Key Takeaways
- Soft quarter, order inflow back-loaded: Revenue grew marginally YoY, but reported order book rose only ~₹200 crore by 30 September; management disclosed that H1 inflow actually reached ~₹1,000 crore because a substantial quantum was secured after quarter-end.
- Other income hit by PPP transition: Other income fell sharply as dividends from the completed ISTPL project stopped, surplus cash moved into PPP equity, and exchange gains shrank. Management calls this a periodic, sporadic issue that reverses as new HAM projects complete.
- JV losses persist but are narrowing: Coal connectivity JVs remain in the red due to teething issues around coal transportation infrastructure. Losses are reducing and breakeven is expected in about two years.
- Full-year guidance held, FY28 cautious: Standalone revenue guided to ₹9,000–₹9,500 crore (5%–6% growth), PAT margin at 6%–7%, and consolidated core EBITDA margin at 8%–9%. FY28 outlook is deliberately conservative given global volatility.
- What to watch next quarter: Whether the ₹9,000–₹10,000 crore order inflow target stays on track after the post-September surge, and any concrete FY28 revenue signal when management revisits guidance after February.
Order Book & Inflow
- Timing mismatch resolved: The reported order book increase up to 30 September was only ~₹200 crore, but total H1 inflow was ~₹1,000 crore because a substantial quantum of orders was secured after the quarter closed. Management confirmed this when an analyst flagged the math.
- FY27 inflow target: The company aims to secure ₹9,000–₹10,000 crore in orders this year, bidding across railways, highways, and overseas works. Management is hopeful that "we will get definitely some good works" in the next quarter.
- Bidding pipeline: Works quoted and pending opening total ~₹25,000 crore, giving visibility toward the inflow target.
- Year-end order book: Expected to be maintained at ~₹25,000 crore.
- International ambition: International orders currently sit at ~9% of the order book; management wants to take that to 15%, with aggressive bidding in Algeria, Sri Lanka, African countries, and Eastern Europe where margins are better and competition is less.
Ragini Advani: "You are absolutely right. If you are doing mathematics, the increase in order secured in the order book is close to INR 200 crore, which is the number up to 30th September. But if you are talking today, then that number goes up to INR 1,000 crore."
Revenue & Execution
- Full-year revenue: Standalone operating turnover expected to close at ₹9,000–₹9,500 crore, representing marginal growth of 5%–6%. Faster execution is a focus this year.
- Key project drivers: The Sivok project (tunnels and bridges in West Bengal and Sikkim) and the T-2 track work package for the bullet train project are the main contributors to current revenue.
- Domestic focus: Railways remains the first line of preference, supported by a large railway budget; highways are the second priority.
- FY28 outlook deliberately vague: Management hopes to take revenue "slightly on an upward trend" but stresses the market is volatile and sensitive to global uncertainties. A better view will be possible "maybe few months down the line. Maybe after February."
Ragini Advani: "As of now, I mean, to probably give you a better feedback on FY 2028 may be few months down the line, because it's a very volatile and a very sensitive market, more so to the uncertainties overall, all across the world. We are also going conservative..."
Other Income & PPP Transition
- Three-part decline: Other income fell on both consolidated and standalone levels because (1) dividends from the earlier PPP project ISTPL stopped when its concession period ended, while new HAM projects are still in construction and have not started generating dividends; (2) surplus cash and bank balances are being deployed into PPP project equity, reducing temporary interest income; (3) exchange gains this year are much lower than last year, which is more of a book entry.
- Temporary by design: Management describes the dip as a periodic, sporadic issue. The interest income forgone today will be made up by IRRs from the PPP projects over time, and HAM projects should complete by the end of this financial year.
- Working capital loan tested: The company took a small nominal working capital loan of ₹100 crore for these projects, described as testing the waters.
Ragini Advani: "It is that period in between where dividend from the previous PPP projects stopped, and from the new ones, it's still to take off."
Joint Ventures & Subsidiaries
- Structure: Ircon has 11 subsidiaries (roads, highways, renewable projects) and 7 joint ventures (mainly coal connectivity projects).
- Coal connectivity JV losses: The one operational JV, CERL, is incurring losses because while infrastructure is ready, coal transportation from the mines is still under development or facing other issues. Losses are reducing and should reduce further next year.
- Breakeven timeline: Management expects these coal connectivity projects to start breaking even from another two years down the line, with breakeven "probably the year after that."
Ragini Advani: "We do expect these coal connectivity projects to start breakeven from another two years down the line. The losses are reducing. It should be reduced next year, but in terms of breakeven, it should be probably the year after that."
Margins & Tax
- Tax rate spike: Q2 and H1 FY27 tax rate was elevated at ~33% because of a one-off additional tax liability of ₹12–₹13 crore on the completed Sri Lanka project. The full-year tax rate is expected to normalize to 23%–24% as this gets nullified over the year.
- Standalone PAT margin: Guidance maintained at 6%–7%.
- Consolidated core EBITDA margin: Guidance maintained at 8%–9%.
Merger Speculation
- RVNL-Ircon merger: An analyst asked for an update. Management stated they have no knowledge whatsoever and, as a listed company, will inform the market immediately if anything arises.
Ragini Advani: "To us, there is no knowledge whatsoever. As and when we get to know, of course, being a listed company and in accordance with the governance issue, we shall be immediately informing if there is any such thing. As of now, no."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Order inflow | Secure ₹9,000–₹10,000 crore in new orders | FY27 |
| Year-end order book | Maintain at ~₹25,000 crore | End of FY27 |
| Standalone revenue | ₹9,000–₹9,500 crore (5%–6% growth YoY) | FY27 |
| Standalone PAT margin | 6%–7% | FY27 |
| Consolidated core EBITDA margin | 8%–9% | FY27 |
| Full-year tax rate | 23%–24% (one-off Sri Lanka liability nullified over the year) | FY27 |
| International order book share | Increase from ~9% to 15% | No date; bidding strategy in place |
| HAM project completion | New HAM projects completed | By end of FY27 |
| Coal connectivity JV breakeven | Losses reduce next year, breakeven the year after | ~2 years |
| FY28 revenue guidance | Revisit and provide better feedback | Maybe after February |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Consolidated total revenue | ₹2,364 cr |
| Consolidated operating revenue | ₹2,272 cr |
| PAT | ₹100 cr |
| Core EBITDA | ₹227 cr |
| EPS | ₹1.09 per equity share, not annualized, face value ₹2 per share |
| Order book | ₹21,296 cr at 30th September 2026 |
| Order book composition | 55% competitive basis, 45% nomination basis |
| Order book geography | 91% domestic, 9% international |
| H1 FY27 order inflow | ~₹1,000 cr, of which ~₹200 cr reflected in order book up to 30th September, substantial quantum after |
| Full-year order inflow target | ₹9,000–₹10,000 cr, ₹1,000 cr already received |
| Works quoted and pending opening | ~₹25,000 cr |
| Standalone operating revenue guidance for FY27 | ₹9,000–₹9,500 cr |
| Consolidated core EBITDA margin guidance | 8%–9% |
| Standalone PAT margin guidance | 6%–7% |
| Full-year tax rate guidance | 23%–24%, Q2 impacted by one-off Sri Lanka tax liability of ₹12–₹13 cr |
| Total invested in subsidiaries and JVs | ~₹3,100 cr, with another ₹800–₹900 cr to be invested |