Lloyds Metals & Energy Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/0syaqudawcrvj7tijwt535jq.pdf

Key Takeaways


Project Execution & Timelines

Rajesh Gupta: "These are our internal projections. Our projections to our board are the original projections which were little bit more than this like Riyaz mentioned."

Mining Expansion & EC Clearance

Rajesh Gupta: "And one more thing that we have to keep in mind is the logistics movement. So that becomes a bottleneck. With the pipeline of 1 crore tons being commissioned simultaneously, that bottleneck stands reduced dramatically."

Beneficiation & Cost Structure

Rajesh Gupta: "The cost of beneficiation would be around INR800 a ton, but that is more than offset by the fact that this material would be piped by slurry pipeline to our steel plant or pellet plant facility, number one as well as the royalty would come down because we are doing this beneficiation outside the mine area and the royalty would be paid on lower grade material."

Market & Commercial Updates

Rajesh Gupta: "In the preliminary discussion, some surprises have been thrown up. For example, many of the steel authority mines also expire at the same time as some of the other mines in 2030. That I didn't knew, for example."

Steel Plant & Capex


Guidance & Commitments

CommitmentSpecificsTimeline
EC clearance for mining expansionPublic hearing post-Maharashtra Elections, then MOEA approvalFebruary 15th-20th, 2025
2.5 crore ton DSO dispatch run-rateAchievable "more or less immediately" post-ECFY26 (2.5 crore tons guided)
Pellet Plant 1 and iron ore grinding plant1 crore ton capacity each, operations from FY26Completion by March 2025
DRI plant at GhugusOperations from FY26Completion by end of March 2025
Pellet Plant 21 crore ton capacityCompletion by March 2026
BHQ beneficiation last phaseFinal phase of beneficiation capacitySeptember 2027
IPS income commencement150% IPS for Gadchiroli post-pellet-plant; DRI plant IPS post-startFY26
Capex fundingDebt-free, via QIP and warrantsOngoing (35% warrants received)

Key Metrics

MetricQ2 FY25
Revenue growth26% YoY for H1 FY25
EBITDA growth37% YoY for H1 FY25
Iron ore realization₹5,516 per ton, up 19% YoY
EBITDA per ton (iron ore)₹1,668, up 17% YoY
DRI segment volumes84,552 tons
Iron ore production volume0.54 crore tons in H1 FY25
Power segment sales growth38% YoY for Q2 FY25
Other income (IPS benefits)₹72 crores, from previous years, booked in H1 FY25
Capital expenditure incurred₹1,714 crores in H1 FY25
Full-year capex guidance₹3,400–3,500 crores for FY25
Full-year mining volume guidance1.3–1.4 crore tons for FY25
Full-year DRI volume guidance~330,000 tons for FY25
Beneficiation pilot plant yield38%, producing 68% Fe output
All-inclusive cost (beneficiation, royalty, transport)₹2,800–3,000 per ton
Slurry pipeline transport cost to pellet plant~₹50 per ton