J Kumar Infraprojects Ltd Q4 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/8phw51djohvaw41g0pl7np2c.pdf

Key Takeaways


Financial Performance

Madan Biyani: "In the EPC industry, it's a little cyclical. You cannot go on a straight line basis. Also if you see our revenue has increased. So debtors in terms of number of days, working capital in terms of number of days remains same and we endeavour to further reduce it."

Order Book & Bid Pipeline

Nalin Gupta: "So clearly it's a business call that we have taken. And if you talk of 40% also, you're talking of around ₹6,400 crores single job of at 1 location. So I think that's a good respectable number that we have finalized as a business call."

Project Execution Update

ProjectProgressTimeline
Line 3 Metro (underground packages)86% completeFull completion by year-end; MMRC planning to open first phase (SEEPZ to BKC) by end of CY23
Dwarka Expressway65% combined progress; additional ₹550 crores change-of-scope awardedPartial opening in 3 months; 95% done by year-end
Sewri Worli47% completePartial operation before MTHL connection; full completion in ~1.5 years
Mithi Package IV30% progress; 2 shafts completed, TBM runningNot specified
Pune MetroOperational completions imminentHandover by June 8
Mira Bhayandar (Line 9)Depot land approved and shifted to Dongri; airport land issue resolved, shaft ready for TBMElevated section in 1–1.5 years; underground in 2–2.5 years
CIDCO Coastal RoadCasting yard 50% complete; designs and investigations doneAwaiting final court approval, expected in 1–1.5 months
Bangalore Metro~₹250 crores in order book (2% of total)No indication of stoppage; management not concerned even if work stops
Kamal Gupta: "All of our contracts are covered with price escalation clause so any delay because of any other reasons does not affect us. ... if our major work is completed, we demobilize our resources from the site so our overheads go down apart from some maintenance staff. So it does not affect our bottom line."

Competitive Position & Capacity

Nalin Gupta: "Well, I would say that metro sector is in area where there are limited contractors pan India though the competition level exists, I wouldn't deny to that, but it is a very core competency area where you have limited players executing that size of projects whether it is elevated or underground."

Balance Sheet & Capital Allocation


Guidance & Commitments

CommitmentSpecificsTimeline
Revenue growth~15% CAGRFY24 and FY25
EBITDA margins14% to 15%Ongoing
FY24 capex~₹150 crores (₹200 crores if bullet train won)FY24
Debt level₹500–₹550 croresFY24 year-end
Order inflow₹5,000-plus croresFY24
CIDCO Coastal Road startCourt approval expected in 1–1.5 monthsNear-term
Dwarka Expressway partial opening3 monthsQ2 FY24
Dwarka Expressway near-completion95% doneFY24 year-end
Sewri Worli full completion~1.5 yearsFY25
Mira Bhayandar elevated section1–1.5 yearsFY25
Mira Bhayandar underground section2–2.5 yearsFY26
ROE/ROCE improvementFurther YoY improvement through EBITDA growthOngoing

Key Metrics

MetricQ4 FY23
Revenue from operations (FY23)₹4,203 cr, +19% YoY
Q4 FY23 revenue growth~2% YoY
EBITDA (FY23)₹597 cr, +18% YoY
PAT (FY23)₹274 cr, +33% YoY
PAT margin (FY23)6.5%, vs 5.8% in FY22
FY24 revenue growth guidance~15% YoY
FY24 EBITDA margin guidance14% to 15%
Order book₹11,854 cr as of Mar 31, 2023; Metro 53%, flyovers/bridges/roads 36%, others 11%
Order inflow (FY23)₹2,652 cr
Q4 FY23 order inflow~₹500 cr
Price escalation and scope changes added to order book (FY23)~₹1,200 cr
ROE (FY23)12.4%, vs 10.4% in FY22
ROCE (FY23)17.6%, vs 15.2% in FY22
Capex (FY23)₹230 cr
Capex guidance (FY24)~₹150 cr, plus additional if bullet train project won
Net debt~₹516 cr as of Mar 2023; expected ₹500–₹550 cr by FY24 year-end
Working capital days126 days as of Mar 2023
Trade receivables₹1,141 cr as of Mar 2023; ₹540 cr collected post year-end
Unbilled revenue₹546 cr as of Mar 2023
Mobilization advance outstanding₹548 cr as of Mar 2023
Retention money receivable₹267 cr; payable ₹212 cr as of Mar 2023
Bids submitted and awaiting outcome₹12,000+ cr; includes bullet train C3 package of ₹16,000 cr (J Kumar share 40%, ~₹6,400 cr)
Bid pipeline for FY24₹40,000+ cr planned, in addition to ₹12,000 cr already submitted
L1 projects awaiting award2 projects: ₹100 cr and ₹386 cr
Metro Line 3 (Colaba–SEEPZ) progress86% completed
Dwarka Expressway combined progress~65%; additional scope work of ₹550 cr received
Sewri Worli project progress47% completed
Mithi Package IV progress30% completed
CIDCO Coastal Road project statusCasting yard 50% done; work expected to start in 1–1.5 months
Fund-based sanction limit utilization62% utilized (₹394 cr of ₹637 cr)
Non-fund-based sanction limit utilization80% utilized (₹2,630 cr of ₹3,280 cr)
Dividend recommended₹3.5 per equity share of ₹5 each