Key Takeaways
- Earnings hit by price, not operations: Nine-month PAT fell to INR175 crores from INR266 crores, driven entirely by lower net sales realization which MOIL does not control. Production grew to 14.21 lakh tons.
- Production engine is running, sales lagged: Nine-month production rose 6.8% YoY while sales declined to 10.84 lakh tons, partly due to a higher proportion of lower-grade output that the company is now learning to monetize.
- Balaghat shaft delayed again: The high-speed shaft, critical to the 2030 production target, needs another six months in the next financial year to become operational. Visa and COVID issues caused the slip.
- Cost structure is a genuine moat: Management claims one of the world's most competitive cost bases, and is driving it lower through headcount reduction, outsourcing, and a shift to long-hole open stoping.
- What to watch next quarter: Whether the Balaghat shaft commissioning timeline holds, progress on beneficiation partnerships for low-grade inventory, and any concrete step on the INR275 crore overseas acquisition plan.
Price & Demand Environment
- NSR drove the profit decline: Revenue fell to INR1,056 crores from INR1,152 crores and PBT to INR223 crores from INR362 crores, "basically due to fall in the NSR, which is not controlled by MOIL. It is usually controlled by the demand of steel and LME."
- Demand is not the problem: Raipur demand is "excellent" and continuously growing; the Central region now depends on imported ore as well. Whatever MOIL produces gets sold, with no demand constraint visible.
- Central region logistics advantage: MOIL is very competitive in the Central region because imported ore costs at least INR1,500 per ton extra in logistics. The company cannot even reach Vizag and Durgapur because there is enough demand in the Central region, with space to grow by another 0.15 crore tons within that geography.
- International price drivers: Chinese port inventory is currently low at 0.43-0.44 crore tons, South32's Groote Eylandt jetty remains destroyed 1.5 years later, South Africa's Transnet railway has allocation issues, and South African and Gabonese miners control output to keep prices at certain levels.
- Pricing premium maintained: MOIL prices are always kept 5%-6% higher than imported prices for comparable grades (37% or 44%), with a 2% premium over index movements as standard practice. Average NSR comparisons are misleading because of product mix differences.
Rashmi Singh: "We are very, very competitive in the Central region, and there is space to grow by another 0.15 crore tons within the Central region for MOIL."
Production Growth & Project Delays
- Nine-month production rose: Output increased to 14.21 lakh tons from 13.31 lakh tons YoY, while sales declined to 10.84 lakh tons from 11.40 lakh tons. The gap between production and sales is not more than 2 lakh tons.
- Balaghat high-speed shaft delayed: Shaft sinking is completed, equipping completed, winder installation ongoing. Expected operational in six months in the next financial year. Delay attributed to visa issues related to Chinese personnel and COVID. Management did not give a direct yes/no answer on whether the shaft has physically reached the ore body.
- Balaghat current production clarified: Current production at Balaghat is around 3.5 lakh tons, not 6.5 lakh tons as an analyst assumed. The EC is for 6.5 lakh tons. The high-speed shaft will take around five to six years to reach its highest production capacity of ~8 lakh tons.
- Gumgaon vs Balaghat confusion resolved: Management clarified that the earlier guidance of "in three months we will be doing" referred to Gumgaon mine, not Balaghat. Gumgaon mine winding system is already commissioned.
- FY27 production target: Next year's target is 25 lakh tons for the whole of MOIL. Management is working on that and believes it will be achieved, with the two shaft projects (Balaghat and Gumgaon) to be commissioned "in this year and the next year."
- New shaft ramp-up is slow by nature: To achieve maximum capacity of new shafts will take at least five years, as production grows slowly with phases developed month by month. After Balaghat and Gumgaon projects come into high steam with mechanization and method change, production rise will be "much more than" 38%.
- Dongri Buzurg conversion: MOIL's biggest opencast mine will convert to underground mining within five years, with new shafts being developed.
Rakesh Tumane: "See what happens when the things go bad, they go bad. Whatever you do, they do not get resolved."
Low-Grade Strategy & Beneficiation
- Low-grade proportion has risen: In the past few months, the proportion of lower grades in production has slightly gone up. MOIL has been quick to find markets for those lower grades, with 50% growth in low-grade sales this year. Low grades are used for blending with imported high grades.
- Beneficiation is the answer: MOIL has stocks of 10% to 20% grade material and is mulling setting up beneficiation units within its mines to add value rather than sell low grades. A partner would require a commitment of ~3 lakh tons per annum for 3-4 years to set up a beneficiation plant, and MOIL is now in a position to possibly commit such volumes.
- No panic selling: MOIL does not panic-sell low grades; it holds inventory and waits for opportune moments. There is no dearth of storage space. Ex-mine price for domestic and export is the same, so MOIL does not sell cheap internationally.
- Export channel now open: Government appointed MOIL as the state trading enterprise for all exports of manganese ore from India in February 2024. Three shipments have already been exported, and MOIL has recently booked one parcel of 60,000 tons of its own low-grade ore for exports.
- Briquetting also in focus: The company is working on making briquettes so low grades can be utilized in better form, alongside beneficiation.
