Key Takeaways
- Revenue surged, order book stable: Consolidated nine-month revenue rose 46% YoY, yet the order book held at ₹930-940 crores as high execution consumed the backlog.
- Margins held despite mix shifts: Q3 EBITDA margin stayed at 23% on ₹180 crore revenue, same as a prior quarter with ₹140 crore, though management noted dispatch mix can cause variation.
- US manufacturing build-out is accelerating: Orange expansion, a new Houston plant, and a target of $60-65 million US capacity by 2029 signal a structural shift toward local production.
- Disc filter localization slashed costs by over 50%: In-house filter mesh manufacturing and 98% indigenization turned a high-cost import into a competitively priced product, with orders now flowing.
- What to watch next quarter: Whether the ₹240 crore Q4 revenue target materializes and lifts full-year margins, the signing of the Galliford Try agreement, and any movement on the $6-8 million radial gates order in the US.
Revenue Growth & Order Book Dynamics
- Nine-month performance: Consolidated revenue grew 46% YoY, with standalone Jash Engineering up 44%, Shivpad up 201%, and Jash USA up 35%. PAT margin expanded from 9% to 12% at the consolidated level.
- Order book stability despite growth: The order book has remained at ₹930-940 crores for three quarters because sales execution is high, consuming the backlog. Management expects the order book to grow as new markets like the US and UK add $10 million and $2 million respectively, contributing ₹150-200 crores.
- Order book consumption timeline: The ₹933 crore order book is expected to be consumed in 1.5-2 years.
- Order cancellation impact: An order for gates was canceled, resulting in approximately ₹60 crore of revenue not being recognized.
- Revenue targets: Current year target is ₹675 crore, expected to be exceeded. Next year target is ₹850 crore, with the following year at ₹1,000 crore. Management is looking at 20% growth over the next two years.
- Q4 revenue expectation: Over ₹240 crore revenue is expected in the last quarter, representing roughly 50% of the previous nine months' output, which should lift EBITDA and PAT as fixed expenses remain constant.
Pandey: "you can easily understand from that entire setup of strategic planning that by 2029 we will be easily able to produce $60-65 million from US."
US Market: Manufacturing Build-Out & Strategy
- Current US revenue and targets: US is targeting more than $33 million this year, with next year's target at $40-45 million and $50 million the year after. The Orange facility expansion will provide bandwidth for $30-35 million, and the Houston plant will add another $10 million, planned for FY27-28.
- Manufacturing margin dynamics: Initial US operation overheads were very high, but with only 60 people (up by 5), operational expenses will not increase proportionally with revenue. For BABA projects, margins are calculated based on local US costs, so additional price is received for local manufacturing.
- Product focus: The US market is currently focused only on gates, not screens, because the gate market is growing and there is no dearth of orders. Only 60 people are in the US, with 25 in Houston covering marketing, project management, and finance.
- Screens opportunity: The company sees a future opportunity in US screens. Ranjith, the president of marketing in the US, has 23 years of screen experience from Headworks, and Headworks is currently low on business in the US market.
- Trump tariff resilience: Management stated there is no impact from the Trump tariff system, clarifying that nothing is exported from Shivpad to Rodney Hunt except gates, certain screens, and knife gate valves sent once a year or once in two years for stock.
- Regulatory flexibility: If new US regulations favor increased domestic manufacturing, the company is prepared to manufacture there, with Orange expansion planned next year and Houston construction possible within one to two years if additional capacity is needed.
Jain: "If new regulations in the U.S. post-Trump administration favor increased manufacturing within the country, we are prepared to manufacture there as well. We plan to expand our Orange facility next year. If additional capacity is needed, we already have a plot in Houston and can begin construction on that plant within one to two years."
UK & Waterfront: Frameworks, Integration, Turnaround
- Framework system constraint: Most UK water utilities operate on a framework system, and business cannot be secured without being part of it. Galliford Try, the biggest contractor in the UK, is already listed in the majority of frameworks.
- Galliford Try agreement: The company is on the verge of signing an agreement with Galliford Try, which has taken up Ham Baker Engineering Services. Galliford Try has given in writing that the agreement will be signed before March.
- Waterfront integration: Previously known only for SDP pen stocks and trading, Waterfront's business is growing post-acquisition. CNC machines and testing facilities have been sent from India, and the setup is now complete. Waterfront is manufacturing SDP pen stocks locally and selling them.
- Waterfront financials: Waterfront is currently in loss. Management stated "$4-4.5 billion will be breakeven," which appears to be a slip for million. Next year's target is crossing $4 million in sales, with a vision of reaching $10 million in four years.
- Framework wins: Waterfront was accepted as a supplier chain partner in United Utilities (the fifth biggest in the UK) three weeks ago and is already in seven trends, the second biggest framework authority in the UK.
- Screens entry in UK: Starting a screens business in the UK is not easy. With Ganot's reference, who has already supplied screens in the UK, the company is trying to build things up and has already quoted for screens through Galliford Try.
- UK revenue sourcing: Even at $10 million UK revenue, 80-85% would still come from India.
Pandey: "Most water utilities in the UK run on this framework, so we won't secure business unless we are part of it."
Product & Cost Initiatives
- Disc filter localization: Previously, 85% of the product was imported at extremely high cost. Now 98% is localized, including the filter mesh, which was previously imported from Germany. A machine has been procured to make filter mesh in-house, reducing costs by over 50%. An eight-wheel disc filter now costs around ₹45-50 lakhs.
- Disc filter orders: Orders worth ₹3.5 crores have been received for seven disc filters, with orders worth ₹3 crores in the pipeline from Malaysia.
