Key Takeaways
- Demand-led generation dip, not structural: Group generation fell ~600 crore units YoY on a milder summer and extended monsoon, but management sees firm underlying economic momentum and maintained coal station availability above 90%.
- Record H1 capacity addition of 4,403 MW: The highest in any half year since inception, with another 956 MW added in October, putting the group on track for its 6 GW COD target this fiscal.
- Balance sheet strengthening on multiple fronts: Average cost of borrowing dropped 52 bps to 6.11%, DISCOM receivables improved to 28 days, and fixed cost under-recoveries are expected to halve to ~₹250 crore by year-end.
- Renewable ambition scaled up materially: The 2032 capacity target was revised from 130 GW to 149 GW, with a 60 GW RE goal by FY32, and NGEL’s operating EBITDA margin improved to 88% in H1.
- What to watch next quarter: Whether the Meja II state approval arrives within the promised two months, the pace of Q3 RE commissioning (~2 GW targeted), and any progress on BESS offtake tie-ups that would firm up return expectations.
Demand & Generation: A Weather-Driven Quarter
- Milder summer, extended monsoon: The primary driver of the ~600 crore unit YoY generation decline was subdued demand from weather, consistent with the broader trend in India’s coal-based generation. Management characterized this as a moderation, not a structural shift, citing firm underlying economic momentum.
- PLF still well ahead of the industry: Coal station PLF of 70.52% compared to a rest-of-India average of 64.32%, reflecting best-in-class operational practices and sustained maintenance.
- Grid curtailment added pressure: PLF was also down due to grid curtailment. While this does not have a direct correlation with higher O&M, management noted that if backing down occurs, overall tariff likely rises because fixed costs are distributed over fewer units.
- Coal security improved: Coal stock reached 13.4 MMT, up 2.1 MMT YoY, sufficient for 15 days at 85% PLF. Six of nine captive coal blocks are now under commercial operation, with Kerandari declared commercial from April 1, 2025.
Management: "There was a clear dichotomy over which was working to them, which was detrimental to us. But based on the policy advocacy and follow-up, now this Suo-Moto order has ameliorated that situation for us."
Capacity Addition: Record Pace, Bigger Ambition
- H1 FY26 was the best half-year ever: 4,403 MW added, plus 956 MW in October, taking the seven-month total to 5,359 MW. NGEL added 1,506 MW in H1 and a further 156 MW in October, reaching 7,564 MW installed capacity.
- Targets revised sharply upward: The 2032 capacity target moved from 130 GW to 149 GW, and the 2037 target to 244 GW. Between 2032 and 2037, the plan adds 13 GW thermal, ~0.3 GW hydro, 55-60 GW incremental renewable, and ~2.1 GW nuclear.
- Three-year COD visibility: Management guided 6 GW COD this fiscal, 8 GW next year, and 8 GW in FY28. Thermal COD is 2,780 MW this year, 1,600 MW next year, and 2,120 MW in FY28. Hydro delivers 1 GW this year, nothing next year, then 444 MW in FY28.
- RE commissioning back-half loaded: Q2 is typically muted due to the monsoon. The bulk of the balance-period capacity will come from Bhuj, Khavda, and Rajasthan. Q3 is targeted at ~2 GW and Q4 at another ~1.7 GW, from both NGEL standalone and ONGPL (Ayana).
- Meja II ready to start: All clearances are in place; only State Government of UP approval is pending, expected within two months, with project work starting from January 1. LNTP has already been issued on an EPC basis to BHEL.
- Mahi Banswara nuclear advancing: The 4 x 700 MW Rajasthan Atomic Power Project was transferred from NPCIL to ASHVINI at book value. Excavation work is expected to commence shortly, with the balance nuclear island and TG package award targeted this fiscal.
Management: "We have a clear visibility on the CODs over the next three years."
Financial Health: Lower Costs, Cleaner Balance Sheet
- Cost of borrowing down 52 bps: Average cost fell from 6.63% to 6.11%, mainly through refinancing and restructuring of loans. A JPY equivalent of US$100 million loan was executed with CTBC Bank in July 2025.
- Fixed cost under-recoveries shrinking: Stood at ₹625 crore as of September 2025, expected to reduce to ~₹250 crore by year-end.
- DISCOM receivables improving: Days outstanding improved to 28 days from 33 days YoY.
- Operational gains contributing: ₹238 crore from coal stations (SG incentive, primary frequency response) and ₹49 crore from hydro stations in H1 FY26.
- EESL remains a drag, but action underway: Losses will continue till FY26. Promoters are taking it very seriously, attempting to get receivables from urban local bodies and looking at options including a stake sale in IntelliSmart.
Management: "I would just like to inform the members that the promoters are taking this very, very seriously and all attempts are being made to get the receivables from the various urban local bodies and we are looking at various options including our stake sale in IntelliSmart."
