Lloyds Metals & Energy Ltd Q4 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/9sbu2z0mrd1j8uiqtrw63k4b.pdf

Key Takeaways


The 5.5 Crore Ton Mine Expansion

Rajesh Gupta: "Looking ahead, our road map to 5.5 crore is going to be one of its kind in the Indian iron ore space. We shall be single location mine operating at this scale."

Forward Integration into Steel


The Logistics Moat

Rajesh Gupta: "I always say one thing, my friend, that steel is more of a logistics game than steel itself."

Cost Structure & Competitive Position

Rajesh Gupta: "Our mines will fetch no premiums royalty till 2057, which is a big differentiator from every other steel maker in the country today except one."

Capital Structure & Funding


Guidance & Commitments

CommitmentSpecificsTimeline
Iron ore expansion approvalsIBM plan approval and environmental clearance for mine expansionBy end of FY25
FY25 iron ore volume1.2 to 1.3 crore tons (1 crore minimum, balance pro-rata on approvals)FY25
Chandrapur DRI and power plantTwo DRI units and 2×30 MW power plant operationalMarch 2025
Chandrapur steel plant0.12 crore ton wire rod plant operational1.5 years after DRI units
Ghughus slurry pipeline185 km pipeline operationalMarch 2028-29
First beneficiation plantFull-scale beneficiation plant operationalFY27-28
Maharashtra incentivesPhased incentives totaling ~Rs. 2,500 crore, capped at 110-150% of capexBy 2030-31

Key Metrics

MetricQ4 FY24
Revenue₹6,000 cr for FY24, +90% YoY; Q4 growth +74% YoY
EBITDA+153% YoY in Q4; +101% YoY for FY24
Profit after taxSurpassed ₹1,000 cr for FY24
Iron ore EBITDA per ton₹2,375 in Q4; ₹1,710 for FY24
ROCENorth of 50%; exceeds 100% adjusted for CWIP
Iron ore production1 cr tons for FY24, a record
Iron ore dispatches1 cr tons for FY24
DRI production2,60,000 tons for FY24
Power sales18.8 cr units for FY24
CAPEX incurred~₹1,700 cr in FY24
Dividend100%, ₹1 per share
Gross debtDebt-free, expected to remain so through ₹33,000 cr CAPEX plan
FY25 iron ore volume outlook1.2–1.3 cr tons, 1 cr minimum plus pro-rata if approvals received
Slurry pipeline progress50% complete on 85 km Hedri-Konsari pipeline