NMDC Ltd Q3 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/ep4f5oztu0pxnhlnoqpkrewx.pdf

Key Takeaways


Volume & Production

Mukherjee: "the main and it will be a onetime sudden big jump around 28-29 if we are able to award all the projects in the next financial year there is another three years to execute that is the timeline that I see."

NMDC Steel Ramp-Up


One-Off Charges & Below-the-Line Drags

Mukherjee: "It is a very unfortunate thing that happened... the actual amount paid is only 30-31 Crores which has been capitalized next is basically penalty of around 60 Crores and 180 Crores is interest on penalty."

Projects & Diversification


Export & Pricing

Mukherjee: "very few times there is an economic justification of export. Yes, there is a strategic of export because when you go to 10 crore ton you would require to have access to international markets as well for which of course to be present on a long-term basis you cannot be a Fly by Night operator there, but that is an aspect that we are looking at in terms of our expansion plan, not in terms of an immediate sort of thing."

Capital Allocation & Balance Sheet


Guidance & Commitments

CommitmentSpecificsTimeline
FY24 volumeVery close to 47 crore tons; comfortable if Kumaraswamy enhancement approved in 3-4 daysFY24 end
FY25 volume50-51 crore tons; ~53 crore tons if one more project comes onFY25
NMDC Steel breakevenProfitable at 1.5-1.6 lakh tons/month (66%-70% utilization)Not specified
NMDC Steel utilization milestone55% utilization (5,000 tons of coils per day)Q1 FY2025
Slurry pipeline and pellet plant commissioningFully commissionedFY2025 end
Tokisud coal block mining start16-18 months to start mining after CBA approvalEarly FY2026 if CBA approved
Pellet plant partnership finalizationO&M revenue-sharing partnership with private players3 to 6 months
Panna Diamond mining restartStart mining once EC approval receivedEC approval expected in 3-4 days
Major volume jumps (deposits 11C, 14)0.5-1 crore ton each, tendering nowAround FY2028-29
Australia other depositsMine other deposits within 18-24 months18-24 months
Lithium PFS completionPFS to commence in 2-3 months, completed in 12-18 months12-18 months from commencement

Key Metrics

MetricQ3 FY24
Production growth (9M)+19% YoY
Sales growth (9M)+24% YoY
Turnover growth (9M)~25% YoY, entirely volume-driven; average realization almost unchanged
FY24 volume guidance~4.7 crore tons; management targeting ~47 crore tons, contingent on Kumaraswamy enhancement
FY25 volume guidance50–51 crore tons; up to 53 crore tons if one more project comes on
NMDC Steel HR coil production (Jan 2024)~1 lakh tons, up from ~65,000–66,000 in the previous month
NMDC Steel break-even level1.5–1.6 lakh tons per month (66%–70% utilization)
Sales to NMDC Steel₹555 cr in the last 4–4.5 months up to December end
Supreme Court refund receivable~₹1,800 cr still to be received, out of ₹2,900 cr
Capex FY24₹1,750–1,800 cr; ₹1,500 cr spent by end of January
Capex FY25~₹2,000–2,100 cr
Net cash~₹11,500 cr
Dividend announced₹5.75 per share, payout of ~₹1,580 cr
Customer sales mixJSW 38%, AM/NS ~18%, RINL 15%
Pellet segment loss (9M)₹65 cr; losses came down from ₹58 cr to ₹17 cr over the last 9 months
Donimalai forest penalty (Q3 hit)₹252 cr total outflow, of which ~₹180 cr was interest on penalty