Key Takeaways
- Steady execution, 19% revenue growth: FY23 revenue reached ₹4,203 crores with PAT up 33% YoY to ₹274 crores; management advises looking at annual figures rather than quarterly swings.
- Order book fortified by annual reset: Year-end order book hit ₹11,854 crores, boosted by ~₹1,200 crores of price escalation, variations and scope changes added as a regular year-end correction.
- Margins and returns trending up: PAT margin expanded to 6.5% from 5.8%, ROE rose to 12.4% and ROCE to 17.6%, both up ~20% YoY on EBITDA growth.
- Bullet train bid is the swing factor: A ₹16,000 crore JV bid with 40% share could add ~₹6,400 crores to the order book; win would also lift capex meaningfully.
- What to watch next quarter: Whether the bullet train bid converts, the pace of order inflow against the ₹5,000-plus crore FY24 target, and the start of CIDCO Coastal Road after court approval.
Financial Performance
- Top-line trajectory: FY23 revenue grew 19% YoY; Q3 was very good and Q4 also performed well, so management urged investors to assess performance on an aggregate yearly basis.
- Profitability gains: PAT grew 33% YoY to ₹274 crores, with PAT margin expanding to 6.5% from 5.8% a year earlier.
- Return ratios improving: ROE rose to 12.4% (from 10.4%) and ROCE to 17.6% (from 15.2%), a ~20% jump in both metrics, attributed to EBITDA growth and improved percentage terms.
- Capex overshoot: FY23 capex of ₹230 crores exceeded the ~₹150 crores plan, mainly due to an additional TBM and a new casting yard at Porbandar for a metro project.
- Working capital stable: Maintained at 126 days, consistent with the stated target of ~120 days; management sees potential for slight improvement to 125–126 days.
- Trade receivables cyclical: ₹1,141 crores as of March 2023, with ₹540 crores collected by the call date; described as a normal EPC pattern, not a collection challenge, with working capital days stable despite revenue growth.
Madan Biyani: "In the EPC industry, it's a little cyclical. You cannot go on a straight line basis. Also if you see our revenue has increased. So debtors in terms of number of days, working capital in terms of number of days remains same and we endeavour to further reduce it."
Order Book & Bid Pipeline
- Year-end order book: ₹11,854 crores, boosted by ~₹1,200 crores of price escalation, variations and change in scope of work added at year-end, a regular annual correction.
- Q4 inflow modest: ~₹500 crores of new projects awarded in Q4 FY23.
- L1 positions: Declared L1 in two projects, one of ₹100 crores and one of ₹386 crores; orders expected in Q1 FY24.
- Bullet train bid: Submitted a JV bid for the C3 high-speed railway elevated corridor package worth ~₹16,000 crores; J Kumar holds a 40% share, which would add ~₹6,400 crores to the order book if won.
- FY24 order inflow target: Looking for ₹5,000-plus crores; bid pipeline of ₹40,000+ crores of projects planned to be bid in FY24, in addition to ₹12,000 crores already bidded.
- GMLR and Dahisar Coastal Road: Bids will be placed once final tender dates are set; tenders were extended due to department reasons. Management deflected a question on whether it would go solo or partner, saying a call will be taken at the time of bidding.
Nalin Gupta: "So clearly it's a business call that we have taken. And if you talk of 40% also, you're talking of around ₹6,400 crores single job of at 1 location. So I think that's a good respectable number that we have finalized as a business call."
Project Execution Update
| Project | Progress | Timeline |
|---|---|---|
| Line 3 Metro (underground packages) | 86% complete | Full completion by year-end; MMRC planning to open first phase (SEEPZ to BKC) by end of CY23 |
| Dwarka Expressway | 65% combined progress; additional ₹550 crores change-of-scope awarded | Partial opening in 3 months; 95% done by year-end |
| Sewri Worli | 47% complete | Partial operation before MTHL connection; full completion in ~1.5 years |
| Mithi Package IV | 30% progress; 2 shafts completed, TBM running | Not specified |
| Pune Metro | Operational completions imminent | Handover by June 8 |
| Mira Bhayandar (Line 9) | Depot land approved and shifted to Dongri; airport land issue resolved, shaft ready for TBM | Elevated section in 1–1.5 years; underground in 2–2.5 years |
| CIDCO Coastal Road | Casting yard 50% complete; designs and investigations done | Awaiting final court approval, expected in 1–1.5 months |
| Bangalore Metro | ~₹250 crores in order book (2% of total) | No indication of stoppage; management not concerned even if work stops |
- Metro execution broad-based: All metro projects (Line 3, Line 9, Line 2B, Line 6, Navi Mumbai, Pune, Delhi, Surat) are progressing in full swing.
- Contract protections built in: All contracts carry price escalation clauses, so client-side delays do not affect the company; once major work is complete, resources are demobilized, overheads drop, and the bottom line is insulated from operational delays.
Kamal Gupta: "All of our contracts are covered with price escalation clause so any delay because of any other reasons does not affect us. ... if our major work is completed, we demobilize our resources from the site so our overheads go down apart from some maintenance staff. So it does not affect our bottom line."
