Key Takeaways
- Presales doubled, driven by launch velocity: 9M FY23 presales hit ₹1,452 crores, a 100% like-to-like increase, powered by four launches including projects brought forward by strong demand.
- Demand is splitting by price point: Management flagged constriction in the sub-₹40 lakh segment due to higher mortgage rates and inflation, while the mid-market segment continues to grow significantly.
- Margins are improving on new launches: Recent projects are delivering profitability 4–5 percentage points above the ~18% guardrail, driven by better cost control and superior net realizations.
- The BD engine is active but conversion is binary: A ₹5,500 crore GDV pipeline is in play, with a hard two-quarter conversion window; anything not converted gets dropped.
- What to watch next quarter: The Q4 spillover from the December Kalyan-2 launch, conversion of the carried-over ₹2,500 crore BD pipeline, and any further softening in the affordable segment.
Residential Demand & Launch Momentum
- Launch cadence accelerated: Four projects launched in 9M FY23, including Mahindra Eden Phase 2 in Bangalore, which was pulled forward by nearly a year after Phase 1 saw outstanding response and a ~14% price increase.
- Pricing power evident: Mahindra Happinest Chennai Phase 2 launched with a >20% price increase over Phase 1, which was fully sold.
- Execution speed improving: Mahindra Citadel in Pimpri, Pune went from land acquisition in April 2022 to launch in November 2022, with designs and approvals completed in seven months.
- Affordability pinch is real: Management openly acknowledged demand constriction in the sub-₹40 lakh segment, attributing it to higher mortgage rates and inflation pinching affordability, while the mid-market segment grows quite significantly.
- Spillover into Q4: The Kalyan-2 launch occurred in December, so a material portion of its bookings will reflect in Q4 numbers; management declined to quantify the spillover quantum.
Subramanian: "I must openly state that we are starting to see some constriction of demand in that segment of the market, the sub INR 40 lakh kind of segment."
Business Development & Land Pipeline
- Two new wins announced in January 2023: A land parcel on Hosur Road, Bangalore and a society redevelopment project in Santacruz, Mumbai, marking the company's first breakthrough in the society redevelopment space.
- BD pipeline mechanics: The company is working on a pipeline of ~₹5,500 crores GDV, with a further ₹2,500 crores carried over from the prior pipeline. Conversion typically happens within two quarters; if a deal does not convert in that window, it gets dropped.
- Redevelopment is a new, slower vector: Society redevelopment deals take significantly longer than land transactions because decisions involve 100-plus members making a joint, highly emotive decision. The company structures deals so significant costs start only after full site vacation, keeping IRRs healthy.
- Land conveyance completed: Conveyance of the Kandivali land (purchased from M&M) and the planned 60 acres at Thane (Ghodbunder) was completed in Q3 FY23.
- GDV uplift in existing land: Development potential of the Pimpri land was enhanced, with GDV revised upward from ₹1,700 crores to ₹2,300 crores.
- Murud land (1,300 acres) under evaluation: Two growth axes are being assessed: second-home market expansion from Alibag toward Kashid and Murud, and industrial opportunity from the Dighi port expansion hinterland; eventual development will combine both.
Subramanian: "Our experience has been gets converted within 2 quarters, then if it doesn't get converted in 2 quarters, it gets stopped."
Launch Pipeline & Project Timelines
| Project | Timeline | Status |
|---|---|---|
| Mahindra Nestalgia Phase 2 (Pune) | Q4 FY23 | Launch this quarter |
| Plotted development (MWC Chennai) | Q4 FY23 | First plotted launch for the company |
| Mahindra Citadel full launch (Pimpri) | H1 FY24 | Pre-launch done in Nov–Dec; main launch ahead |
| Kandivali project | H1 FY24 | On track |
| Hosur Road, Bangalore | H1 FY24 | New acquisition; to market in H1 |
| Dahisar project | Later in FY24 | |
| Santacruz redevelopment | Later in FY24 | First society redevelopment win |
| Thane (Ghodbunder) | Early FY25 | On track, unchanged |
| Ahmedabad | No timeline | Work in process; looking for right anchor; no headway yet |
- Plotted development as a new format: The Chennai plotted launch this quarter is the company's first; new BD in the plotting space is being explored, particularly in Bangalore and Pune.
- Annual GDV addition target: Management expects to add ₹3,000–4,000 crores of GDV annually for the next year or two.
Industrial Leasing & Warehousing
- Leasing pickup in Chennai: Q3 industrial leasing of ₹69 crores was driven by a pickup in Origins, Chennai and Mahindra World City, Chennai, after prior quarters concentrated in Jaipur.
- Advanced leasing pipeline: ~50 acres of advanced pipeline is expected to convert over the next two quarters.
