Key Takeaways
- Integrated model delivered margin resilience: EBITDA margin expanded 348 bps QoQ as the slurry pipeline and captive pellet plant insulated the business from a weak steel cycle, even while Thriveni’s contribution disappointed.
- Pellet plant hit full utilisation in four months: The first 0.4 crore ton plant crossed 100% capacity in October, generating sustainable margins of INR4,000–5,000 per ton and validating the low-cost producer thesis.
- Thriveni’s H1 missed its own run-rate: Consolidated EBITDA margin came in at 16.5% vs a projected 33% because an extended monsoon crushed volumes, leaving fixed costs spread over a much smaller production base.
- The steel plant timeline is slipping, deliberately: Work now starts mid-to-end 2027, not earlier, while a Chinese consultant restudies the technology and product mix; management wants to enter on the other side of the cycle.
- What to watch next quarter: Whether Thriveni’s margin snaps back toward 30–33% as post-monsoon volumes recover, and if the DRI and secondary steel pricing rebound that management expects actually materialises.
The Integrated Model Is Working
- Slurry pipeline is the structural moat: The 85 km pipeline commissioned this year eliminates trucking, saves INR600 per ton versus competitors who pay INR1,000, and kept evacuation seamless through the monsoon when road logistics typically seize up.
- Pellet economics are built to last: Captive ore, the pipeline’s cost advantage, INR300–400 lower operating costs, and a INR200–300 per ton selling price premium combine to make INR4,000–5,000 per ton margins sustainable even if the pellet industry elsewhere is struggling.
- Gross margin question was deflected: When an analyst noted standalone gross margin had fallen to ~79% from a historical ~87–88%, management denied any reduction and said only that it “should improve further,” leaving the driver unexplained.
- The philosophy is long-cycle, not quarterly: Management explicitly frames every project for a 30-year horizon, which explains why it is willing to restudy the steel plant rather than rush to meet an earlier timeline.
Rajesh Gupta: “Our policy and our philosophy for all these projects remains the same, plan meticulously, execute swiftly, execute efficiently and build for the next 30 years, not for the 3 quarters.”
Thriveni: A Weak Start, A Confident H2 Promise
- Monsoon wiped out H1 volumes: Production ran 0.8–1.0 crore tons below forecast because the extended monsoon halted operations; since costs are overwhelmingly fixed (equipment, labour), the 16.5% EBITDA margin was barely half the projected 33%.
- Management is adamant the full-year guide holds: The INR8,000 crore revenue and ~INR2,800 crore EBITDA targets are intact, with the rebound resting on higher EC limits at client mines, Surjagarh ramping to 2.6 crore tons, and post-monsoon normalisation all concentrated in H2.
- Underlying quality is not in doubt: Thriveni holds a 5-star rating at all key mines and is inducting electric and LNG hybrid equipment, so the miss is framed as a volume-timing problem, not a structural one.
- Margin recovery is promised next quarter: Management expects a return to around 30–33% EBITDA margin from Q3 onward as volumes rise and fixed-cost absorption improves, though the commitment carries a vague timeline qualifier.
Steel Plant: Deliberately Slowing Down to Get It Right
- Work start pushed to mid-to-end 2027: The earlier slide deck suggested construction beginning Q1 FY27; management now says that date is for work to begin, not the plant itself, while land acquisition continues and a big Chinese consultant restudies the entire project.
- Product mix is back on the drawing board: The originally envisaged 0.3 crore ton HR coil plant with downstream cold rolling, galvanised, and colour-coated lines is being re-examined because of the technology upheaval of the last 3–4 years; the final mix and overall size are unsettled.
- The cycle-timing bet is explicit: Management hopes the current tough steel cycle will have passed by the time its plant starts, so the company enters “on the other side” and hits full swing from day one.
- Something smaller may come sooner: Before the steel plant, the company expects to commission something next year, though what that is remains unspecified.
Rajesh Gupta: “The steel industry is going through a tough cycle at the moment, and we hope to cross this by the time our steel plant starts so that when we are on the other side of a steel cycle, we are in full swing on the steel schedule as well.”
DRI and Secondary Steel: Waiting on a Coal-Led Recovery
- Current quarter remains subdued: Both DRI and the secondary steel market are suffering, with the only positive signal being that international coal prices have reached a bottom.
- Pricing recovery expected in 2–3 months: Management sees coal as the leading indicator and believes DRI pricing will come back over the next quarter, though the current period is still weak.
Rajesh Gupta: “The only rainbow that you’re seeing is a little reduction in coal price, which has reached its bottom, international coal. I think over the next 2, 3 months, the pricing will come back.”
The Project Pipeline: What Is Coming, What Is Late
- Pellet plant number two is in advanced stages, and a third is planned for FY28–29 alongside the third phase of the beneficiation plant.
- BHQ beneficiation plant is a first-of-its-kind project in India in difficult terrain; the first unit is now expected in the last quarter of next year, roughly plus/minus six months from the original schedule, with six modules to follow at one per month.