Competitive Position & Capacity
- Metro sector moat: Management described the metro sector as having limited contractors pan-India; while competition exists, it is a core competency area with few players capable of executing projects of this size, whether elevated or underground.
- Stand-alone bidding capacity rising: J Kumar has bagged orders of ₹2,500 crores and ₹2,000 crores (Metro Line 9) on a stand-alone basis; with Line 3 execution at 86%, the company will be entitled to take up jobs of bigger magnitude up to ₹3,000–₹4,000 crores on a stand-alone basis.
- Bangalore metro exposure minimal: At ~₹250 crores or 2% of the order book, management is not concerned even if work stops, though currently there is no indication of stoppage.
Nalin Gupta: "Well, I would say that metro sector is in area where there are limited contractors pan India though the competition level exists, I wouldn't deny to that, but it is a very core competency area where you have limited players executing that size of projects whether it is elevated or underground."
Balance Sheet & Capital Allocation
- Debt level: Expected to remain around the same level (~₹516 crores) for the coming year; net debt to stay at similar levels, with FY24 year-end debt projected at ₹500–₹550 crores.
- FY24 capex plan: Contemplated at ~₹150 crores, including maintenance capex of 5% plus some incremental capex; if the bullet train project is won, FY24 capex may rise to ~₹200 crores, with the additional spend spread over 3–4 years and already factored into costing.
- Liquidity comfortable: Sufficient cash and unutilized working capital facilities available to undertake large projects and ramp up execution; no intention to draw an additional ₹250 crores mobilization advance at this moment.
- Shareholder return: Board recommended a dividend of ₹3.5 per equity share (face value ₹5), subject to shareholder approval at the ensuing AGM.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | ~15% CAGR | FY24 and FY25 |
| EBITDA margins | 14% to 15% | Ongoing |
| FY24 capex | ~₹150 crores (₹200 crores if bullet train won) | FY24 |
| Debt level | ₹500–₹550 crores | FY24 year-end |
| Order inflow | ₹5,000-plus crores | FY24 |
| CIDCO Coastal Road start | Court approval expected in 1–1.5 months | Near-term |
| Dwarka Expressway partial opening | 3 months | Q2 FY24 |
| Dwarka Expressway near-completion | 95% done | FY24 year-end |
| Sewri Worli full completion | ~1.5 years | FY25 |
| Mira Bhayandar elevated section | 1–1.5 years | FY25 |
| Mira Bhayandar underground section | 2–2.5 years | FY26 |
| ROE/ROCE improvement | Further YoY improvement through EBITDA growth | Ongoing |
Key Metrics
| Metric | Q4 FY23 |
|---|---|
| Revenue from operations (FY23) | ₹4,203 cr, +19% YoY |
| Q4 FY23 revenue growth | ~2% YoY |
| EBITDA (FY23) | ₹597 cr, +18% YoY |
| PAT (FY23) | ₹274 cr, +33% YoY |
| PAT margin (FY23) | 6.5%, vs 5.8% in FY22 |
| FY24 revenue growth guidance | ~15% YoY |
| FY24 EBITDA margin guidance | 14% to 15% |
| Order book | ₹11,854 cr as of Mar 31, 2023; Metro 53%, flyovers/bridges/roads 36%, others 11% |
| Order inflow (FY23) | ₹2,652 cr |
| Q4 FY23 order inflow | ~₹500 cr |
| Price escalation and scope changes added to order book (FY23) | ~₹1,200 cr |
| ROE (FY23) | 12.4%, vs 10.4% in FY22 |
| ROCE (FY23) | 17.6%, vs 15.2% in FY22 |
| Capex (FY23) | ₹230 cr |
| Capex guidance (FY24) | ~₹150 cr, plus additional if bullet train project won |
| Net debt | ~₹516 cr as of Mar 2023; expected ₹500–₹550 cr by FY24 year-end |
| Working capital days | 126 days as of Mar 2023 |
| Trade receivables | ₹1,141 cr as of Mar 2023; ₹540 cr collected post year-end |
| Unbilled revenue | ₹546 cr as of Mar 2023 |
| Mobilization advance outstanding | ₹548 cr as of Mar 2023 |
| Retention money receivable | ₹267 cr; payable ₹212 cr as of Mar 2023 |
| Bids submitted and awaiting outcome | ₹12,000+ cr; includes bullet train C3 package of ₹16,000 cr (J Kumar share 40%, ~₹6,400 cr) |
| Bid pipeline for FY24 | ₹40,000+ cr planned, in addition to ₹12,000 cr already submitted |
| L1 projects awaiting award | 2 projects: ₹100 cr and ₹386 cr |
| Metro Line 3 (Colaba–SEEPZ) progress | 86% completed |
| Dwarka Expressway combined progress | ~65%; additional scope work of ₹550 cr received |
| Sewri Worli project progress | 47% completed |
| Mithi Package IV progress | 30% completed |
| CIDCO Coastal Road project status | Casting yard 50% done; work expected to start in 1–1.5 months |
| Fund-based sanction limit utilization | 62% utilized (₹394 cr of ₹637 cr) |
| Non-fund-based sanction limit utilization | 80% utilized (₹2,630 cr of ₹3,280 cr) |
| Dividend recommended | ₹3.5 per equity share of ₹5 each |