- MWC Chennai realizations dipped: Realization came down because transactions involved outside-boundary lands beyond planned World City boundaries, with no infrastructure extended there, commanding significantly lower prices; management expects this pattern to continue.
- Actis warehousing JV progressing: The company has been incorporated and the management team is being built out; key leadership is expected in place in the next three months, after which seed assets and greenfield assets will be brought in.
- SEZ (Desh bill) opportunity: Rules are awaited on opening up SEZ units to serve the domestic market; clarity is expected in the next few months.
Margins, Costs & Balance Sheet
- New launch margins improving: The last two launches performed 4–5 percentage points better than the ~18% profitability guardrail, driven by stronger cost control, active design and costing interventions for more accurate estimations, and superior net realizations.
- Employee cost decline is accounting, not headcount: 9M FY23 employee remuneration fell to ₹61 crores from ₹66 crores in 9M FY22 despite revenue growth, because of higher inventorization of costs tied to launches and cost allocations across projects and entities for tax structuring; headcount actually increased.
- Net debt rose on land funding: Residential net debt rose sequentially by ~₹121 crores, driven by land acquisition funding requirements including Thane land conveyance payouts to state authorities and part consideration for Kandivali.
- Operating cash flow healthy: ₹450 crores positive in 9M, driven by solid IC leasing (~₹254.85 crores) and strong collections and sales; the majority was deployed toward new land parcels or buying more development potential in existing parcels.
- Leverage philosophy: Management will remain prudent about leverage and stated finance will never be a constraint; if good land parcels are available, the company will invest. Long-term borrowing will start being seen, but no specific quantum was disclosed.
Agarwal: "Our going in position say from, especially from finance point of view, is that will never be the constraint so far as we are getting good land parcels we will go ahead and invest."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Q4 FY23 launches | Two projects: Nestalgia Phase 2 (Pune) and plotted development (MWC Chennai) | Q4 FY23 |
| BD pipeline conversion | Reasonable proportion of ₹5,500 cr GDV pipeline to convert; ₹2,500 cr carried-over pipeline to convert or drop | Next 2–3 quarters |
| Industrial leasing pipeline | ~50 acres of advanced pipeline to convert | Next 2 quarters |
| FY24 launch cadence | Kandivali, Mahindra Citadel full launch, Hosur Road to market in H1; Dahisar and Santacruz later in FY24 | FY24 |
| Thane launch | Ghodbunder project to market | Early FY25 |
| Annual GDV addition | ₹3,000–4,000 cr range | Next 1–2 years |
| FY25 residential pre-sales | ₹2,500 cr target remains; management would like to do better but wants land visibility to build up before updating | By FY25 |
| Actis warehousing JV | Key leadership team in place, seed and greenfield assets brought in | Next 3 months |
| SEZ Desh bill clarity | Rules on opening SEZ for domestic market expected | Next few months |
Key Metrics
| Metric | Q3 FY23 |
|---|---|
| Residential presales | ₹451 cr, bringing 9M FY23 to ₹1,452 cr; 100% growth on a like-to-like 9M basis |
| Industrial leasing | ₹69 cr, taking 9M FY23 leasing to ₹255 cr vs full year FY22 of ₹297 cr |
| Consolidated total income | ₹198 cr, up from ₹74 cr in Q3 FY22 |
| Consolidated EBITDA | Profit of ₹5.5 cr, compared to profit of ₹20 cr in Q3 FY22 |
| 9M FY23 operating cash flow | ~₹450 cr positive, after all operating costs including corporate overheads |
| 9M FY23 revenue (excl other income) | ₹351 cr, up from ₹241 cr in 9M FY22 |
| 9M FY23 employee remuneration | ₹61 cr, down from ₹66 cr in 9M FY22 due to inventorization and cost allocation optimization |
| Land acquisition cost incurred in 9M FY23 | ~₹400 cr, with a similar amount pending |
| GDV addition FY23 YTD | ₹3,100 cr (including Pimpri GDV uplift from ₹1,700 cr to ₹2,300 cr, per an analyst's math) |
| Business development pipeline GDV | ~₹5,500 cr, split as Mumbai ₹2,500 cr, Pune ₹2,000 cr, Bangalore ₹1,000 cr |
| Pipeline structure split | ~₹3,500 cr outright, ~₹1,000 cr JDA, ~₹1,000 cr redevelopment and plotted |
| Advanced industrial leasing pipeline | ~50 acres to be converted over the next 2 quarters |
| New project profitability guardrail | ~18% or upwards (all costs taken), about 4–5 percentage points better than older projects |
| Residential net debt increase (sequential) | Up ~₹121 cr as of 31 Dec vs 30 Sep, driven by land acquisition payments |
| Amount shared with external stakeholders in 9M FY23 | ~₹200 cr, including IFC World Bank, Actis, and other partners |