Renewables & Storage: Scaling the Next Engine
- NGEL profitability robust: Operating EBITDA margin improved to 88% in H1 FY26 (86% H1 FY25) and 86% in Q2 FY26 (83% Q2 FY25).
- RE capacity goal of 60 GW by FY32: Fresh contracts placed for 3 GW of renewable capacity, with land and connectivity contracts placed for 1,200 MW. The land bank has reached 22.8 GW, with 16.5 GW in advanced-stage allotments across Andhra Pradesh (4 GW), Rajasthan (10 GW), and Gujarat (2.5 GW).
- Green hydrogen/ammonia entry: NGEL secured a contract for supply of 0.7 lakh tonnes of green ammonia in a green chemical tender, marking entry into green hydrogen chemicals under the National Green Hydrogen Mission.
- Pumped storage momentum: Two 250 MW units of Tehri PSP commissioned in H1; remaining two units expected this fiscal. Firm allocation of 12,670 MW of additional PSPs secured from various states.
- Battery storage: two distinct models: 5 GW co-located with thermal plants will be part of the thermal business on a cost-plus regulated model, with VGF of ₹18 lakh per MWh. A separate 5,020 MWh co-located with solar is not regulated and will start on a merchant basis, with the intent to use solar capacity during evening peak hours. Exact return numbers will be known once offtake tie-ups are firmed up.
- BESS co-location logic: Thermal-plant sites were chosen based on variable cost (higher variable cost means higher backing-down risk) and peak-hour tariff viability. Projects are expected to complete within three years from award, with awards expected this fiscal.
- International renewables advancing: Sampur Solar Phase 1 ground-breaking held in Sri Lanka; a joint declaration signed to advance a 17.5 MW floating solar PV with 48 MWh BESS at Tamarind Falls, Mauritius.
Management: "The co-located BESS are primarily being done with an intent to use the solar capacity during the peak hours in the evening. So, that is expected to give us a significant boost in our revenue. But the exact numbers would come up only once we are able to firm up the tie-ups."
Thermal & Nuclear: The Base Load Foundation
- New coal ordering pipeline: 1.6 GW (Lara Stage 3) expected to be awarded this fiscal, predominantly on a packaging basis. 2.4 GW planned next fiscal, with another 800 MW beyond that, potentially scaling to 1.6 GW.
- No tariff-based competition: Management explicitly declined to participate in fresh thermal bidding, even as PPAs are being signed between states and private players like Adani and JSW.
- Biomass co-firing ramping: Reached over 5 lakh metric tons in H1 FY26, nearly double YoY.
- Nuclear partnerships in exploration: NTPC is exploring partnerships with international players for NTPC Parmanu Urja Nigam Limited, pending required government permissions.
- FGD work continues: Balance 39,390 MW of FGD work is in progress, though no specific timeline was committed.
Management: "No, we don't intend participating in any tariff-based competition."
ESG & Operational Excellence
- ESG ratings improving: MSCI ESG rating progressed from 3.4 to 4.1; Sustainalytics ESG risk rating improved from 35.7 to 31, very close to a band upgrade.
- Coal mine transfer progressing: Business transfer agreement signed for transfer of coal mines from NTPC to NTPC Mining Limited at an estimated value of ₹10,503 crore. Chatti Bariatu and Badam mines transferred; remaining mines expected to transfer this fiscal.
- NEEPCO hydropower foundation laid: PM laid the foundation stone for Heo (240 MW) and Tato-1 (186 MW) hydroelectric projects in Arunachal Pradesh, with an estimated cost over ₹3,700 crore.
