MTAR Technologies Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/xmnh4cyurnqsbbiw6gqo4ht6.pdf

Key Takeaways


The Bloom Energy Correction

Srinivas Reddy: "This is just a temporary correction what they have made. And when we are phasing out from Yuma to Santa Cruz, it's a matter of one or two quarters."

Margins: The Investment Overhang

Srinivas Reddy: "I would not say like 29%, 30%, but definitely, we'll proactively look at how we can actually margin close to about 28%."

Fluence: The Next Clean Energy Leg

Srinivas Reddy: "So, final negotiations are going on. This is purely for export as well as for domestic. And in the long run, they want us to build facilities in a manner in which they can go up to about 3,000 units plus per year for their export and domestic requirements."

Domestic & Nuclear: The H2 Surge


New Engines: SSLV, New Customers, Import Substitution

Srinivas Reddy: "We have done a phenomenal progress. We are right on track with our milestones. And probably, I would ask my senior project director, Dr. Vedachalam to update all of you in the next call."

Order Book & Growth Visibility

Srinivas Reddy: "It's too premature to tell exactly the kind of growth we're looking at next year. But we are looking at definitely a reasonable and good amount of growth for next year. If I say, like, 30% to 40%, I'll be saying approximately, but I'll have more clarity by the end of, by next quarter."

Guidance & Commitments

CommitmentSpecificsTimeline
EBITDA margin26%, plus-minus 100 bpsNext two quarters
EBITDA margin targetClose to ~28%Over the next one year
Fluence deal closureFinal negotiations to closeThis quarter
Santa Cruz rampRamp to 528 units of Block 2Ongoing; Block 2 is the final version
Kaiga 5 & 6 order finalization~INR500 crores expected from 17 packages bidProbable by end of December
Closing order bookINR1,400-1,500 croresBy end of this year
Santa Cruz Block 2 stabilityNo further model changes expectedAt least next four to five years
Deferred Bloom shipmentsYuma-to-Santa Cruz deferred units executedNext fiscal year

Key Metrics

MetricQ2 FY24
Revenue from operations₹166.8 cr, +32.2% YoY
EBITDA₹36.1 cr, +3.4% YoY
Profit before tax₹25.7 cr, -22.1% YoY
EBITDA margin guidance (full year)26%, plus-minus 100 bps; revised down from 28%
Full-year revenue guidance₹370–400 cr, with ₹140–150 cr from domestic and rest from export
Order backlog (current)₹1,000 cr
Closing order book target (FY24)₹1,400–1,500 cr
New orders needed (H2 FY24)~₹800 cr over the next five to six months
Bloom Energy hotbox deferral~1,200 units moved from FY24 to FY25 delivery
Hotbox deliveries (Q2 FY24)~400 units of Yuma and ~200 units of Santa Cruz Block 1
Santa Cruz Block 2 ramp-up target528 units anticipated for the current quarter
Electrolyzer dispatches44 units this quarter, ~66 units next quarter
Fluence initial order~1,000 units for next year, roughly ₹120–130 cr range
Payable days49 days, reduced from 108 days
Space and defense share of order book18%