Key Takeaways
- Muted Q1, H2-weighted year: Revenue grew just 2% YoY as U.S.-Iran war disruptions and BMC water-use restrictions slowed site progress, but management expects 15% full-year growth with H2 carrying the load.
- The order book is finally converting: ~₹5,500 crores of orders booked in Q1 to date, and big-ticket projects that stalled FY26 (GMLR, VDCR, Chennai) are now resolving their land, tree-cutting and GAD bottlenecks.
- Vadhvan is the FY28 story: Mobilization is underway, tree-cutting started, but actual excavation begins only in October after the monsoon, so material revenue contribution waits until Q3.
- Margins held, ambition inches up: EBITDA margin moderated to 14.1% from 14.6% YoY on mix and timing; management targets a 0.5–1.0 ppt improvement going ahead while insisting it will not chase topline at the expense of margin.
- What to watch next quarter: Whether the ₹1,500 crore Delhi Metro L1 converts to an order, the pace of TBM launches at GMLR, and the actual Q2 revenue pickup after a monsoon-hit July.
Execution: Why FY26 Stalled and Why FY27 Looks Different
- The FY26 flat-revenue puzzle: Despite a strong order book, revenue was flat last year because three large projects (GMLR, VDCR, Chennai Elevated Corridor) and one cancelled project (Orange Gate) could not take off. The common blockers were land acquisition delays, tree-cutting permissions, and GAD finalization.
- GMLR turning the corner: Tree-cutting permission was obtained only in August 2025 after Supreme Court clearance; land acquisition issues are now fully resolved. The first TBM is fully ready and waiting for political confirmation (Chief Minister, ECM) to launch; the second TBM is in advanced assembly and expected to launch in about two months. Internal completion target is June 2029, with December 2029 as the maximum, against an original contract date of November 2028. The company is entitled to a 2-year extension but intends to complete earlier.
- Chennai NHAI extension de-risked: 21 km of the 25 km alignment lies in the Cooum River, where state department restrictions apply. NHAI granted a timeline extension and paid prolongation cost, so there is no margin impact. The company is confident of completing by December 2028.
- Anand Nagar handover resolved: A 3 km stretch out of 8.5 km was previously not handed over due to an NHAI-MMRDA toll decision; that was sorted after a meeting last week. The project remains on track for its scheduled October 2028 completion and is around 15% complete.
- VDCR poised to start: GAD is finalized and land acquisition is done; the project is expected to be fully on track in 1–2 months with a good push from Q3.
- Monsoon reality check: The first 10 days of July were very bad with no work possible; work is now ongoing at all sites except where earthwork cannot be done in rains, such as Vadhvan.
Kamal Gupta: "So last year and '25 and '26 in this period, this process took a lot of time. And that's how we could not get the revenue like GMLR, Chennai, VDCR, all these projects could not see the light of sun."
Order Book & Pipeline
- Q1 order haul: Orders of ~₹5,500 crores booked in Q1 FY27 till date, including one received the day before the call, and an additional ~₹1,500 crores in L1 status.
- L1 position: A ₹1,500 crore Delhi Metro underground project with international funding from the World Bank is in L1 status; clearances are expected and conversion is anticipated in Q2 FY27, not Q3.
- FY27 inflow target: Management targets ₹8,000–10,000 crores of order inflow and is optimistic of achieving it, with better visibility expected after Q2. The company states it has the potential to take orders up to ₹15,000–20,000 crores at desired margins.
- Bid pipeline depth: ~₹50,000 crores to ₹1 lakh crore worth of jobs to be explored in the coming 9–12 months, spanning MSRDC Shaktipeeth corridors, the Uttan-Virar corridor (~₹15,000–16,000 crores), NHAI, flyovers, DMRC and metro work.
- Big-project deferral risk: The Virar-Uttan corridor received MoRTH clearance on merging locations, and Anand Nagar Saket is also in the pipeline, but these projects can get deferred by 3–6 months and may slip into next year.
- New-order revenue contribution: Orders booked this year could contribute ₹400–600 crores of revenue within FY27, with good revenue also coming from new models.
Kamal Gupta: "We really don't want to overcome it. We want to over deliver and then speak."
Vadhvan: The Multi-Year Anchor
- Mobilization in full swing: Surveys are done, tree-cutting permissions from the forest department have been obtained, and tree cutting and transplantation have started. Government land acquisition is ongoing.
- Excavation waits on the monsoon: Actual excavation and work will start only in October after the rains, so material revenue contribution begins from Q3 FY27.
- Land acquisition is partial, not project-wide: Only the initial 6–7 km stretch from the port side has a land acquisition issue, not the entire 32 km stretch. Tunnelling will start after the rains.
- Strategic significance: Vadhvan is a Greenfield port-connectivity project and is expected to contribute to the FY28 revenue target of ₹7,500 crores.
Margins & Capital Allocation
- Q1 margin walk: EBITDA margin moderated to 14.1% from 14.6% YoY, attributed to timing-related factors and the evolving mix of projects under execution.
- Margin-first philosophy: Management was emphatic that it does not bid for work at wrong margins and that last year, even with no growth, 14–15% EBITDA was maintained. The stated ambition is to increase EBITDA margin by 0.5% to 1.0% going ahead, targeting 15–16% versus the current 14–15% band.