- CO2-based storage pilot: Work on a 160 MWh CO2-based energy storage system at Kudgi is under progress.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Fixed cost under-recoveries | Reduce to ~₹250 crore | By year-end FY26 |
| Tehri PSP commissioning | Remaining two 250 MW units | Current fiscal |
| Coal mine transfer to NML | All remaining mines transferred | Current fiscal |
| Meja II project start | State UP approval, work begins | Approval within 2 months; work from Jan 1 |
| Mahi Banswara nuclear award | Balance nuclear island and TG package awarded | This financial year |
| BESS project award | Awards for battery storage projects | Current financial year |
| Lara Stage 3 (1.6 GW) award | New thermal ordering | This financial year |
| FY26 capacity addition (COD) | 6 GW total | Current fiscal |
| FY27 capacity addition (COD) | 8 GW total | Next fiscal |
| FY28 capacity addition (COD) | 8 GW total | FY28 |
| NGEL FY26 RE capacity addition | 5,365 MW | Current fiscal |
| NGEL FY27 RE capacity addition | 8 GW | Next fiscal |
| NGEL FY26 capex | ~₹30,000 crore | Current fiscal |
| NGEL FY27 capex | ~₹45,000-46,000 crore | Next fiscal |
| Q3 RE commissioning | ~2 GW | Q3 FY26 |
| Q4 RE commissioning | ~1.7 GW | Q4 FY26 |
| Ayana RE-RTC projects | Commissioned | Almost by end of this year |
| BESS project completion | Within 3 years from award | 3 years from award date |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Standalone total income | ₹40,689 cr, vs ₹41,245 cr in Q2 FY25 |
| Standalone PAT | ₹4,653 cr, vs ₹4,649 cr in Q2 FY25 |
| Standalone adjusted PAT | ₹4,518 cr, up 8% vs ₹4,202 cr in Q2 FY25 |
| Consolidated adjusted PAT | ₹5,069 cr, up 3% vs ₹4,943 cr in Q2 FY25 |
| Group total income (H1 FY26) | ₹93,083 cr, vs ₹94,179 cr in H1 FY25 |
| Group PAT (H1 FY26) | ₹11,334 cr, up 4% vs ₹10,886 cr in H1 FY25 |
| NGEL consolidated revenue | ₹612 cr, up 21% vs ₹504 cr in Q2 FY25 |
| NGEL operating EBITDA | ₹530 cr, up 26% vs ₹420 cr in Q2 FY25 |
| NGEL operating EBITDA margin | 86%, vs 83% in Q2 FY25 |
| Average cost of borrowing (H1 FY26) | 6.11%, vs 6.63% in H1 FY25 |
| Group CAPEX (H1 FY26) | ₹23,115 cr, vs ₹17,474 cr in H1 FY25 |
| Standalone CAPEX (H1 FY26) | ₹14,149 cr, vs ₹14,040 cr in H1 FY25 |
| NGEL consolidated capex (H1 FY26) | ₹6,607 cr, vs ₹4,884 cr in H1 FY25 |
| Consolidated regulated equity | ₹1,16,022 cr as on 30 Sep 2025, up 10% vs ₹1,05,049 cr as on 30 Sep 2024 |
| Standalone regulated equity | ₹94,454 cr as on 30 Sep 2025, up 6% vs ₹89,430 cr as on 30 Sep 2024 |
| NTPC Group installed capacity | 84,849 MW as on date, up from 83,893 MW at H1 end |
| Group total generation (H1 FY26) | 214 BUs, ~600 crore units lower vs H1 FY25 |
| Coal stations PLF | 70.52%, vs rest of India average of 64.32% |
| Coal stock at stations | 13.4 MMT, up 2.1 MMT YoY, sufficient for 15 days at 85% PLF |
| Captive mines dispatch growth (H1 FY26) | 2.61% YoY |
| Fixed costs under recoveries | ₹625 cr till Sep 2025, expected ~₹250 cr by year-end |
| Operational gains from coal stations (H1 FY26) | ₹238 cr |
| Operational gains from hydro stations (H1 FY26) | ₹49 cr |
| Receivables from DISCOMs | 28 days, improved from 33 days YoY |
| FY26 capacity addition target | 9,844 MW (2,019 MW standalone, 7,825 MW JVs and subsidiaries) |
| Capacity added till H1 FY26 | 4,403 MW, highest in any half year since inception |
| Additional capacity added in October 2025 | 956 MW, taking total fresh addition to 5,359 MW as on date |
| NGEL Group installed capacity | 7,564 MW as on date |
| Current capacity under construction | 33 GW (17 GW coal, 2 GW hydro, 14 GW renewable) |
| Revised capacity target | 149 GW by 2032, 244 GW by 2037 |
| Estimated capex requirement | ₹7 lakh crore by 2032 |
| First interim dividend | ₹2.75 per equity share for FY 2025-26 |
| MSCI ESG rating | 4.1, improved from 3.4 |
| Sustainalytics ESG risk rating | 31, improved from 35.7 |
| FGD cumulative capacity commissioned | 20,270 MW, work in progress for balance 39,390 MW |
| Biomass co-firing (H1 FY26) | Over 5 lakh metric tons, nearly double YoY |
| NTPC Vidyut Vyapar Nigam power trading growth | 11.45%, from 22.3 BUs to 24.8 BUs |
| NGEL green ammonia contract | 0.7 lakh tonnes secured in green chemical tender |
| Mahi Banswara nuclear project | 4 x 700 MW, estimated cost ~₹50,000 cr, completion by 2032-33 |
| BESS at existing thermal projects | 5,000 MWh, fully regulated, with VGF of ₹18 lakh per MWh |
| BESS tendered | 2.3 GW already tendered, 2.9 GW expected in December |
| Land pool for solar projects | 22.8 GW total, with 16.5 GW in advanced stage |
| EESL losses | Expected to continue till FY26 |