Key Takeaways
- DPU guidance raised on strong collections: FY24 DPU guidance lifted to Rs. 14.10/unit and the quarterly run rate to Rs. 3.55/unit, driven by collections that beat expectations at 114% for transmission and 127% for solar.
- Virescent acquisition closed, but one-time costs compressed EBITDA: Revenue grew ~20% YoY while EBITDA grew only 4%, as two acquisition-related charges (a deferred acquisition fee accrual of ~Rs. 23 crores and ~Rs. 48 crores in employee exit incentives) hit the quarter.
- NAV declined on rising rates and asset depreciation: The NAV drop reflects fixed-life asset depreciation and a higher risk-free rate, partially offset by the accretive Virescent and Khargone acquisitions.
- The transmission pipeline is historically large: Over Rs. 1,25,000 crores of projects are slated for auction in the next 12 to 18 months, and IndiGrid is preparing to bid while also pursuing its first greenfield project and a BESS award.
- What to watch next quarter: Whether the DPU run rate holds at the new Rs. 3.55 level, progress on the Rs. 1,500 crore equity raise, and any update on the Kallam greenfield project COD.
Distribution & DPU
- Guidance raised: FY24 DPU guidance increased to Rs. 14.10/unit, a 7.5% YoY rise, and the quarterly run rate moved to Rs. 3.55/unit from Rs. 3.45 in Q1.
- Collections drove the upgrade: Transmission collections reached 114% and solar 127%, substantially aiding net distributable cash flow.
- Reserves replenished: Reserves closed at Rs. 303 crores after adding Rs. 49 crores in the quarter, now exceeding one full quarter's DPU.
- DPU growth strategy, not guidance: Management frames 3% to 5% DPU growth as an intent and strategy, explicitly declining to guide for a higher rate because it compounds.
Harsh Shah: "I would say even 3% to 5% is the intent and strategy. It's not a guidance, so it's a strategy."
Virescent Acquisition & One-Time Costs
- Scale transformation: The ~Rs. 4,000 crore Virescent acquisition multiplied IndiGrid's solar megawatt capacity fivefold, taking solar AUM to roughly 17% of the portfolio.
- EBITDA compressed by two one-time items: Operating revenue rose ~20% YoY but EBITDA grew only 4%, because the quarter booked an acquisition fee accrual of 0.5% of enterprise value (~Rs. 23 crores including GST) and ~Rs. 48 crores in incentives paid to Virescent employees who did not continue. Neither is a recurring cash outflow this quarter: the fee is only accrued and payable if full-year guidance is met.
- Solar performance improving: Solar CUF reached 18.9%, up 4% on the prior-year quarter from reliability and performance initiatives, and solar DSO improved sharply to 73 days from 125 days a year ago and 87 days last quarter.
- Refinancing plan: Of the short-term loan taken for Virescent, Rs. 400 crores has been repaid; the remaining Rs. 1,200 crores will be refinanced through the impending equity raise.
NAV & Balance Sheet
- NAV decline explained: The reduction is not from capital repayment (an accounting change under tax rules) but from three forces: fixed-life assets depreciating over time, a rise in the risk-free rate between Q2 last year and Q2 this year that had a significant negative impact, and a partial offset from the accretive Virescent and Khargone Transmission acquisitions. Without those acquisitions, NAV would likely have dropped further.
- AAA rating maintained: IndiGrid continues to hold AAA ratings from all three rating agencies.
- Leverage headroom intact: Net debt to AUM stands at 63.5%, below the 70% cap, and management will raise capital to preserve headroom for further growth.
- Refinancing discipline: The target is to limit refinancing to no more than 10% to 12% of gross borrowings per year.
- IFC bond landmark: IndiGrid charted a path for one of the longest infrastructure bonds, a nearly 15-year tenure with IFC, which also became the largest lender.
Growth Pipeline
- Transmission opportunity: Over Rs. 1,25,000 crores of transmission projects are announced for auction over the next 12 to 18 months, a pipeline management calls unprecedented. IndiGrid is preparing to identify and bid on relevant projects but will not quantify an expected win share.
- Greenfield entry: Kallam Transmission is IndiGrid's first greenfield transmission project, with COD being focused on. Under-construction assets, including Kallam, will remain below 1% of AUM against a SEBI allowance of ~10%.
- Battery storage awarded: IndiGrid received its first letter of award for a 20 MW / 40 MWh battery energy storage project in Delhi. The project is not yet operational and must be installed.