- Product expansion: The company is expanding into aerators, mixers, and recanters.
- Chennai plant: A state-of-the-art manufacturing facility in Sipcot, Chennai, for stainless process equipment and screening equipment for south India is set to inaugurate in May 2025.
- Capacity expansion timeline: SEZ Pithampur expansion is expected by December 2025, the USA plant extension by January 2026, and the Houston office building by February 2026. Capacity utilization currently stands at 60%.
- Ashgal approval: Recently obtained Ashgal approval in just 2-3 months, attributed to brand strength, product quality, and deliveries.
Pandey: "Currently eight wheel disc filter is around just Rs.45-50 lakhs. So, you can understand that we have reduced 50% of the entire pricing, not even cost. Cost is going much down, 98% of the products utilize in this complete equipment is now localized, indigenized, including fabrication, all forges, machine and everything."
Margins, Working Capital & Manpower
- Margin stability with higher revenue: Q3 revenue of ~₹180 crore delivered the same 23% EBITDA margin as an earlier quarter with ~₹140 crore. Management attributes this to the mix of orders dispatched in the quarter, with some orders carrying lower margins. The full-year EBITDA margin target of 21-23% remains on track.
- Q4 margin uplift expected: With over ₹240 crore revenue expected in Q4, higher EBITDA and PAT are anticipated as some fixed expenses remain constant.
- Working capital stability: Working capital has been stable over the last 2-3 years, with debtor days around 100-120 and inventory days around 120-140. The working capital cycle is expected to remain around 150-160 days for the next 1-2 years, with no major change expected from BABA Act implementation.
- Capex funding: Capex will be partly funded from internal accruals and partly from term loans if liquidity issues arise.
- Skilled manpower shortage: There is a serious dearth of skilled manpower across the globe, including Germany, the US, and the UK. In the UK, the company has been searching for manpower for four months without finding the right people. However, the search is only for worker, technician, and junior-level positions, not senior roles, so the cost impact on profitability is minimal.
- Mahr Maschinenbau revival: Currently a no-transaction company with zero turnover, Mahr Maschinenbau will start taking orders that were previously taken in Jash Engineering Limited. Existing installations in the UK and other locations help create a track record, and the aim is to take out-of-India orders through Mahr Maschinenbau itself. The company expects ₹4-5 crores from Mahr Maschinenbau this year.
Growth Drivers & Market Context
- Four structural growth drivers: Reuse of water, desalination, stormwater flooding, and rising sea levels underpin long-term demand.
- UK AMP period headwind: The Asset Management Period in the UK slows business because of the complete approval process for asset management and funds from the government toward water business.
- Radial gates order in US: The company is on the verge of getting a radial gates order in the US valued at $6-8 million with a 4-year lead time.
- Middle East and Saudi Arabia: A Saudi Arabia manufacturing facility is "in the thought process, nothing materialized," and management declined to comment further. No market size figure was provided for the Middle East market.
- Shivpad recovery: Shivpad achieved ₹27 crores in FY23, but turnover dropped last year due to missing one or two significant orders. The business has now recovered and is in a strong position.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY25 consolidated revenue | ₹675 crore (expected to be exceeded) | FY25 |
| FY25 closing order book | More than ₹825 crore, possibly up to ₹900 crore | FY25 end |
| Next year revenue target | ₹850 crore | FY26 |
| Following year revenue target | ₹1,000 crore | FY27 |
| Revenue growth rate | 20% growth | Next two years |
| Full-year EBITDA margin | 21-23% | FY25 |
| US revenue target | $40-45 million | FY26 |
| US revenue target | $50 million | FY27 |
| US manufacturing capacity | $60-65 million | By 2029 |
| Waterfront sales target | Crossing $4 million | FY26 |
| Waterfront revenue vision | $10 million | In four years |
| Mahr Maschinenbau revenue | ₹4-5 crores | FY25 |
| Working capital cycle | 150-160 days | Next 1-2 years |
| Chennai plant inauguration | May 2025 | May 2025 |
| SEZ Pithampur expansion | December 2025 | December 2025 |
| USA plant extension | January 2026 | January 2026 |
| Houston office building | February 2026 | February 2026 |
| Galliford Try agreement signing | Before March | Before March 2025 |
| Order book consumption | ₹933 crore consumed | 1.5-2 years |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Consolidated revenue (9M FY25) | ₹522 cr, +46% YoY |
| Consolidated revenue (Q3 FY25) | ~₹180 cr, with 23% EBITDA margin |
| Gross margin (9M FY25) | 61%, flat YoY |
| EBITDA margin (9M FY25) | 20%, flat YoY |
| Profit after tax margin (9M FY25) | 12%, up from 9% YoY |
| Consolidated order book (as of 1 Feb 2025) | ₹933 cr |
| FY25 consolidated revenue target | ₹675 cr, expected to be exceeded |
| FY26 consolidated revenue target | ₹850 cr |
| FY27 consolidated revenue target | ₹1,000 cr |
| EBITDA margin target (FY25 full year) | 21–23% |
| EBITDA margin target (next two years) | 12–14%, excluding rupee depreciation impact |
| US business revenue (FY25) | $33 mn targeted |
| US business revenue target (next year) | $40–45 mn |
| Waterfront revenue (since acquisition, 8 months) | $1.8 mn |
| Waterfront full-year FY25 revenue target | ~$3 mn |
| Waterfront revenue target (next year) | >$4 mn |
| Waterfront 4-year revenue vision | $10 mn |
| Capacity utilization (consolidated) | ~60% |
| Working capital cycle | 150–160 days, expected to remain stable |
| Order cancellation (gates, revenue not recognized) | ~₹60 cr |