National Aluminium Company Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/xttda64vrdmq3zpq2ion07sb.pdf

Key Takeaways


Cost Headwinds and the H2 Recovery Plan

Behuria: "In the first half of this year, there was adverse impact of techno-economic, so which will be taking action for the next step. That will give reduction cost by a little above INR500 to INR1,000 alumina cost."

Alumina: Export Disruption and Pricing

Singh: "Ultimately, everything depends on almost blockage because there is a demand of alumina in the Middle East, but the vessels are not going through those blockages. So, due to which the insurance charges have increased, the shipment charges have increased. So that's why the buyers -- the spot buyers who are buying, they are quoting somewhat low. If the situations get improved, then the prices may further increase."

5th Stream Refinery and Growth Projects

Singh: "That's some kind of resistance we are getting from the locals and local activities, but it is taken at the highest level when the -- our ministry, state government, they are seeing it. They are negotiating with the people, and we are hoping that within two, three months, we'll be able to solve this issue and start the mines."

Aluminium and LME Outlook

Singh: "At the beginning of the year also, we have assumed that the LME will be somewhere around INR3,000 -- INR2,900 to INR3,000. Due to war it went up but our annual target, whatever we have taken annual business plan, that we are expected that INR3,000 and we are very much confident that it will remain somewhere around INR3,000."

Margins and Structural Cost Position

Behuria: "NALCO will be maintaining the same margin level in the next 3, 4 years, and till our new smelter is commissioned."

Mine Life and Lease Renewal

Behuria: "There is a provision in the Act for renewal. But additional royalty, they may impose upon because they cannot take out this mines and go for bidding. They got into the captive management. It's captive when our whole refinery and plant is dependent on this. So, there's a legal provision also in the Act."

Guidance & Commitments

CommitmentSpecificsTimeline
5th Stream refinery startIntegrated trial and start of productionLast week of December or early January
5th Stream refinery ramp-upRamp-up to full capacity3–5 months from start
5th Stream refinery FY28 production0.08 crore tonsFY28
Alumina cost reductionINR 500–1,000 per ton reduction via 6–7 kg lower caustic soda consumptionH2 FY27
H2 PBT upliftINR 300–350 crores extra from new refinery, techno-economic gains, and non-repeat of royaltyH2 FY27
Alumina export normalizationReturn to ~4 vessels per monthFrom November onward
Utkal coal production0.48 crore tonsFY27
Utkal environmental clearancesMoEFCC clearanceNext two months
Pottangi mines startResolution of local resistance and start of mining2–3 months
Pottangi long-distance conveyorCompletion2–2.5 years
Brownfield smelter DPRDPR completionJanuary–February
Brownfield smelter board approvalBoard approvalFebruary
Brownfield smelter package orderingAll packages orderedDecember next year
Brownfield smelter mechanical completionMechanical completionDecember 2030
Brownfield smelter commissioningCommissioningQ1 2031
NLC power plant JVDPR to boardNext 2–3 months
FY27 capexMore than INR 1,800 croresFY27
Year-end cash balanceINR 12,000 croresMarch 2027
Pay revision bookingBooked for three months (Jan–Mar) at least 15% increaseQ4 FY27
Alumina spot price expectation$370–380 average, not more than $350 in export market beyond FY27FY28 and beyond
Margin sustainabilitySame margin level maintainedNext 3–4 years until new smelter commissioned

Key Metrics

MetricQ2 FY27
H1 Revenue₹11,143 cr, all-time high
H1 EBITDA₹5,539 cr, all-time high
H1 PBT₹5,160 cr, all-time high
H1 PAT₹3,837 cr, all-time high, up 54% YoY
Q2 Net Profit₹1,835 cr, up 28% YoY
Alumina H1 average realization₹33,200 per ton; H2 expected ~₹35,000
Alumina spot price expectation$370–$380 per ton average; not more than $400
Alumina full-year production guidance0.245 crore tons (0.25 crore tons)
Aluminium pricing basisLME-linked, revised every 3 days; ~95% domestic customers on MOU
LME assumption for annual business plan~$3,000 per ton
Captive coal production target FY270.48 crore tons; H1 achieved 0.21 crore tons
Power and fuel cost increase H1 YoY₹317 cr increase; fuel oil in refinery contributed ₹256 cr of that
Purchase power cost H1₹123 cr, up from ₹50 cr last year
Other income QoQ change+43% QoQ, driven by higher interest income on deposits and wind power
Total capex plan FY27~₹1,800 cr; H1 completed ~₹800 cr
Expected cash balance at fiscal year-end₹12,000 cr
5th Stream refinery startLate December 2026 or early January 2027; integrated trials then
Smelter brownfield expansion total investment~₹25,000 cr (smelter ~₹17,000–18,000 cr plus power plant)
Alumina exports volume changeDown 16% YoY; October only 1 vessel dispatched vs normal 4 per month
Caustic soda price Q3 projection~₹49,000 per ton, up from ~₹47,000 in H1
CP coke price Q3 projection₹70,600 per ton, up from ₹63,700 in H1
Employee cost expectation FY27Lower than FY26, despite 15% pay revision for 3 months, due to retirements and new hires at lower scales
Bauxite reserves life~15 years from combined Panchpatmali and Pottangi (~25 crore tons total)