NMDC Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/res7o8vs35ln03irhp8rnwmm.pdf

Key Takeaways


Production & Volume Outlook

Mukherjee: "a lot of bureaucracy in the project management has been cut and that is what you see the results that we are about 80% higher than our targets and 40% higher than as compared to last year"

Pricing & Realization Strategy

Mukherjee: "I make more money net of taxes, net of transportation, and net of duties through domestic sales rather than through export sales."

Capex Acceleration & Project Pipeline


Diversification: Steel, Gold, Lithium & Diamonds


Financial & Capital Allocation


Transformation & Sustainability

Mukherjee: "the company is under a major transformation right now starting with what we have seen with the logo itself"

Guidance & Commitments

CommitmentSpecificsTimeline
FY24 production47–49 mt, hope to achieve ~50 mtFY24
FY24 capexCross Rs.1,600 Cr; expected Rs.1,800–2,000 CrFY24
FY25 production ceilingStagnation at 51–52 mt; no production beyond 52–53 mtFY25
Next major volume ramp-upAfter two financial years (current and next)FY26 onward
Bacheli fifth line commissioningAwaiting CTE; load testing doneNext 4–5 days
Kumaraswamy mine startOne final approval pendingWithin a week to 10 days
SP3 rapid wagon loading systemAwaiting consent to operate7–8 days after Nov 17
SP3 stacking yardDelayed by monsoon damageAround 2025
SP2 tender awardThree offers under evaluationAround mid-next month
Railway line doubling completion100+ km of 131 km commissioned; two block sections remainEnd of financial year
Beneficiation plantContract awarded six months backEnd-2024 or early 2025
Customized products marketing studyConsultants appointed; clarity on what to produce and whereBy this financial year
NMDC Steel capacity ramp-up70–80% utilizationEnd of current financial year
NMDC Steel full capacityFull capacity operationNext financial year
Gold presence expansionExploring six nearby minesAround 24 months
Lithium PFSUndertake pre-feasibility studyStarting next April; ~18 months
Diamond mining startSubject to EC clearanceWithin a month of EC receipt
Annual capex quantum jumpFrom Rs.2,000 Cr to Rs.4,000–5,000 CrNext 3–4 years
EC enhancement for Bailadila sectorEnhanced environmental clearance16–24 months

Key Metrics

MetricQ2 FY24
Production growth25% higher YoY
Sales growth~14% higher YoY
Realization per tonne₹4,146, up 7% YoY
H1 realization per tonne₹4,928, up 8% YoY
Capex incurred (year to date)~₹1,008 cr, 40% higher YoY and 80% above proportionate target
Full-year capex target₹1,600 cr (original); expected to reach ₹1,800–2,000 cr
FY25 capex guidance₹2,200–2,300 cr
H1 production~2 crore tonnes
Production run-rate (as of call)~2.4 crore tonnes
FY24 production target47–49 lakh tonnes (4.7–4.9 crore tonnes)
Lump-to-fine recovery ratio30:70
Lumps price change YoY-2%
Fines price change YoY+11%
QoQ realization change (vs Q1 FY24)~10% decrease
RINL supply (H1 FY24)~30 lakh tonnes, up 10% YoY
NMDC Steel capacity utilization40–45% currently; ramp-up to 70–80% targeted by FY24-end
Dividend payout (historical)40–45% of PAT (including buybacks) over last 6–7 years
Cash balance~₹14,000 cr
Gold mine production (Australia)~1 tonne over next 12–15 months
Diamond mine (initial year)~10,000 carats (of 30,000 carat capacity)