Rashmi Singh: "We want to convert this waste to wealth and this year the focus will be on beneficiation."
Cost Structure & Efficiency
- Cost of production is a claimed strength: Management states the cost of production is "one of the most competitive" globally, in the Q1 kind of cost range. Underground mining is more costly than opencast: opencast cost is ~INR4,200/ton vs overall ~INR5,500/ton.
- Headcount reduction underway: Employee count has dropped from ~6,000 to ~5,200. The company is moving to more outsourcing, mechanization (LHDs, SDLs), and changing mining method from conventional cut and fill to long-hole open stoping, which is 5x to 10x more productive. Manpower is ~48% of cost of production, so cost will go down as production increases with lesser manpower.
- No MDOs used: MOIL does not use any MDOs because all mines are old, continuing mines. Core mining activity is done by company people; ancillary operations like loading rock and supporting works are done contractually.
- Wage revision impact expected to be offset: Wage revision for officers starts 1st January 2027, for workers August 2027, but negotiations typically push to next year. Management argues mechanization and employee count reduction will offset the impact, so cost per ton may not rise despite absolute wage cost increase. Employee cost increased only ~2% in 9 months, not the normal 5% assumed.
- Capex trajectory: For existing mines, capex will be ~INR350-INR400 crores every year. Next year capex target is ~INR800 crores, with INR350 crores for modernization and the remaining for overseas acquisition. Four new/five shafts (three production, two ventilation) will also require capex in coming years.
Rakesh Tumane: "Whatever number of hike we say, that is an absolute amount, right. That would be absolute amount on the wage cost itself, okay. But when you talk about the cost per ton, that rise would not be there."
Expansion & New Ventures
- 2030 production target: MOIL committed to produce around 0.35 crore tons of manganese ore by 2030, increasing market share from 20% to around 32%. EC expansion is expected to increase the limit from 36.33 lakh tons to 50 lakh tons to support this.
- GMDC JV in advanced stage: Approval received from DIPAM and NITI Aayog for JV formation; Government of Gujarat has forwarded the file for allocating lease area in favor of GMDC so the JV agreement can be initiated.
- Madhya Pradesh JV progressing: Draft JV agreement signed with Government of Maharashtra and Madhya Pradesh Steel Mining Corporation Limited in 2024; approval received from DIPAM and NITI Aayog for formation of JVC; JVC in process for approval.
- Ore bodies established: Successfully established ore bodies in Bhudkum block and Selva block (Chhindwara and Balaghat Districts). Nilkanthpur block core drilling completed (11,628 meters) with some positive results, though drilling is currently suspended due to local issues.
- Overseas acquisition planned: MOIL is looking for property abroad and has marked INR275 crores for overseas acquisition. Management is working on getting overseas assets.
- Profit ambition: Management stated the INR500 crores profit number "is not far off" and will be "much more than that," though no timeline was given.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Balaghat high-speed shaft operational | Shaft to become operational after equipping and winder installation | Six months into next financial year |
| FY27 production target | 25 lakh tons for whole of MOIL | FY27 |
| 2030 production target | 0.35 crore tons, market share from 20% to 32% | By 2030 |
| EC limit expansion | From 36.33 lakh tons to 50 lakh tons | To support 2030 target |
| Dongri Buzurg conversion to underground | Opencast mine converts via new shafts | Within five years |
| Balaghat ramp-up to peak capacity | High-speed shaft reaches ~8 lakh tons capacity | Five to six years after commissioning |
| Capex for current year | INR325 crores for capacity enhancement, modernization, mechanization | Current year |
| Next year capex | ~INR800 crores (INR350 crores modernization, remainder for overseas acquisition) | Next year |
| Overseas acquisition budget | INR275 crores marked | No date |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Revenue from operations (9M FY26) | ₹1,056 cr, vs ₹1,152 cr in 9M FY25 |
| Total revenue (9M FY26) | ₹1,126 cr, vs ₹1,238 cr in 9M FY25 |
| Profit before tax (9M FY26) | ₹223 cr, vs ₹362 cr in 9M FY25 |
| Profit after tax (9M FY26) | ₹175 cr, vs ₹266 cr in 9M FY25 |
| Production (9M FY26) | 14.21 lakh tons, vs 13.31 lakh tons in 9M FY25 |
| Sales volume (9M FY26) | 10.84 lakh tons, vs 11.40 lakh tons in 9M FY25 |
| Cost of production (factory gate, ex royalty) | ~₹5,300 per ton (FY26), vs ~₹5,500 per ton in FY25 |
| FY26 production target (revised) | 19–20 lakh tons, revised from 23.5 lakh tons; FY27 target is 25 lakh tons |
| FY26 capex target | ~₹600 cr (MOU target): ₹325 cr for mine modernization, ₹275 cr for overseas acquisition |
| Interim dividends declared | ₹1.80 (first) and ₹3.53 (second) per share |
| Low-grade ore sales growth | ~50% YoY growth for each of the last three years |
| Employee cost increase (9M FY26) | ~2% YoY |
| Average return on equity | 161% over the last 10 years |
| Chinese port inventory | ~0.43–0.44 cr tons, down from ~0.6 cr tons earlier |