J Kumar Infraprojects Ltd Q1 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/ytlkwo5u7a7wizsr7szlzulw.pdf

Key Takeaways


Revenue & Profitability

Kamal Gupta: "Of course, like we do not work without bottom line, so our focus is always a profitable growth and not on the topline, as you must be seeing our previous history also..."

Order Book & Bid Pipeline

Kamal Gupta: “Right now the balance sheet and the financial status of J. Kumar entitles us to go up to Rs.20000 Crores also without any limitations; however, it totally depends upon the nature of work if what type of Capex or what type or new types of jobs or in which geography we are taking up the work...”

New Project Wins

ProjectDetails
IRCON expressway (Delhi-Mumbai corridor)₹1,068 Cr (ex-GST), Vadodara to JNPT package 17, including a 4.2 km dual blast tunnel (4+4 eight-lane). Appointed date expected from October 1, 2022; survey and mobilization already started to save time and potentially earn a bonus. Secured at 14–15% operating margin.
BMC sewage tunnel (Don Bosco to Malad)₹510 Cr (ex-GST) JV project, J. Kumar share ₹306 Cr, awarded in Q2 FY23. Involves a smaller-diameter TBM with segment lining. Secured at 14–15% operating margin.

Margin & Inflation Protection

Nalin Gupta: "Whether it is metro or non-metro, the situation is same, so all of our projects, 100% of our projects are covered with price escalation variation clause okay and these are linked with the RBI index, if the commodity price goes up, the RBI index goes up. If the commodity prices go down, the RBI index goes down, so whether it is Cement, Steel, Fuel, Labor, CNM or other commodities, it is all linked with our price escalation clause, so any increase or decrease does not hit our bottom line..."

Capex & Equipment

Kamal Gupta: “...the stretch between Vasant Kunj to Kishangarh is having a varied type of strata ranging from EPB machine requirement which is for soil to open type of TBM which is for rock, so we had no other choice but to get one machine new brand and this strata over, which we encounter there is the hard strata is very, very hard...”

Sector Outlook & New Opportunities


Project Updates


Guidance & Commitments

CommitmentSpecificsTimeline
FY23 revenue₹4,000 Cr (described as conservative)FY23
EBITDA margin14% to 15% bandFY23
Order inflow~₹5,000 Cr to maintain order book of ₹12,000–13,000 CrFY23
Capex₹125–150 CrFY23
IRCON expressway appointed dateWork to begin formallyFrom October 1, 2022
CIDCO coastal road startConstruction commencementMid-October to November 2022
Metro Line 2a operationPut into operationAround November 2022
CIDCO water tunnel tenderQuote submission3–6 months
GMLR RFP submissionRFP submissionNext couple of months
Bidding pipeline outcomes~₹30,000 Cr of submissionsLikely after next quarter

Key Metrics

MetricQ1 FY23
Revenue from operations₹994 cr, up 47% YoY from ₹675 cr
Operating EBITDA₹140 cr, up from ₹97 cr in Q1 FY22
EBITDA margin14.1%, vs 14.4% in Q1 FY22; guidance maintained at 14–15%
PAT₹62 cr, up 93% YoY from ₹32 cr
PAT margin6.2%, vs 4.8% in Q1 FY22
Revenue guidance for FY23₹4,000 cr, conservative; upside possible
Order inflow target for FY23~₹5,000 cr, vs ₹3,670 cr inflow in FY22
Order book as of June 30, 2022₹12,950 cr, metro 57%, flyover bridges and roads 35%
Order book execution period3–4 years average
Projects awarded in FY23 to date₹1,374 cr, comprising IRCON expressway and BMC sewage tunnel JV
Capex target for FY23₹125–150 cr, revised up from ₹100–125 cr; Q1 capex ₹31 cr
Cash and bank balances₹139 cr, including escrow accounts
Fixed deposits₹384 cr
Trade receivables₹907 cr
Unbilled revenue₹545 cr
Mobilization advance₹557 cr
Retention money₹220 cr
Inventory₹359 cr
Trade payables₹524 cr
Bidding pipeline~₹30,000 cr of projects in process of submission across India
RFQ submitted for GMLR₹6,000 cr
Mumbai Metro Line 3 completion85% completed, expected completion by December 2023
Mumbai Metro Line 2a completion~99% completed
Mumbai Metro Line 7 completion~97% completed
Pune Metro completion~80% completed
TBM fleet7 TBMs owned, 1 more being added; all currently utilized