Key Takeaways
- Earnings quality improved, but the mix shifted: Standalone PAT rose 5% while Group PAT surged ~25%, driven by a steep jump in JV/subsidiary profit share (₹5,533 cr vs ₹2,246 cr) rather than the core standalone business.
- Capitalization is converting, with a lag: Standalone regulated equity grew ~₹10,000 crore to ₹87,713 crore as CWIP declined sharply, but the full earnings benefit of this capitalization will only be seen next year.
- Renewable commissioning missed the quarter badly: Only 0.2 GW was commissioned in Q4 against an expected ~1 GW, due to module import clearance delays and land acquisition issues, though management says both are now largely addressed.
- The thermal pipeline is firming up: 15.2 GW of thermal capacity is planned for award through FY27, with a specific quarter-by-quarter tendering schedule laid out, and ~8,000 MW of PPA tie-up already available.
- What to watch next quarter: Whether the delayed renewable capacity actually commissions in H1 FY25, progress on the ~7,000 MW of thermal PPA still under discussion, and the NGEL IPO DRHP filing post-June.
Profitability Drivers: The Mix Shift
- JV/subsidiary profit surge: Group PAT was lifted by a ₹3,287 crore increase in share of profit from JVs and subsidiaries, with key contributions from BRBCL (₹248 cr to ₹517 cr), RGPPL (significant variation), NGEL (doubled, +₹169 cr), NEEPCO (₹396 cr to ₹548 cr), HURL (+₹411 cr), and BIFPCL in Bangladesh (+₹309 cr after COD of both units).
- Dividend income declined: Dividend from subsidiaries and JVs fell to ₹1,630 crore from ₹2,336 crore, as entities retained earnings to plough back into hydro and renewable projects.
- Surcharge income fell on better collections: Q4 surcharge was ₹118 crore and the full year ₹303 crore, a decline management framed as a mark of improved collection efficiency.
- Interest cost ticked up: The rate of interest on borrowings rose to 6.67% from 6.40%, adding pressure to the financing line.
- Under-recovery concentrated in two plants: Of the ₹776 crore full-year under-recovery (₹36 cr in Q4), the major part came from Barh and Barauni. Barauni, a vintage plant, has been decommissioned, and the Barh problem has been significantly arrested. Outside these two, disincentive was close to ₹150 crore, driven by high/low demand season regulation that has now been discontinued through policy advocacy.
Management: "So, we are hopeful that in the coming years, disincentive would be brought to the minimum level."
Regulated Equity: The Lead-Lag Effect
- Capitalization accelerated: Standalone CWIP declined sharply to ₹47,154 crore from ₹61,744 crore, and group CWIP to ₹87,593 crore from ₹89,133 crore, indicating better conversion of investments into completed assets.
- Regulated equity base expanded: Standalone regulated equity grew ~₹10,000 crore to ₹87,713 crore, reflecting capitalization of plants achieving COD.
- Earnings catch-up is pending: Regulated equity starts reckoning only once a plant achieves COD, so the denominator has increased suddenly but the full-year earnings effect has not yet flowed through.
- Receivables improved: Trade receivables improved to 31 days of sales from 36 days, with the highest-ever realization of over ₹1.56 lakh crore.
Management: "So, the complete effect of this capitalization and the incremental regulated equity benefit will be seen in the next year."
Renewable Energy: Missed Quarter, Intact Ambition
- Q4 commissioning fell short: Only 0.2 GW was commissioned against an expectation of ~1 GW. The two reasons cited were delay in procurement of modules (late government clearance to import modules from outside India) and delays on the land acquisition front. Management says both have been largely addressed and modules are already at sites.
- Pipeline remains large: 3.6 GW commissioned cumulatively, 8.4 GW under construction, 11.2 GW under tendering, 6.6 GW of land with connectivity tenders, and a 4.8 GW land bank.
- Commissioning ramp planned: FY25 target is about 3 GW, FY26 about 5 GW, and FY27 about 8 GW, with the delayed capacity expected to come progressively in H1 FY25.
- Equity IRR steady, not rising: Despite lower module prices and higher tender tariffs, management said equity IRR indications broadly remain the same as earlier (~12%), citing the blend of auction routes, JVs with other PSUs, and the C&I segment. Lower gestation periods in renewables help achieve IRR comparable with thermal's regulated return.
