Key Takeaways
- Cash flow turned negative as order book swelled: Receivables and retention money tied up in a growing order book, plus government paying only 60% upfront, pushed cash flow into the red. Management will try to use QIP funds to turn it positive.
- Margin compressed sharply on an unusual supply mix: H2 margin fell because the supply-to-service ratio hit 75:25 versus the normal 50:50, and supply carries lower margin than service execution.
- FY26 revenue guided at ₹275–300 crore: Management set a firm topline target and expects to bring in more than ₹500 crore of new tenders this year, targeting a ₹750 crore order book by year-end.
- Backward integration pushed to Q4 FY26: The conductor and transformer manufacturing plans, meant to lift margin, are delayed as EPC work absorbs all available manpower; CAPEX of over ₹3 crore is already sunk.
- What to watch next quarter: Whether the supply:service mix normalizes back toward 50:50 as raw material inventory converts to execution, pulling margin off the floor, and whether the ₹40 crore of receivables actually land by July-August.
Margin Mechanics: The Supply-Service Mix
- H2 margin dip is a mix story, not a cost story: In H1 the company does more execution and service work, which carries higher margin. In H2 supply activity dominates as inventory builds for the next year's execution, and supply margin is structurally lower. This year the split was an extreme 75:25, compressing OPM well below trend.
- Raw material inventory signals near-term recovery: Out of ₹35 crore total inventory, ₹23 crore is raw material that will convert to execution in April-May, so H1 FY26 should naturally deliver better margin as the service portion rises.
- Management drew an 18% floor: The company is targeting not to go below 18% margin, calling it the minimum acceptable level, while trying to push back toward last year's 21%.
- Supply and service margins are not separately tracked: Management declined to break out the two, stating that supply and service are linked parts of the same contract and are not calculated independently.
Divyanshu Jain: "We are trying not to go below 18 but we are trying to increase it more as compared to the last year which was 21%."
Order Book & Revenue Outlook
- Order book stands at ₹537 crore, to be executed by December 2026. Of the three JV orders covering 16 lines, 12 will complete and 4 will extend, with completion now pushed to March 2026 due to delays on the department's side.
- A ₹120 crore order landed in April, and management is confident of bringing in more than ₹500 crore of new tenders this year. The stated target is a ₹750 crore order book by FY26 end, after exhibiting ₹300 crore of revenue.
- Tender pipeline is deep but lumpy: The company will apply for tenders worth ₹500-700 crore in the next six months, and management flagged that transmission line work worth ₹7,000-8,000 crore is yet to come in Rajasthan alone, with total transmission line EPC work estimated at ₹15,000-20,000 crore.
- JV entity Suryavayu Renewables has been created and has applied for connectivity, but has generated no revenue yet.
Cash Flow & Working Capital
- Cash flow turned negative because growth consumes cash: Deposits released from tenders get absorbed into larger orders as the order book expands. Government clients pay only 60% initially, with the balance held back until contract closure, trapping cash in retention money and receivables.
- QIP proceeds earmarked for working capital: The recently completed ₹25 crore QIP at ₹198 per share will be deployed to try to make cash flow positive. Promoter stake diluted as a result.
- ₹40 crore of receivables expected back by July-August, offering a near-term liquidity catalyst.
Lokendra Jain: "The main reason for this is the deposit which is released from tender it goes into the big orders because our order book is getting increased regularly."
Competitive Position & Geography
- Rajasthan is both a moat and a concentration risk: More than 90% of work is in Rajasthan, where the company enjoys a 5-7% cost advantage on tenders because of its local base, own CMP and TAC, and zero rent cost. Over 35% of India's renewable energy comes from Rajasthan, driving transmission network demand.
- Overhead advantage is real but fragile: Being based in Rajasthan for 26-27 years keeps boarding, lodging and accommodation costs low. Outside the state, those costs pile up in a labor-intensive business, eroding the edge.
- Small-scale geographic diversification exists: The company has done work in Haryana, UP, and railway projects in Balaghat and Kerala, but the stated strategy is to try to take big contracts in Rajasthan.
- Price variation clauses protect input exposure: Contracts include a PV formula that reimburses the company on both positive and negative fluctuations in steel and aluminum prices, and management enters only those contracts that carry the clause.
Lokendra Jain: "We get a benefit of 5%-7% because of being in Rajasthan in terms of the cost of the tender. We are comfortable in that."
Backward Integration: Delayed but Still Planned
- Manufacturing CAPEX of over ₹3 crore is already sunk: The shed for the second manufacturing unit is built and the company says it is fully prepared, but the start date has slipped to Q4 FY26 because EPC work is increasing and absorbing all available manpower.
- Two DPRs in progress: A conductor plant DPR is underway, and a transformer DPR for a 13.5 ampere unit is being worked on, with a decision expected in three to four months. Transformer delivery lead times of 12-18 months are a factor, and the department is encouraging the move.
- A small hardware facility exists but is idle: Manpower is fully engaged in EPC work, and management says it is not affecting the business so they are not paying much attention to it.
- Margin uplift from backward integration is loosely quantified: Management cited a 2-3% PAT margin impact but did not provide a detailed mechanism for how the integration would flow through to margins.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue target | ₹275 crore to ₹300 crore | FY26 |
| Order book target | ₹750 crore | FY26 end |
| New tender inflow | More than ₹500 crore | FY26 |
| Margin floor | Not below 18% OPM | Ongoing |
| Supply:service mix normalization | Back to 50:50 | FY26 |
| Manufacturing start | Conductor and/or transformer production begins | Before March 2026 |
| Receivables recovery | ₹40 crore collected | July-August 2025 |
| Order book execution | ₹537 crore current order book fully executed | By December 2026 |
| JV order completion | 12 of 16 lines completed; 4 extended | By March 2026 |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Revenue | ₹152.68 cr (FY25), +137% YoY from ₹64.46 cr in FY24 |
| H2 FY25 revenue | ₹114.82 cr, +184.63% YoY from ₹40.33 cr in H2 FY24 |
| Net profit | ₹17.06 cr (FY25), +160.68% YoY from ₹6.54 cr in FY24 |
| PAT margin | 11.17% (FY25), up from 10.15% in FY24 |
| EBITDA | ₹27.61 cr (FY25), +109% YoY from ₹13.19 cr in FY24 |
| EBITDA margin | 17.5% to 18% (FY25), management floor at 18%, last year was 21% |
| Order book (unexecuted) | ₹537 cr as on 30th April 2025 |
| Order book target | ~₹750 cr by end of FY26, after executing ₹300 cr |
| FY26 revenue guidance | ₹275 cr to ₹300 cr |
| Supply-to-service mix | 75:25 in H2 FY25, targeting 50:50 going forward |
| Large order inflow | ₹120 cr order received in April 2025 |
| Tenders quoted (recent) | ₹180 cr in last ten days, price bid yet to open |
| Tender success rate | More than 70% on ₹800-900 cr of tenders applied |
| QIP raised | ₹25 cr at ₹198 per share |
| Employees on payroll | 1,050 (3,000 including contractors) |