- Balance-sheet snapshot: Gross debt rose to ₹840 crores, mainly from a term loan for the TBM and capex for Chennai projects; the last TBM instalment was paid in the last week of June. Management expects gross debt to be less than ₹800 crores by year-end, with no further material term loans planned.
- Capex outlook: ₹150 crores per year for the next two years, including maintenance capex, unless a new project requires higher capex. No big capex is foreseen beyond that.
- Working capital improvement: Working capital days improved to 103 from the previously stated 120-day target; the intent is to keep it in the 100–110 range.
- Vizag land monetization: A deal for ₹180 crores for 30 acres is done; money is yet to flow, with completion expected in Q2 or Q3 FY27. The company is above breakeven on the asset.
- Buyback on hold: A buyback is on the cards but the company is waiting, currently focused on capital infusion for orders and capex. No fund raise is being considered for the moment.
Nalin Gupta: "Unless we make margins, we don't want growth. We don't want to become a follow company where we don't have margins and we are just doing top lines and making everyone a rosy picture. As far as you don't have margins there is no use of doing business."
Financial Mechanics
- Depreciation step-up coming: Depreciation is expected to increase from ~₹50 crores per quarter to ~₹60 crores per quarter once the TBM (₹300 crores of CWIP) is capitalized, which management said would happen in the next 2, 3 days or so from the call date. The full impact of last year's ₹480 crores of capitalization will also be felt in the current year.
- Tax rate normalization: The Q1 tax rate was higher at 29.7% because the TBM was not yet capitalized; once the ₹300 crores CWIP is capitalized, it will provide a tax shelter and the full-year rate is expected to be more or less similar to FY26.
- Other income is recurring: Higher other income of ₹19 crores in Q1 is recurring, driven by surplus money invested in debt securities and margin money kept as FDs with banks for non-fund-based facilities.
- Client payment profile: While Maharashtra irrigation and PWD departments have payment issues, J Kumar's clients (DMRC, MMRDA, MSRDC, BMC, NHAI) pay promptly, so there are no cash flow problems.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth FY27 | 15% on ~₹6,500 crores base | FY27 full year |
| Revenue growth FY28 | 15% YoY to reach ₹7,500 crores | FY28 full year |
| EBITDA margin | 14–15% for FY27, with ambition to increase by 0.5–1.0 ppt to 15–16% | FY27; FY28 also guided at 14–15% |
| Order inflow FY27 | ₹8,000–10,000 crores | FY27 full year |
| Delhi Metro L1 conversion | ₹1,500 crores order expected | Q2 FY27 |
| GMLR completion | Internal target June 2029, max December 2029 | June–December 2029 |
| Chennai NHAI completion | Confident of completion | December 2028 |
| Anand Nagar completion | Scheduled date | October 2028 |
| Chennai state project handover | Plan to hand over | March 2027 |
| Vadhvan excavation start | After rains | October 2025 |
| Gross debt | Less than ₹800 crores | FY27 year-end |
| Capex | ₹150 crores/year | Next 2 years |
| Tax rate | Similar to FY26 once TBM capitalized | FY27 full year |
| Vizag land deal completion | ₹180 crores inflow | Q2 or Q3 FY27 |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Revenue from operations | ₹1,511 cr, up 2% YoY from ₹1,484 cr in Q1 FY26 |
| EBITDA | ₹215 cr, down 1% YoY from ₹217 cr in Q1 FY26 |
| EBITDA margin | 14.1%, vs 14.6% in Q1 FY26 |
| PAT | ₹97 cr, down 6% YoY from ₹103 cr in Q1 FY26 |
| PAT margin | 6.4%, vs 7% in Q1 FY26 |
| Revenue growth guidance for FY27 | 15% on FY26 top line, implying ~₹6,500 cr |
| EBITDA margin guidance | 14% to 15% |
| Order inflow target for FY27 | ₹8,000 cr to ₹10,000 cr |
| Order inflow booked in FY27 till date | ~₹5,500 cr (announced), plus L1 of ₹1,500 cr for Delhi Metro underground |
| Total order book as on 30 June 2026 | ₹22,246 cr |
| Order book composition | Elevated corridors & flyovers 48%, roads & road tunnels 20%, metro 9%, others 23% |
| Net debt as on 30 June 2026 | Negative ₹45 cr |
| Gross debt as on 30 June 2026 | ₹840 cr |
| Gross debt-to-equity | 0.24 |
| Working capital days | 103 days, vs 99 days for FY26 |
| Capex in Q1 FY27 | ₹34 cr |
| Capex guidance for next 2 years | ~₹150 cr per year (including ~₹100 cr maintenance capex) |
| Depreciation in Q1 FY27 | ~₹50 cr per quarter, expected to rise to ~₹60 cr once TBM is capitalised |
| Other income in Q1 FY27 | ₹19 cr, expected to be recurring |
| Effective tax rate in Q1 FY27 | 29.7%, expected to reduce for full year |
| Mobilisation advance (interest-bearing) | ₹470 cr, entirely interest-bearing, rate 8.5% to 9.5% |
| Fund-based limit utilisation | 39% utilised (limit ₹1,300 cr) |
| Non-fund-based limit utilisation | 65% utilised (limit ₹5,000 cr) |
| Chennai NHAI packages execution | ~20% completed, target completion December 2028 |
| GMLR project status | 2,000 links cast (~4 km tunnel), first TBM ready for launch |
| FY28 revenue target | ₹7,500 cr, shifted from FY27, with similar margins of 14% to 15% EBITDA |