KSB Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/aizgk0t2640my4ff8uefvgyz.pdf

Key Takeaways


Nuclear: The Persistent Overhang

Rajeev Jain: "I feel very embarrassed in every investor call when I come and tell you those orders on hand will go next quarter, next quarter. But to give you an assurance, nothing is wrong with those pump."

Exports & Localization Headwinds


Aftermarket, Standard Products & Margin Resilience

Rajeev Jain: "I don't think we are being conservative. 13% to 14% EBITDA is a very good EBITDA. So I don't think we are being conservative."

Solar: Learning Curve & Receivables Build


Product Launches, Digitization & Operational Initiatives


End-Market Outlook

MarketTrendCommentary
Wastewater▲ OptimisticInvestments visible; B pump launched to capture share.
Distillery▲ Coming backSegment showing signs of recovery.
Chemical & Paper▼ DownturnIndustries in a down cycle, weighing on demand.
Real Estate▬ UncertainPerformance depends on inflation and tightness in personal loans.
Coal (India)▬ Selective80 GW government target over seven years, but BHEL dominates as EPC and makes pumps in-house; KSB only participates when L&T wins orders.
Petrochemical▼ CutthroatVery competitive; KSB is selective, recently won share in HPL project and some Reliance orders.
Mining▲ New entryKSB entering the market, planning white iron foundry capability and pump localization.
Water Projects▲ Building presenceEntering with split-case and vertical turbine pumps; larger tubular casing pumps planned in coming months and years.
Rajeev Jain: "I always say KSB has this unique USB that you name a product, you name a pump, and we will have it, whether it is a small domestic pump or it's a cooling pump for the reactor. And everything in between is available."

Guidance & Commitments

CommitmentSpecificsTimeline
Nuclear invoicingAt least two pump sets invoiced; 50% of ₹267 crore Kudankulam order invoiced; ₹250 crores target from nuclear businessQ4 next year (possibly Q3 if all goes well)
FGD aftermarket revenueSpare part demand from 400+ supplied pumps as plants commission2026 onwards
Mechanical seal localizationEngineered seals localized; nuclear seals already 100% localNext two years
Solar receivablesReceivables to come down as documentation is now mostly completeBy end of this year
Solar controllersOwn controllers to be launchedNext year
Mining pump localizationWhite iron in own foundry; pumps localized for competitivenessNo date (planning stage)
EBITDA marginMaintain stable, consistent level around 13%-14% despite aggressive growth mixOngoing
Green hydrogen localizationLocalize pumps to become more competitive as local demand picks upNext 2-3 years

Key Metrics

MetricQ2 FY25
Revenue (9M FY25)₹1,806.7 cr, vs ₹2,247.2 cr in FY23 and ₹1,822 cr in FY22
Profit before tax (9M FY25)₹228.2 cr, continued increase from FY22 and FY23
Net cash position₹308 cr, as of Sep 2024, improved compared to last year
Order intake growth (9M FY25)8% to 10% over 9M last year, single-digit growth
Orders on hand₹2,400 cr, split equally between nuclear (₹1,200 cr) and non-nuclear (₹1,200 cr)
Order intake YTD (non-nuclear)₹1,118.6 cr orders in hand
Standard business share of order intake48%, improved from 43%
Engineered business share of order intake16%
SupremeServ share of order intake15%
Valves share of order intake21%
Exports share of revenue12% YTD, down from 16%
Solar business revenue (FY25 estimate)₹120 cr
Solar receivables₹80 cr to ₹85 cr
Nuclear revenue target (next year)₹250 cr, from two pump sets and 50% of ₹267 cr Kudankulam order
Dealer network strength1,100 dealers
Renewable energy share of total requirement71%, with 50% from new 6.65 MWp solar open access project
Voice overall engagement score88%, with 100% participation, improved from prior survey