NTPC Ltd Q4 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/u372c82i6436ljeow79thj53.pdf

Key Takeaways


Profitability Drivers: The Mix Shift

Management: "So, we are hopeful that in the coming years, disincentive would be brought to the minimum level."

Regulated Equity: The Lead-Lag Effect

Management: "So, the complete effect of this capitalization and the incremental regulated equity benefit will be seen in the next year."

Renewable Energy: Missed Quarter, Intact Ambition

Management: "No, we don't think that it would be any kind of a rush because we are going as per our plan and our conviction and there is immense value capturing which we foresee and given the visibility of almost 22 GW which I was sharing with you and the plans for going ahead and reaching a 60 GW by FY32."

Thermal Pipeline: Visibility Through FY27


Operations: High PLF, Lower Backing Down


New Business & Strategic Updates


Guidance & Commitments

CommitmentSpecificsTimeline
Thermal capacity award15.2 GW to be awarded: 10,400 MW in FY25, 3,200 MW in FY26, 1,600 MW in FY27FY25-FY27
Renewable commissioning~3 GW in FY25, ~5 GW in FY26, ~8 GW in FY27; delayed Q4 capacity to come in H1 FY25FY25-FY27
Group CODFY25: 6,780 MW (thermal 2,780, hydro 1,000, RE 3,000); FY26: 6,460 MW (thermal 1,460, RE 5,000); FY27: 9,244 MW (thermal 800, hydro 444, RE 8,000)FY25-FY27
Group CAPEX₹35,000 to ₹50,000 crore per annum across coal mining, renewable, FGDNext 2-3 years
Standalone CAPEX FY25₹22,700 croreFY25
Coal mining production5 crore tonnes annual productionIn 3 years
NGEL IPODRHP activities post-June; IPO tentatively October/NovemberFY25
Renewable capacity target60 GWBy FY32
Nuclear (ASHVINI JV)Mahi Banswara project FPC in FY26, commissioning by FY32FY26 / FY32

Key Metrics

MetricQ4 FY24
Total Income (Group)₹1,81,166 cr for FY24, vs ₹177,977 cr in FY23
PAT (Standalone)₹18,079 cr for FY24, +5% YoY
PAT (Group)₹21,332 cr for FY24, +25% YoY
Reported PAT (Standalone, Q4)₹5,556 cr
Adjusted PAT (Standalone, Q4)₹5,107 cr, +6% YoY
Adjusted PAT (Standalone, FY24)₹16,405 cr, +2% YoY
Standalone Regulated Equity₹87,713 cr as on 31.03.2024, +13% YoY
Consolidated Regulated Equity₹104,331 cr as on 31.03.2024, +11% YoY
Group CAPEX₹34,943 cr for FY24, vs ₹35,204 cr in FY23
Standalone CAPEX₹19,319 cr for FY24, vs ₹24,597 cr in FY23
Standalone Capital Outlay (FY25E)₹22,700 cr
Group CAPEX Guidance (next 2-3 years)₹35,000 to ₹50,000 cr per annum
Rate of Interest on Borrowings6.67% for FY24, vs 6.40% in FY23
Total Dividend per Share₹7.75 for FY24, vs ₹7.25 in FY23
Group Commercial Capacity75,958 MW as on 31.03.2024
Group Generation42,200 crore Units for FY24, +6% YoY
Average PLF (Coal Stations)77.25% for FY24, vs National Average of 69.49%
Coal Supply241.21 MMT for FY24, including 9.57 MMT imported
Captive Coal Production34.39 MMT for FY24, +48% YoY
Trade Receivables31 days of sales as on 31.03.2024, vs 36 days as on 31.03.2023
Under Recovery (Disincentive)₹36 cr for Q4; ₹776 cr for FY24
Surcharge Income₹118 cr for Q4; ₹303 cr for FY24
Share of Profit from JVs and Subsidiaries₹5,533 cr for FY24, vs ₹2,246 cr in FY23
Dividend Income from Subsidiaries and JVs₹1,630 cr for FY24, vs ₹2,336 cr in FY23
NGEL EBITDA₹1,820 cr for FY24
NGEL PAT₹343 cr for FY24
Renewable Capacity Commissioned (Cumulative)3.6 GW
Renewable Capacity Under Construction8.4 GW
Renewable Capacity Under Tendering11.2 GW
Renewable Auctions Won in FY24More than 5 GW
Renewable Capacity Addition Target (FY25E)3 GW
Thermal Capacity Under Construction (Group)9.6 GW
Thermal Capacity Planned for Award15.2 GW in near future
Thermal Capacity Planned for Tendering (FY25E)10,400 MW
Group Capacity Addition Expected (FY25E)6,780 MW (thermal 2,780 MW, hydro 1,000 MW, renewable 3,000 MW)
Group Capacity Addition Expected (FY26E)6,460 MW (thermal 1,460 MW, renewable 5,000 MW)
Group Capacity Addition Expected (FY27E)9,244 MW (thermal 800 MW, hydro 444 MW, renewable 8,000 MW)
FGD Capacity Undertaken66.8 GW, with 8.9 GW commissioned
Gas Capacity Without PPA908 MW