- BHQ mining will start before the plant: Management confirmed more BHQ mining will happen ahead of commissioning but declined to give exact figures, saying they would be known as mining progresses.
- 0.12 crore ton wire rod plant groundwork is progressing systematically.
- Two new Odisha mining projects (Indrani Patnaik and MGM Mines) have been proposed, and a 0.3 crore ton NTPC coal contract will start immediately this financial year.
- Madhya Pradesh coal mining remains under study with no update.
Capital Allocation and the Balance Sheet
- Capex is scaling steeply: INR4,500–5,000 crores planned for FY26, rising to INR6,000–6,500 crores in each of the next two years as the steel plant and beneficiation projects ramp.
- Debt is coming: An INR9,500 crore NCD issue is planned over the next six months, with a target debt level of ~INR8,000 crores and a debt-to-EBITDA ceiling of 1x.
- Negative cash conversion was flagged but not explained: An analyst noted consolidated cash conversion had turned negative while standalone remained positive; management attributed part to debt and working capital but could not provide details on the call and asked for a follow-up.
- Bharat Wire Ropes investment is purely financial: The CCPS acquisition targets an ~18–20% return with conversion expected within 18 months, carrying no strategic direction.
- Land purchase adds infrastructure flexibility: 290 acres acquired ~10 km from the Konsari factory will house existing dwellings and a switchyard station for MSEDCL support.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Iron ore volumes | Fill full EC capacity of ~2.2 crore tons | FY26 |
| Thriveni full-year revenue | INR8,000 crore | FY26 |
| Thriveni full-year EBITDA | ~INR2,800 crore | FY26 |
| Thriveni EBITDA margin recovery | Return to ~30–33% | From Q3 FY26 |
| DRI and secondary steel pricing recovery | Pricing to come back as coal has bottomed | Next 2–3 months |
| Pellet margins | Not below INR4,000 per ton, even at export parity | Next 3 months |
| Steel plant work start | Mid-to-end 2027 (not the plant itself) | Mid-to-end 2027 |
| BHQ plant first unit commissioning | Last quarter of next year, ±6 months from original schedule | FY27 last quarter |
| BHQ output | 1 crore tons from 3 crore tons input | By FY28 |
| Third pellet plant | Around time third beneficiation phase is commissioned | FY28–29 |
| Capex | INR4,500–5,000 crores (FY26), INR6,000–6,500 crores (next 2 years each) | FY26–FY28 |
| NCD issue | INR9,500 crores | Next 6 months |
| Debt target | ~INR8,000 crores at 1x debt-to-EBITDA | Unspecified |
| Bharat Wire Ropes CCPS conversion | ~18–20% return | Within 18 months |
| NTPC coal contract start | 0.3 crore tons | Immediately this financial year |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Total income (standalone) | ₹2,575.4 cr, up 75% YoY |
| EBITDA (standalone) | ₹869.3 cr, up 95% YoY; margin 33.75%, expanding 348 bps YoY |
| PAT (standalone) | ₹605.6 cr, up 22% YoY |
| Iron ore production | 0.34 cr tons; sales 0.25 cr tons, up 77% and 10% YoY respectively |
| Iron ore realization | ₹5,571 per ton, stable sequentially |
| Iron ore EBITDA per ton | ₹1,781, up 7% YoY |
| Pellet production | 0.08 cr tons; realization ₹9,916 per ton; EBITDA per ton ₹5,039 |
| DRI volumes | 88,200 tons, up 4% YoY |
| DRI EBITDA per ton | ₹3,150 |
| IPS benefit recognized | ₹94 cr |
| Slurry pipeline saving | ~₹600 per ton |
| Capex spent (H1 FY26) | ₹2,411.7 cr |
| Full-year capex guidance | ₹4,500 cr to ₹5,000 cr |
| Consolidated gross debt | ~₹7,980 cr, vs ₹756 cr in March; includes ~₹6,000 cr from Thriveni consolidation |
| Thriveni EBITDA margin (H1 FY26) | 16.5%, vs projected 33% due to lower production and fixed-cost absorption |
| Thriveni FY27 revenue guidance | ₹7,800 cr to ₹8,000 cr |
| Thriveni FY27 EBITDA guidance | ~₹2,000 cr, implying 30–35% opex EBITDA margin |
| Pellet plant capacity utilization | Crossed 100% in October with production of 350,000 tons |
| Iron ore dispatches guidance (FY26) | 2.0 cr to 2.2 cr tons |
| Self-consumption of iron ore (FY26) | ~0.8 cr tons for pellet, ~0.1–0.12 cr tons for DRI |
| Open market iron ore (FY26) | ~1.8 cr tons |
| Annual IPS benefit (forward-looking) | ~₹350 cr to ₹400 cr |
| Pellet EBITDA per ton floor | Not expected below ₹4,000, even at export parity |
| BHQ plant first unit commissioning | Last quarter of FY27; 1 cr ton output from 3 cr ton input by FY28 |
| Debt-to-EBITDA target | 1x |