Kirloskar Industries Ltd Q1 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/i35vy72urfl9o7ti7qtg04zb.pdf

Key Takeaways


Volume vs. Price: The Top-Line Tension

R.V. Gumaste: "Pig iron manufacturing has improved, substantially. It has gone to 0.85 crore tons. Availability has improved. Prices have come down and also import up to get in have increased... No dumping restrictions so far that we have been presenting to government, taking time."

Margin Mechanics: Who Keeps, Who Passes

R.V. Gumaste: "All the projects which we have taken, they have given the benefits in line with the plan. And where we have compelled to pass on to the customers is in the area of pig iron and steel. Whereas we continue to retain the margins in case of casting and tubes."

The Expansion Blueprint: Steel, Tubes, and a Mine

R.V. Gumaste: "We are a moderate-sized player in the market today. We are still talking about 200,000 tubes. Rather, I would say that we are looking towards how to enhance this capacity to 300,000 metric tons or 3,50,000 metric tons per annum. And we see a great opportunity for us to expand the capacity."

New Engines: Ramp-Ups in Progress

R.V. Gumaste: "If you ask me whether we are very-very confident, we are never very-very confident. Every project is a challenge to us. We want to handle it carefully. We want to take the challenge. We want to surmount the difficulties and successfully pass the test of every project."

External Threats: Dumping, Prices, and Power


Guidance & Commitments

CommitmentSpecificsTimeline
Tube sales volumeAchieve 200,000 metric tons; reach 14% EBITDA level for tube divisionThis financial year (FY26)
Tube capacity expansionExpand to 300,000–350,000 metric tons per annumOver next 2–3 years
Casting volume run rateReach 200,000 tons per annum (16,000–17,000 tons/month)"Very shortly"
Casting capacity targetReach 260,000 metric tons per annumOver next 2–3 years
Steel bloom project (Koppal)3.6 lakh metric tons per annum; CAPEX ₹700–₹800 crores2 to 2.5 years to operationalize
Engine block ramp-up5,000 blocks per month; optimistic 8,000–10,000 per monthNext six months
Solapur Phase-II ramp-up5,000 tons per month from current 4,200Next three months
Two-part foundry (Oliver)Commission first phase; 12,000–15,000 tons per annum capacityWithin one year
Jambunatha MineComplete all processesWithin three years
Total capex outlay₹500–₹600 crores this year; ₹2,000–₹2,500 crores totalThis year / over next 3–4 years
Tube division EBITDA15–16% once steel manufacturing cost internalizedWhen backward integration complete
NSE listing applicationApplication being prepared; will file itNo specific timeline committed

Key Metrics

MetricQ1 FY26
Revenue₹1,685 cr, +8.5% YoY
EBITDA₹214 cr, +14% YoY
PBT₹130 cr, vs ₹104 cr in Q1 FY25
PAT₹96 cr, vs ₹76 cr in Q1 FY25
Power and fuel cost6.1% of sales, improved from 8.9% in Q1 FY25
Pig iron realizationdown 8% YoY; down 38% over two years
Casting realizationdown 1% YoY
Tube division realizationdown 9% YoY; Baramati tube down 13%
Steel realizationdown 6% YoY
Casting volume growth+4% YoY
Pig iron volume growth+5% YoY
Steel and tube volume growth+42% YoY
Tube sales volume target2,00,000 metric tons for FY26
Casting sales volume target1,70,000 metric tons for FY26
OCTG contribution in tube segment~20% of tube sales
FY26 CAPEX plan₹500–600 cr
Expected incentive income₹15 cr for full year FY26