IndiGrid Infrastructure Trust Q2 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/cnvl7y88el54yohuk095ug6u.pdf

Key Takeaways


Distribution & Cash Flows

Harsh Shah: "This typically when we do the prediction or increase the DPU we work in a way that at least it is sustainable for five to seven years and similarly I think even this is done with the same assumption in mind."

Portfolio Operations


Acquisitions & Growth Pipeline

Harsh Shah: "I think beyond that as we have said before we are not into a year-on-year AUM growth business. We would look for assets which are reasonably priced and meet our criteria."

Balance Sheet & Financing


ESG & Regulatory Initiatives

Harsh Shah: "I think it is a good suggestion. We will try to see if we can publish it."

Management & Governance

Harsh Shah: "At the end of the day it is kind of an institution where we have a very deep management team in place and therefore at the end of the day there are always people related changes that business goes through but the way the institution is created and I am talking about dependent on me or anybody else for that matter is that the business and the stability will continue beyond people side"

Guidance & Commitments

CommitmentSpecificsTimeline
Full-year DPURs.13.20 per unitFY23
KTL acquisition close~Rs.1,500 Cr framework assetBy December 2022
Kallam project completion~Rs.200-250 Cr development projectQ3 of next year (FY24)
NER permanent restorationBoth circuits restored after flood-forced outageFebruary 2023
SPV-level finance costReduced to zero after loan repayment this quarterFrom Q3 FY23 onward
AUM addition visibility~Rs.1,700-1,800 Cr (7-8% growth)Over the next one year
Indicative DPU disclosureManagement will explore restarting the practiceNo fixed timeline

Key Metrics

MetricQ2 FY23
Revenue₹580 cr, +6% YoY
EBITDA₹535 cr, +6% YoY
EBITDA at SPV level₹531 cr
Net distributable cash flow (NDCF)₹280 cr, +25% YoY; +6% YoY excluding one-off factoring repayment in prior year
DPU₹3.30, +4% YoY from ₹3.19 in Q2 FY22
DPU composition₹3.11 interest, ₹0.19 capital repayment
Gross distribution₹231 cr
NAV per unit₹135.30
Cumulative distribution since listing₹65.11 per unit, ₹3,415 cr total
DPU guidance for FY23₹13.20, on track; sustainable for 5–7 years per management
Collections96%, vs 105% in Q2 FY22 and 77% in Q1 FY23
DSO days66 days, vs 52 days at Sep 2021
Monthly collection efficiency trend79% in Jul, 110% in Aug, 100% in Sep
Portfolio availability99.3%
Net debt to AUM57%
Average cost of debt7.51% on ~₹13,000 cr gross borrowings
Fixed-rate borrowings share77% of gross borrowings
Interest coverage ratio2.19x
Cash balance₹1,151 cr at Sep 30, including ~₹230 cr for Q2 distribution, ~₹380 cr for DSRA, and Raichur Sholapur acquisition funds
Incremental debt cost in Q2 FY23~7.50%
Gross borrowing mix60% bank loans, 40% NCDs
Annualized total return since listing14% (62% distribution, 43% price change)
Beta0.08
Trips per line0.15, increased YoY due to thunderstorms and lightning
Lost-time injury (LTI)Zero
Safe man hours milestone0.1 crore
Raichur Sholapur acquisition enterprise value~₹250 cr, closed Nov 9, 2022
Raichur Sholapur expected annual NDCF addition₹10–11 cr
Raichur Sholapur line length208 ckms, 765 kV single-circuit
Raichur Sholapur remaining TSA life27 years of 35-year tenure
KTL framework asset size~₹1,500 cr, acquisition targeted by Dec 2022
Kallam project size~₹200–250 cr, expected completion by Q3 FY24
Visible AUM addition over next one year~₹1,700–1,800 cr, ~7–8% growth
Transmission capex pipeline (next 5 years)~₹1.4 lakh cr
Transmission projects pipeline (private)~₹1,40,000 cr
National monetization plan pipeline~₹45,000 cr
JKTPL revenue contribution~2% of IndiGrid topline; outage revenue loss 0.01–0.02%
ECB hedge income impact on finance cost~₹9–10 cr benefit
FY23 gross borrowing repayment~₹273 cr, already refinanced
Refinancing quantum maturing~₹900 cr, less than 10% of overall borrowings
SPV-level finance cost (Q2 FY23)~₹14 cr, expected zero from Q3 after SPV loan repayment
Trust-level finance cost (Q2 FY23)~₹239 cr
Reserve replenishment in Q2~₹49 cr
Raichur Sholapur starting revenue~₹36 cr, declining to ~₹26–27 cr; average NDCF ₹11 cr
Raichur Sholapur consideration includes cash₹250 cr includes cash, so interest-bearing liability is lower (per management)
Analyst-estimated first-year surplus on Raichur Sholapur~₹20 cr (per an analyst's math)
Analyst-estimated surplus on Raichur Sholapur (simplified)~₹16 cr (per an analyst's math)
Average remaining asset life29 years
Renewable energy market addressed by IndiGridLess than 5–10%
Lines and substations operated54