Key Takeaways


Revenue & Order Book

Narayana Murty: "Whatever little decline was there in Q2 performance due to non-booking of some products in WIP, they will be able to liquidate them in Q3; moving forward at targeted ₹1,300 crore sales as told during Q1 time."

Strategic Announcements

Narayana Murty: "This is the lightest bulletproof jacket that currently is in existence."

Exports & Certification

Narayana Murty: "Deliberately we have not booked some of the orders, even though we've been approached here, because the typical time line for processing of — I mean the import order is about 3 to 4 months. They want material very quickly."

Margins & Capacity

Narayana Murty: "It is not the question of capability. Capability exists. We have a very strong R&D team in Midhani. We have wealth of knowledge. We have profit sheets for so many grades. It is only question of infrastructure."

Growth & Capex Plans

Narayana Murty: "Yes, so basically, it is like that. By the time... once we install the new facilities, we expect it to be higher on a very conservative note, I'm revealing this 10% figure. Yes, we want to have better figures. In the coming years, you will see a bigger growth."

Revenue Mix & Competition

Narayana Murty: "There is enough market for everyone to grow, okay? It is not that competition. There is a significant business. I told you previously, there is INR8,000 crores worth of materials are getting imported. The cake is big, so people can — people have opportunity to participate."

Guidance & Commitments

CommitmentSpecificsTimeline
FY26 top lineReach ₹1,300 crores in salesFY26 (Q3 and Q4 execution)
FY26 EBITDA marginAround 23% overallFY26
Q3 revenue recoveryLiquidate WIP that caused Q2 declineQ3 FY26
Order pipeline conversion₹500 crores from tenders already participated inBy March 2026
Additional defense/navy ordersAnother ₹500 crores expectedBefore March 2026
Opening order book FY27At least ₹2,000 crores minimumApril 2026
Capex plan detailsDetailed figures to be sharedEnd of Q3 / next conference call
Metal Bank installationFacility installed within Midhani campusWithin 6 to 8 months
ABHED jacket readinessReady for receiving ordersWithin 6 months
NADCAP certificationCertification completedBy Q4 FY26
Annual growthAt least 10% every yearOngoing
Export share in order bookAt least 10% to 15%Coming 2 to 3 years
Export revenue potential₹100-150 crores every yearOnce raw material issues settled
Global aero engine ordersPosition to get orders post-certificationPossibly within 6 months

Key Metrics

MetricQ2 FY26
Turnover₹209.73 cr, against ₹262.12 cr in Q2 FY25
Turnover (H1 FY26)₹380.22 cr, against ₹425.57 cr in H1 FY25
Value of production₹256.38 cr
Value of production (H1 FY26)₹497.67 cr, growth of 3.9% YoY
Profit before tax₹19.13 cr
Profit before tax (H1 FY26)₹38.12 cr
Profit after tax₹12.77 cr
Profit after tax (H1 FY26)₹25.58 cr
EBITDA margin (H1 FY26)21.82%
PAT margin (H1 FY26)6.73%
Order book₹2,220 cr as on Nov 14, 2025; ₹1,869 cr as on Oct 1, 2025
Order book composition70% defense, 20% space, 10% energy and others
Revenue mix by alloySuper alloys 21%, titanium alloys 19%, maraging steel 15%, specialty steel 37%, other grades 8%
Titanium order book₹600 cr
Super alloys order book₹450 cr
Order pipeline₹500 cr in tenders participated, expected realization by March 2026
FY26 top-line target₹1,300 cr, management reiterated confidence
FY26 EBITDA margin guidance~23%
Exports (FY25 full year)₹94–95 cr worth of orders
Exports (H1 FY26)₹21 cr supplied
Current export order book~₹25 cr being executed
FY26 exports estimate~₹50 cr, lower due to raw material constraints and geopolitical disruptions
Rohtak facility revenue (H1 FY26)~₹12 cr till October, with another ~₹40 cr visibility
Virgin material to scrap ratio60% to 40%
Expected order book opening balance (Apr 2026)At least ₹2,000 cr
Additional orders expected by Mar 2026₹500 cr from defense and navy, over and above ~₹990 cr already booked