Lloyds Metals & Energy Ltd Q3 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/lzd61tn16yzsxwtov0i5iqlj.pdf

Key Takeaways


The EC Gate: What Unlocks When

The entire growth narrative now hinges on one regulatory event. The public hearing was held on January 28 in Gadchiroli under the Maharashtra government's aegis, queries were addressed, and the company now awaits the district administration's outcome. Management's worst-case expectation is 60 to 70 days, with a broader 60-to-90-day window cited elsewhere.

Rajesh Gupta: "Execution has been one of our biggest strengths, having demonstrated this with the slurry pipeline, which is completed 85 kilometres, awaiting the pellet plant and the DRI plant completed last year in around 13, 14 months after the EC."

Iron Ore: The Profit Engine

Iron ore is where the quarter's margin story was made. Realizations improved 8% YoY to INR5,894 per ton in Q3, and EBITDA per ton rose 21% in both the quarter and the nine-month period. Dispatches reached 0.78 crore tons over nine months.


DRI & Steel: Managing the Cycle

The DRI segment faced headwinds as the secondary steel and scrap markets softened, pulling realizations lower. DRI sales volume fell 8% QoQ, but absolute sales dropped 48% QoQ because the prior quarter included a one-time industrial promotion subsidy of around INR70 crores for a prior period.


Beneficiation: The Long-Term Quality Play

The BHQ beneficiation plant is the bridge from a DSO miner to a producer of premium-grade ore. The pilot plant has run for eight months, consistently delivering Fe content above 66% with a 37% to 40% yield, better than original expectations. Primary engineering is complete and equipment procurement is in progress.


The Long-Term Vision: A Cyclical-Free Steel Business

Management laid out a structure designed to insulate the company from steel cycles. The model splits 2.5 crore tons of mined iron ore into roughly 1 crore tons sold as ore or pellets, with the balance converted into around 0.45 crore tons of steel and the rest as semi-products or pellets. The whole structure is to be built with very low debt, if any.

Rajesh Gupta: "Our long-term vision is to be a cyclical-free steel industry. At the same -- how we will achieve that is, by very, very low debt, if any, number one. Number two, we'll have a part of the iron ore that we mine will be sold as either iron ore or as pellets and part will be sold as steel."

Competitive Position & Cost Edge

Management was repeatedly pressed on cost comparisons with peers and declined to provide specifics, but framed its advantage around the auction premium others pay. The six mines auctioned in Gadchiroli went at roughly a 110% premium to revenue, a burden Lloyds does not carry.

Rajesh Gupta: "As far as I'm aware that the 6 mines have been auctioned at a premium of around 110% of the revenue. So, if I'm selling at around INR4,000 average, their cost would be around INR4,000 into 1.1x extra over and above mine, which I do not have to pay."

Guidance & Commitments

CommitmentSpecificsTimeline
Mine EC approvalPublic hearing completed; worst-case expectation 60 to 70 days, broader range 60 to 90 daysWithin 60 to 90 days
FY25 iron ore dispatches~0.22 crore tons in Q4, total ~1 crore tons for FY25FY25 end
Mining ramp-up post-EC0.2 crore tons per month excavation and loading; first 1.5 to 2 years as DSO onlyImmediately on EC receipt
MDO cost savingsINR400 to INR500 per ton on iron ore sideEffective 1st April 2025
MDO business revenueThriveni MDO revenue to rise from ~INR5,500 crores to ~INR8,000 crores; Lloyds Metals contribution ~INR2,500 croresNext financial year (FY26)
Ghugus DRI and pellet plantCommissioning and testing startedLatest by Q4 FY25 end or early Q1 FY26
First BHQ beneficiation module1.5 crore ton module physically feels like 2027 completion2027
FY28 end-state2 beneficiation plants, ≥0.8 crore tons pellet, 0.12 crore tons steel at ChandrapurFY28 end
Revenue targetINR40,000 crores, with MDO revenue over and aboveFY28 or FY29
DSO reserve life managementReduce DSO to 1 crore tons per year from third year to preserve 15.7 crore ton reserve for 35 yearsStarting third year post-EC

Key Metrics

MetricQ3 FY25
Revenue growth11% YoY for 9M FY25
EBITDA growth31% YoY for 9M FY25
Iron ore realization₹5,894 per ton, +8% YoY
Iron ore EBITDA per ton₹2,021, +21% YoY
Iron ore dispatches0.24 crore tons in Q3; 0.78 crore tons in 9M FY25
DRI production78,000 tons in Q3; 239,000 tons in 9M FY25
Raw material cost as % of sales8% in Q3 FY25, vs 21% in Q3 FY24
Capex spent₹2,700 cr in 9M FY25; ₹4,400 cr total till date
Closing iron ore inventory0.04 crore tons
FY25 iron ore mining guidance~1 crore ton for full year; Q4 implied at ~0.22 crore tons
MDO cost saving expectation₹400–500 per ton on iron ore, effective 1 Apr 2025
DSO reserves15.7 crore tons (JORC-certified); BHQ reserves ~70 crore tons
BHQ beneficiation pilot plant yield37% to 40%, Fe content 66% and beyond
Thriveni MDO current capacity7.1 crore tons, expected to rise to 12.5 crore tons with EC increase
Thriveni MDO revenue~₹5,500 cr currently; expected ~₹8,000 cr next FY; Lloyds contribution ~₹2,500 cr