a board announcement after full feasibility in July or around that time. IRR is also expected to be double-digit, pending confirmation after conceptualization.
- Hot Acid Leaching: Commissioning is now expected in Q2 FY27, delayed due to the complexity of this first-of-its-kind plant in India.
- Fertilizer project: The phosphoric acid plant is set to start in approximately three months, with the DAP manufacturing plant to follow by end-2026 or early January 2027. No operations have started yet, and there is no impact from the Middle East conflict on rock phosphate supply.
- Tailings reprocessing: Site work has commenced at the Rampura Agucha tailings reprocessing plant and engineering is complete. Exploration partners have been onboarded at Zawar and Rajpura Dariba for the 2x growth plan.
- Funding approach: Growth will be primarily funded from earnings; management may consider debt only if loans are cheaper and cash flow timing mismatches exist. The minimum 30% of PAT dividend policy remains regardless of capex, and the board will balance dividends with expansion investment.
Arun Misra: "See, the change which has happened is earlier we were thinking we will make two or three different smelters in different locations. Then we had an idea instead of doing that, why not bring everything together in one place? Then we reworked the whole plan and now the designers have confirmed that in one location about a 600, 700 KTPA smelter can be put."
Financials & One-Offs
- Record financials: Quarterly and full-year records were set for revenue, EBITDA and net profit. FY26 revenue crossed ₹40,000 cr and EBITDA crossed ₹20,000 cr for the first time, driven by higher production, a supportive commodity environment, improved by-product realization, and rupee depreciation.
- Other expenses jump explained: A ~₹600 cr sequential increase in other expenses was matched by a similar increase in other operating income. This reflects new ancillary business agreements where HZL sells smelter residue to third parties and buys back finished goods or work-in-progress; accounting rules require gross presentation of both sides. These are expected to increase to ₹1,200-1,500 cr annually each side.
- Brand license fee: The brand license and strategic services fee to Vedanta Limited is contracted until 2030 with no interim renewal. FY26 payment was ~₹1,300 cr, with an additional ~₹100 cr payable after audit settlement at year-end.
- Hedging stance: Policy permits hedging 10-20% of annual volume, not beyond 12 months. HZL is currently comfortable at 10% and did no hedging in Q4. There is no rolling 12-month obligation and no compulsion to re-hedge if positions unwind. Management views the 58-59% EBITDA margin and silver by-product status as reasons not to experiment beyond 10%.
Sandeep Modi: "Given that 58%, 59% kind of EBITDA margin of the company, we believe that and silver being a by-product, we believe that it's not worthwhile to experiment and do the hedging beyond 10%."
Strategic Positioning
- Critical minerals entry: HZL secured three critical mineral blocks during the year: potash, tungsten, and rare earths, diversifying beyond zinc-silver-lead.
- Sustainability credentials: The company was placed in the top 1% of the S&P Global Sustainability Yearbook for the ninth consecutive year. Chanderiya Lead Zinc Smelter became India's first site to receive both Zinc Mark and Copper Mark certification.
- Index inclusion: HZL was added to the Nifty 100, Nifty Next 50, and multiple Nifty ESG indices during FY26.
- Renewable energy pathway: FY27 target is 30-35% RE share, rising to a committed 70% round-the-clock by FY28. Moving from 20% to 70% RE could yield a $25/ton cost reduction on long-term coal price assumptions.
Arun Misra: "As the world accelerates towards electrification, decarbonization, and energy security, we see a generational opportunity for metals. Our ambition is not only to participate in this transformation but to lead it by building future-ready capabilities, advancing sustainability, and delivering consistent long-term value."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Mined metal production | 1,150 KTPA ± 10 KT | FY27 |
| Refined metal production | 1,100 KTPA ± 10 KT | FY27 |
| Refined silver production | 680 tons ± 10 tons | FY27 |
| Zinc COP ex-royalty | $975 to $1,000 per ton | FY27 |
| Capex | $500 million to $600 million | FY27 |
| Hot Acid Leaching commissioning | Plant start-up | Q2 FY27 |
| Fertilizer project (phosphoric acid) | Plant start-up | ~3 months (Q1/Q2 FY27) |
| Fertilizer project (DAP) | Plant start-up | End-2026 / early Jan 2027 |
| 250 KTPA smelter order placement | Orders placed | ~1 month (June 2026) |
| 0.1 crore ton smelter feasibility | Board announcement after full feasibility | July 2026 or around that time |
| Renewable energy share | 30% to 35% | FY27 |
| Renewable energy share | 70% round-the-clock | FY28 |
| Silver capacity | 830 tons | By 2029 |
| Dividend policy | Minimum 30% of PAT | Ongoing, regardless of capex |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue | ₹13,544 cr, record, up 49% YoY and 23% QoQ |
| EBITDA | ₹7,747 cr, record, up 61% YoY and 27% QoQ |
| EBITDA margin | 57%, industry-leading |
| Net profit | ₹5,033 cr, record, up 68% YoY and 29% QoQ |
| Zinc cost of production (ex-royalty) | $903 per ton, lowest quarterly since underground transition, down 9% YoY and 4% QoQ |
| Mined metal production | 315 KT, record |
| Refined metal production | 282 KT, record |
| Silver production | 176 tons, up 11% QoQ |
| Silver contribution to profitability | 45% |
| Lead concentrate sold | 12,000 tons, with silver equivalent sales of 37 tons including prior quarter |
| FY27 mined metal production guidance | 1,150 KTPA ± 10 KT |
| FY27 refined metal production guidance | 1,100 KTPA ± 10 KT |
| FY27 refined silver production guidance | 680 tons ± 10 tons |
| FY27 zinc cost of production guidance (ex-royalty) | $975 to $1,000 per ton |
| FY27 planned capex | $500 mn to $600 mn |
| Net cash position | ₹5,594 cr as of March 2026, versus net debt of ₹1,169 cr a year ago |
| Free cash flow (before growth capex and RE investment) | ₹13,337 cr for FY26 |
| Renewable energy consumption | 18% in FY26, target 30–35% in FY27 |