- GR Infra Rajgarh Transmission: A pipeline deal to acquire the asset upon its COD, expected in Q3.
- Internal restructuring: Management plans to reduce legal entities from 38 to roughly 25-26 to simplify the structure and cut compliance costs, subject to unit holder approval once the scheme is finalized.
Harsh Shah: "Transmission sector has never seen such a large pipeline to be bid out in a year or two. It's a significant amount of pipeline that we've seen. And we are hopeful that we'll win something reasonable for us."
Operational Performance
- Availability remains high: Average operational availability stayed above par at 99.76%, and solar CUF tracked to budget.
- NER asset issue resolved: An insulator flashover affecting three lines in the NER asset was rectified and the lines are operational.
- Tripping metrics: The trips per line ratio was 0.16 and substation trips per element 0.03, slightly higher than last year due to the insulator issues, but management does not anticipate a recurrence in the near future.
- Asset management focus: Priorities include maintaining 99.5% availability across the portfolio, maximizing incentives, improving O&M practices, deploying digital tools, and ensuring world-class EHS and ESG standards.
Capital & Equity Raise
- Preferential allotment completed: IndiGrid raised approximately Rs. 400 crores from marquee investors and family offices in August.
- Further equity raise planned: Unit holder approval has been obtained to raise equity capital of about Rs. 1,500 crores, which will refinance the remaining Virescent short-term debt and maintain growth headroom.
- Balance sheet priorities: Management is focused on optimizing interest costs, elongating tenures, and maintaining adequate liquidity.
Harsh Shah: "We are confident that storage is in its journey of evolution where solar was 15 years ago. And with incremental investment and support from the government, we are confident that the cost of battery energy storage will continue to come down."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| DPU guidance | Rs. 14.10 per unit for FY24 | FY24 full year |
| Quarterly DPU run rate | Rs. 3.55 per unit | Ongoing from Q2 FY24 |
| DPU growth strategy | 3% to 5% (intent, not guidance) | Ongoing |
| Virescent short-term loan refinancing | Rs. 1,200 crore balance via equity raise | Upon equity raise completion |
| Refinancing cap | Not more than 10% to 12% of gross borrowings per year | Annual |
| Under-construction asset limit | Below 1% of AUM (including Kallam) | Ongoing |
| Legal entity simplification | Reduce from 38 to ~25-26 entities | Subject to unit holder approval |
| GR Infra Rajgarh Transmission acquisition | Acquire upon COD | Expected Q3 FY24 |
Key Metrics
| Metric | Q2 FY24 |
|---|---|
| Revenue | ₹695 cr, +20% YoY |
| EBITDA | ₹558 cr, +4% YoY; includes ~₹71 cr one-time Virescent acquisition costs |
| Consolidated SPV EBITDA | ₹586 cr |
| NDCF (Trust level) | ₹309 cr |
| DPU | ₹3.55 per unit, +3% vs guidance and +7.5% YoY |
| FY24 DPU guidance | ₹14.10 per unit, raised from prior guidance |
| Gross distribution | ₹259.5 cr |
| NAV per unit | ₹133 as of Sep 30, 2023 |
| Total distribution since listing | ₹78.86 per unit, ~₹4,389 cr |
| AUM | ~₹27,000 cr |
| Net debt to AUM | 63.5%, below 70% cap |
| Average cost of debt | 7.56% |
| Fixed-rate borrowings | 84% of gross borrowings (₹18,800 cr) |
| Weighted average borrowing duration | 6.2 years |
| Transmission availability | 99.76% |
| Solar CUF | 18.9%, +4 ppt vs Q2 last year |
| Collection efficiency – Transmission | 114% |
| Collection efficiency – Solar | 127% |
| DSO – Transmission | 67 days as of Sep 30, 2023 |
| DSO – Solar | 73 days, improved from 125 days a year ago and 87 days last quarter |
| Solar share of AUM | ~17% post Virescent acquisition |
| Virescent acquisition enterprise value | ~₹3,850 cr (net of cash) |
| BESS project – Annuity topline | ~₹11 cr for 12 years |
| BESS project – Capex | >₹100 cr |
| BESS project – Equity required | ~₹30 cr (30% equity, 70% debt from GEAPP) |
| Transmission projects announced for auction | >₹1,25,000 cr over next 12–18 months |
| Closing reserves | ₹303 cr, in excess of one quarter’s DPU |