Key Takeaways
- Revenue guidance cut on extended monsoon: H1 revenue grew 10% YoY, but the full-year target was lowered to INR6,200–6,300 crores from INR6,500–6,600 crores after heavy rainfall persisted through October and hit job-site execution.
- Margins held, upgrade promised: H1 EBITDA margin inched up to 14.6% (from 14.5% a year ago); management reaffirmed 14–15% for FY26 and targets a 1-point lift to 15–16% over the coming two years.
- Order book building toward INR23,000 crores: The secured order book plus INR5,000–6,000 crores of targeted inflows this year should push the closing backlog to INR20,000–23,000 crores by March 2026, with metro and elevated corridors making up two-thirds of the mix.
- Balance sheet stays light: Gross debt is just INR75 crores, net debt is negative, and the company carries ~INR900 crores in mobilization advances; a QIP enabling resolution was passed but management says there are no immediate plans.
- What to watch next quarter: Whether the CIDCO project actually starts after environmental clearances, the pace of GMLR tunneling as the TBM is assembled, and whether the INR20,000–25,000 crore bid pipeline converts fast enough to hit the inflow target.
Revenue: The Monsoon Math
- H1 held up despite weather: Revenue reached INR2,826 crores, up 10% YoY, even though an early and extended monsoon that ran till end-October disrupted job-site execution across the portfolio.
- Q2 took the hit: Q2 is seasonally the weakest quarter; this year the rainfall was heavier and longer, compressing the working window further.
- Full-year reset: Management cut its FY26 revenue target to INR6,200–6,300 crores, calling the new number conservative and insisting it always intends to do more than it says. The original INR6,500–6,600 crore guide implied ~15% growth; the revised range implies ~11% YoY.
- Growth ambition intact: The company aims to grow at 16–17% going ahead, with GMLR tunnel revenue and other new inflows expected to accelerate the top line from next year onward.
Kamal Gupta: "So, Shravan, as you are aware, this year, the monsoon has extended till October, in fact. So, we just want to give a conservative figure. And as you know, we always intend to do more than what we say."
Order Book & Bid Pipeline
- Backlog composition: Metro projects account for ~13% of the order book, elevated corridors and flyovers ~53%, roads and tunnels ~17%, and other building and civil works ~17%.
- Inflow target maintained: Management is confident of bagging INR5,000–6,000 crores of new orders in FY26, which would take the closing order book to INR20,000–23,000 crores by March 2026.
- Near-term bids: A BMC flyover and river bridge (~INR2,250 crores) was being submitted on the day of the call; a Delhi Metro project (~INR2,500 crores) is due by month-end; another tender of ~INR3,000 crores is in sight. INR2,000 crores of bids are already submitted and awaiting outcome.
- L1 position: The company is L1 for a INR1,200 crore conventional centre in Lucknow and expects the order very soon.
- Pipeline depth: Management intends to bid another INR20,000–25,000 crores across buildings, towers, metro and other verticals in different geographies over the coming six to nine months.
- Diversification as a shield: The company now works pan-India across seven states and is bidding for a river bridge of INR2,000-plus crores, reducing dependence on any single geography or client.
- Slowdown acknowledged but contained: Management noted some slowdown in order inflows for EPC companies broadly, but believes its geographic and vertical spread keeps it on track for the INR5,000–6,000 crore inflow target.
Project Progress: What Is Moving, What Is Stuck
| Project | Status | Key Detail |
|---|---|---|
| Chennai Elevated Corridor | ▲ Execution in full swing | Casting yard fully operational; foundations and piling ~40–45% done; substructure and pillars underway; only hindrance was extended Chennai monsoon. |
| MMRDA Anand Nagar-Saket (INR1,800 cr) | ▲ Revenue started | Piling, pile caps and pillar works underway; revenue already flowing. |
| NBCC Silicon Valley, Noida | ▲ Revenue started | Work in full swing; revenue has started pouring in. |
| GMLR Tunneling | ▬ Preparatory phase | TBM has reached the job site; ~700 rings cast at the casting yard; main shaft excavation for lowering the TBM ongoing; tree cutting done. |
| CIDCO (INR1,020 cr) | ▼ Awaiting clearance | Environmental clearances expected in November; management expects to start by December. |
| Versova-Dahisar Coastal Road | ▬ Permitting stage | Stage 1 permissions received; Stage 2 at final verge; MPCB and CRZ permissions in hand; tree-cutting permissions awaited; six foundations completed on roadside; IIT suggested one more ramp addition submitted for approval; casting yard land identified. |
- GMLR revenue timeline: Substantial revenue contribution to the top line is expected from next year onward; management declined to put a number on current-year execution, calling 20% too optimistic with only four to five months left.
- TBM depreciation: Depreciation on J. Kumar's TBM should start from Q2 FY27 on a pro-rata basis, with no material impact expected. The second TBM sits in NCC's books.
Margins & Balance Sheet
- Margin walk: H1 EBITDA margin improved 10 bps YoY to 14.6%; PAT margin stood at 6.9%.
- Guidance held with an upgrade path: Management sees no issue maintaining 14–15% EBITDA margin this year and intends to lift it to 15–16% over the coming two years, citing secured margins in the existing order book.
