KPI Green Energy Ltd Q3 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/01qlzfn5coe1hp1de2rtsyrh.pdf

Key Takeaways


The Khavda Unlock & IPP Ramp

Salim Yahoo: "Khavda we had completed in FY '25, but the delay in the offtake of the unit was because of the government substation not completed which was in the scope of GUVNL. The government has completed the substation recently in December. So now in the next quarter, we'll see the revenue from the Khavda because that is one major thing which we'll be seeing movement in our IPP."

Order Book & New Wins

Salim Yahoo: "We don't work below 12% IRR when it comes to any project. So we will try to maintain that. But I think the pricing -- if you look at the tariff in Botswana, it's higher than what we have in India. So automatically, our IRR will be far better than what we are earning."

Margin Structure & Cost Insulation

Salim Yahoo: "IPP EBITDA is around 85% to 90% because I don't have any cost once I set up the plant. So my EBITDA is around 85% to 90%, whereas CPP is around 18% to 20%."

Sundrop IPO & BESS Vertical

Salim Yahoo: "The IPO is for battery energy storage system. We are setting up a separate vertical for Sun Drop, that is battery energy storage system. And that is a new project altogether or a product altogether."

Pledge, Balance Sheet & Shareholder Concerns

Salim Yahoo: "See, Sahil, you need to understand the share has not underperformed. It's the external factors that are impacting, and it is not impacting capex."

Growth Trajectory & Long-Term Bets

Salim Yahoo: "IPP segment will always be there, which will keep on generating revenue for you with an EBITDA of 85% to 90%."

Guidance & Commitments

CommitmentSpecificsTimeline
Khavda IPP revenue start~20 crore units per quarter run rate, subject to stabilization and seasonalityQ4 FY26
1 GW IPP commissioning35 MW already injecting; portion energized by March 2026; full 1 GW completeSeptember 2026
Promoter pledge releaseSBI to remove all pledge within 6 months of 1 GW project completion~March 2027 (6 months post Sept '26)
Sundrop IPOTo fund BESS vertical; KPI to retain 51%+ stakeH1 FY27
BESS project financial closeInvestment of INR 1,000–1,100 crores; IRR target 13–14%Expected shortly
Botswana initial phase500 MW IPP at INR 1,500–1,700 crores project cost; equity in placeCommission in a couple of years
Revenue growth rate50–60% year-on-yearOngoing
IPP revenue shareMinimum 25–30% of total revenue from IPPBy FY30
10 GW capacity visionAchieve 10 GW total capacityBefore 2030

Key Metrics

MetricQ3 FY26
Total revenue₹676 cr, +45% YoY
EBITDA₹251 cr, +73% YoY
Profit before tax₹170 cr, +48% YoY
Profit after tax₹126 cr, +48% YoY
9M FY26 total revenue₹1,931 cr, +64% YoY
9M FY26 EBITDA₹701 cr, +71% YoY
9M FY26 profit after tax₹354 cr, +60% YoY
EPC order book₹5,500+ cr, up from ~₹4,000 cr in Q2 FY26
CPP cumulative capacity2,572 MW, up from 2,426 MW in Q2 FY26
CPP order book1.96 GW, up from 1.60 GW in Q4 FY25
IPP energized capacity~520 MW
IPP revenue share of total topline9%
IPP EBITDA margin85% to 90%
CPP EBITDA margin18% to 20%
Debt-to-equity ratio1.50:1 (total borrowings to equity)
Debtor turnover ratio133 days, up from ~90 days
Return on equity20% to 24% (typical range)
Sun Drop (subsidiary) Q3 revenue~₹150 cr
Sun Drop 9M FY26 revenue₹390 cr
Sun Drop EBITDA margin25% to 30%
Sun Drop PAT margin17% to 18%
Sun Drop order book~₹500 cr
BESS project (GUVNL) expected IRR13% to 14%
BESS project expected investment₹1,000 cr to ₹1,100 cr
Botswana initial 500 MW project cost₹1,500 cr to ₹1,700 cr
Botswana project expected IRRHigher than 13%
FY26 year-on-year growth commitment50% to 60%
IPP revenue target by FY203025% to 30% of total revenue
Long-term capacity vision10 GW by 2030