Key Takeaways
- Projects running ahead of schedule: All major projects are tracking 1 to 1.5 years ahead of original board projections, with the slurry pipeline already commissioned and the first pellet plant on track for March 2025.
- H1 FY25 revenue grew 26% YoY, driven by higher sponge iron and iron ore volumes, with EBITDA up 37% YoY. Management expects a much better H2, though Q2 mining revenue dipped ~₹800 crores QoQ on seasonal rains.
- The logistics bottleneck is being solved: The 1-crore-ton slurry pipeline is commissioned and, once the pellet plant is ready, will cut transport costs by ~₹600 a ton while dramatically easing the movement constraint that caps peak monthly mining.
- Beneficiation pilot is beating expectations: The pilot plant is achieving a 38% yield vs. the 35% originally assumed, producing 68% Fe output. Management remains conservative on scaling but sees the cost more than offset by pipeline savings and lower royalty.
- What to watch next quarter: Whether the EC clearance arrives by the February 15th-20th target, enabling the 2.5 crore ton dispatch run-rate, and whether the pellet plant and grinding unit commission on schedule in March 2025.
Project Execution & Timelines
- Slurry pipeline commissioned: The 85 km pipeline was laid in a record 8-9 months and is ready; utilization begins when the iron ore grinding unit and pellet plant are complete, expected around March 2025.
- Pellet Plant 1 and iron ore grinding plant: Both 1 crore ton capacity projects are on track for completion by March 2025, with operations starting in FY26.
- Pellet Plant 2: Scheduled for completion by March 2026.
- DRI plant at Ghugus: Progressing well, with completion expected by end of March 2025 and operations from FY26.
- 1.2 wire rod mill: Advancing well within schedule at both Konsari and Ghugus.
- BHQ beneficiation last phase: To be completed by September 2027, corrected from the earlier September 2028 date.
- All projects running ahead: Management stated all projects are running almost 1 to 1.5 years ahead of schedule, though they are sticking with the same publicly stated dates rather than accelerating formal guidance.
Rajesh Gupta: "These are our internal projections. Our projections to our board are the original projections which were little bit more than this like Riyaz mentioned."
Mining Expansion & EC Clearance
- EC clearance timeline: The mining plan and Terms of Reference are approved; the public hearing will happen post-Maharashtra Elections, with final EC from MOEA expected by February 15th-20th.
- 2.5 crore ton dispatch target: Once EC is received, management expects to hit the 2.5 crore ton DSO sales run-rate "more or less immediately." FY26 mining is guided at 2.5 crore tons.
- MDO Thriveni already mobilizing: Thriveni has started implementing machinery in anticipation of the EC clearance, so ramp-up can begin without delay.
- FY25 iron ore production guidance: 1.3 to 1.4 crore tons, assuming EC for expansion arrives by mid-February.
- Logistics bottleneck resolved: Peak monthly mining of ~0.22 crore tons was previously constrained by logistics movement; the 1-crore-ton slurry pipeline "stands reduced dramatically" that bottleneck.
Rajesh Gupta: "And one more thing that we have to keep in mind is the logistics movement. So that becomes a bottleneck. With the pipeline of 1 crore tons being commissioned simultaneously, that bottleneck stands reduced dramatically."
Beneficiation & Cost Structure
- Pilot plant outperforming: Commissioned end-March 2024, the pilot plant is achieving 38% yield vs. the 35% originally anticipated, producing 68% Fe output. Management calls 38% an optimum figure but cautions that larger plants introduce more variables.
- Beneficiation cost offset: Beneficiation costs ~₹800 a ton, but this is more than offset by two factors: the slurry pipeline reduces transport cost by ~₹600 a ton, and royalty is paid on lower-grade material since beneficiation happens outside the mine area.
- All-in cost stability: Management expects the all-inclusive cost (beneficiation, royalty, and transport to consuming center) to remain roughly the same as today at ₹2,800 to ₹3,000 per ton even after the enhanced mining and processing chain is fully operational.
- MDO cost reduction: Post-stabilization, MDO costs should come down by ₹150-200 a ton; beneficiation adds another ₹150-200 in savings.