- Working capital: Slight improvement in H1; the company intends to hold net working capital at 120–130 days, with a year-end target of around INR800 crores (currently INR770 crores).
- Debt position: Gross debt is approximately INR75 crores; net debt is negative at INR124 crores. Mobilization advances total ~INR900 crores, of which ~INR500 crores is interest-bearing.
- Capex: FY26 capex is pegged at ~INR500 crores (including INR100 crores of maintenance capex), largely driven by the GMLR and Chennai projects; next year's capex is expected to drop to ~INR200 crores.
- Finance and depreciation run rates: Finance costs should continue at INR38–40 crores per quarter; depreciation at around INR45 crores per quarter.
- Unbilled revenue and retentions: Unbilled revenue stands at ~INR695 crores; retention money at ~INR389 crores. Non-fund based limits are ~INR5,000 crores with utilization at about 75%.
Kamal Gupta: "In H1 also, as you must have seen, we have done EBITDA margin of 14.6%. So, we'll be able to maintain this 14% to 15% of margin in this year as well. There's absolutely no issue. And going forward also, we are intending to go 1% notch higher and trying to do it like 15% to 16% in the coming two years."
Capital Raising: QIP on Standby
- Enabling resolution passed: The board passed a QIP enabling resolution, as it did last year, but management stressed there are no immediate plans to act on it.
- Triggers are deal-dependent: Any decision will turn on the nature of new orders won, specifically how capex-heavy they are and what working capital they demand. Management described itself as "keeping ourselves in preparedness to be ready for it."
- Quantum undisclosed: When asked how much the company might raise, management called the question premature and declined to answer.
Kamal Gupta: "It all depends upon the nature of work that we bag, means whether how capex oriented it is, what is the working capital requirement. So, it's a very dependable discussion. But yes, we are keeping ourselves in preparedness to be ready for it, but with no immediate plans to be precise."
Strategic Positioning & H2 Outlook
- Complexity as a moat: Management framed technically demanding, first-of-their-kind projects as a competitive advantage rather than a risk, arguing they force innovation and create barriers to entry.
- H2 framed as an acceleration phase: H1 was described as a period of consolidation and balanced performance; H2 is positioned as a period of building momentum, scaling up execution and moving with greater speed and focus.
- Value creation pledge: Management stated it is fully committed to creating sustainable value for shareholders, partners and stakeholders.
Kamal Gupta: "Where others see complexity, we see opportunity. Technically demanding, first-of-their-kind projects are not obstacles, they are catalysts that push us to innovate, adapt and lead."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 revenue | INR6,200–6,300 crores (~11% YoY growth) | FY26 full year |
| FY26 EBITDA margin | Maintain 14–15% | FY26 full year |
| Medium-term EBITDA margin | Lift to 15–16% | Coming two years |
| FY26 order inflow | INR5,000–6,000 crores | FY26 full year |
| Closing order book | INR20,000–23,000 crores | March 2026 |
| Revenue growth ambition | 16–17% | Going ahead (no year specified) |
| Net working capital | ~INR800 crores (120–130 days) | FY26 year-end |
| FY26 capex | ~INR500 crores (incl. INR100 cr maintenance) | FY26 full year |
| FY27 capex | ~INR200 crores | FY27 full year |
| CIDCO project start | After environmental clearances | Expected December 2025 |
| GMLR substantial revenue contribution | Material top-line contribution | From next year onward |
| TBM depreciation start | Pro-rata from Q2 FY27 | FY27 Q2 |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue from operations (H1 FY26) | ₹2,826 cr, +10% YoY vs ₹2,574 cr in H1 FY25 |
| EBITDA (H1 FY26) | ₹411 cr, +10% YoY vs ₹373 cr in H1 FY25 |
| EBITDA margin (H1 FY26) | 14.6%, vs 14.5% in H1 FY25 |
| PAT (H1 FY26) | ₹195 cr, +10% YoY vs ₹177 cr in H1 FY25 |
| PAT margin (H1 FY26) | 6.9% |
| FY26 revenue guidance | ₹6,200–₹6,300 cr, ~11% YoY growth, revised from ₹6,500 cr |
| FY26 EBITDA margin guidance | 14% to 15%, maintained; aiming 15%–16% in coming two years |
| Total order book (30 Sep 2025) | ₹20,160 cr |
| Order inflow in H1 FY26 | ~₹150 cr |
| L1 position | ₹1,200 cr, conventional centre in Lucknow |
| FY26 order inflow target | ₹5,000–₹6,000 cr |
| Closing order book target (Mar 2026) | ₹20,000–₹23,000 cr |
| Gross debt | ~₹75 cr |
| Net debt | negative ₹124 cr |
| Working capital | ₹775 cr, expected ~₹800 cr by year-end; target 120–130 days |
| Mobilization advance | ~₹900 cr, of which ~₹500 cr interest-bearing |
| Unbilled revenue | ~₹695 cr |
| Retention money | ~₹389 cr |
| Non-fund based limit utilization | ~75% of ₹5,000 cr limit |
| Capex in H1 FY26 | ₹398 cr |
| Full year FY26 capex target | ~₹500 cr, including ~₹100 cr maintenance capex |