Rajesh Gupta: "The cost of beneficiation would be around INR800 a ton, but that is more than offset by the fact that this material would be piped by slurry pipeline to our steel plant or pellet plant facility, number one as well as the royalty would come down because we are doing this beneficiation outside the mine area and the royalty would be paid on lower grade material."
Market & Commercial Updates
- Iron ore market buoyant: Domestic iron ore market remains strong; international prices stable at ~$100 for 62% Fe grade; a double price increase was seen in the Indian market after many months.
- Pellet trading started as seed marketing: The company began trading higher-grade pellets as a market development exercise; the marginal loss reported is a carry-on from previous quarters. Zero exports this quarter due to low pellet margins on the export front.
- BigMint market study engaged: Preliminary discussions have thrown up "surprises," including that many SAIL mines also expire in 2030 alongside other merchant mines. A detailed report is expected in 2-3 months.
- Sunflag relationship resolved: The arbitration matter is settled; OFCDs converted into 6 crore equity shares; an ore purchase agreement entered for supply of ~0.1 crore tons per annum. Management declined to comment on the shares as a potential overhang, noting they are part of public shareholding.
Rajesh Gupta: "In the preliminary discussion, some surprises have been thrown up. For example, many of the steel authority mines also expire at the same time as some of the other mines in 2030. That I didn't knew, for example."
Steel Plant & Capex
- 0.3 crore ton steel plant: A ₹16,000 crore project; investment will start after most other major projects are completed. The company is evaluating state-of-the-art technologies in the blast furnace route, with a full study underway. No specific timeline was given.
- Capex phasing: ₹3,500 crores in FY25; ₹7,000 crores each in subsequent years. Total ~₹16,000 crores for the DRI plant, pellet plants, pipeline, and beneficiation; another ~₹16,000 crores for the steel plant.
- Funding strategy: Management has decided capex should be without debt, funded through the QIP and warrants. Around 35% of warrants have been received, with 65% still to come.
- IPS income from FY26: New IPS series for Gadchiroli at 150% will start once the pellet plant is operational; similarly for the new DRI plant. Benefits are expected to flow from FY26.
- Carbon footprint: Pelletization will use LNG, not oil. Management does not have carbon footprint figures for the slurry pipeline but will evaluate them.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| EC clearance for mining expansion | Public hearing post-Maharashtra Elections, then MOEA approval | February 15th-20th, 2025 |
| 2.5 crore ton DSO dispatch run-rate | Achievable "more or less immediately" post-EC | FY26 (2.5 crore tons guided) |
| Pellet Plant 1 and iron ore grinding plant | 1 crore ton capacity each, operations from FY26 | Completion by March 2025 |
| DRI plant at Ghugus | Operations from FY26 | Completion by end of March 2025 |
| Pellet Plant 2 | 1 crore ton capacity | Completion by March 2026 |
| BHQ beneficiation last phase | Final phase of beneficiation capacity | September 2027 |
| IPS income commencement | 150% IPS for Gadchiroli post-pellet-plant; DRI plant IPS post-start | FY26 |
| Capex funding | Debt-free, via QIP and warrants | Ongoing (35% warrants received) |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Revenue growth | 26% YoY for H1 FY25 |
| EBITDA growth | 37% YoY for H1 FY25 |
| Iron ore realization | ₹5,516 per ton, up 19% YoY |
| EBITDA per ton (iron ore) | ₹1,668, up 17% YoY |
| DRI segment volumes | 84,552 tons |
| Iron ore production volume | 0.54 crore tons in H1 FY25 |
| Power segment sales growth | 38% YoY for Q2 FY25 |
| Other income (IPS benefits) | ₹72 crores, from previous years, booked in H1 FY25 |
| Capital expenditure incurred | ₹1,714 crores in H1 FY25 |
| Full-year capex guidance | ₹3,400–3,500 crores for FY25 |
| Full-year mining volume guidance | 1.3–1.4 crore tons for FY25 |
| Full-year DRI volume guidance | ~330,000 tons for FY25 |
| Beneficiation pilot plant yield | 38%, producing 68% Fe output |
| All-inclusive cost (beneficiation, royalty, transport) | ₹2,800–3,000 per ton |
| Slurry pipeline transport cost to pellet plant | ~₹50 per ton |