- NGEL IPO on track: Plans are proceeding, tentatively around October or November, with DRHP activities and due diligence to take shape post-June. The IPO could be in the nature of a fresh issue, and NGEL will remain a subsidiary of NTPC even post-IPO.
Management: "No, we don't think that it would be any kind of a rush because we are going as per our plan and our conviction and there is immense value capturing which we foresee and given the visibility of almost 22 GW which I was sharing with you and the plans for going ahead and reaching a 60 GW by FY32."
Thermal Pipeline: Visibility Through FY27
- 15.2 GW planned for award: Management laid out a specific tendering schedule: FY25 (10,400 MW across Sipat 3, Darlipalli 2, Meja 2, Nabinagar 2, Telangana 2, Gadarwara 2 in Q2-Q4), FY26 (3,200 MW: Anpara 1,600, Obra 1,600), and FY27 (1,600 MW: Patratu). The split is 53% standalone, 47% JV/subsidiary.
- PPA tie-up partially secured: Out of the ~15,000 MW to be ordered, ~8,000 MW of PPA tie-up is available. The remaining ~7,000 MW is being taken up for higher tie-up, with discussions ongoing with states and the Ministry.
- 9.6 GW already under construction: The existing thermal construction pipeline adds to the award pipeline.
- Coal mining scaling up: Captive coal production jumped ~48% to 34.39 MMT, and management expects to reach 5 crore tonnes of annual production in three years. Imported coal was reduced from 14.56 MMT to 9.57 MMT.
Operations: High PLF, Lower Backing Down
- PLF outperformance sustained: NTPC coal stations achieved a PLF of 77.25% against a national average of 69.49%, with four stations among the top 10 nationally.
- Backing down reduced: Improved scheduling by beneficiaries reduced backing down from 9,186 crore units to 8,639 crore units.
- Group generation grew ~6% YoY: Standalone generation was up ~5% YoY.
- Group capacity added 3,924 MW in commercial capacity during FY24.
- FGD compliance progressing: 66.8 GW of FGD capacity has been undertaken, with 8.9 GW commissioned so far.
New Business & Strategic Updates
- Nuclear JV advancing: The ASHVINI joint venture with NPCIL is expected to get cabinet clearance possibly by next month end. The Mahi Banswara project in Rajasthan (4x700 MW) is likely to be allotted to this JV, with FPC expected in FY26 and commissioning by FY32.
- Green hydrogen pilots progressing: The Leh project plans to run 5 buses by July 2024, and the Delhi e-mobility project plans 5 buses by December 2024. An agreement with the Army for a microgrid based on green hydrogen is already awarded and underway. A hydrogen hub is being established at Pudimadaka, and a tie-up with Gujarat Pipavav for ammonia export is in place.
- Pumped storage pipeline building: Upper Bhavani (1,000 MW) is in DPR stage, with construction to begin after two years of pre-construction and take around five years. More PSP orders are expected from Chhattisgarh, Himachal Pradesh, Karnataka, Gujarat, Maharashtra, and Meghalaya, holding to the earlier target of 10 GW.
- SMR and battery storage at exploratory stage: Plans for small modular reactors and battery energy storage systems are being worked on but remain at an exploratory stage.
- Multiple MOUs signed: Key agreements include a Maharashtra MOU for up to 0.1 crore metric tonnes/year of green hydrogen, 2 GW PSP, and 5 GW RE (potential investment ~₹80,000 crore); an MOU with GSPC for green hydrogen blending and fuelling stations; and an MOU with Nepal Electricity Authority for joint power project development.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Thermal capacity award | 15.2 GW to be awarded: 10,400 MW in FY25, 3,200 MW in FY26, 1,600 MW in FY27 | FY25-FY27 |
| Renewable commissioning | ~3 GW in FY25, ~5 GW in FY26, ~8 GW in FY27; delayed Q4 capacity to come in H1 FY25 | FY25-FY27 |
| Group COD | FY25: 6,780 MW (thermal 2,780, hydro 1,000, RE 3,000); FY26: 6,460 MW (thermal 1,460, RE 5,000); FY27: 9,244 MW (thermal 800, hydro 444, RE 8,000) | FY25-FY27 |
| Group CAPEX | ₹35,000 to ₹50,000 crore per annum across coal mining, renewable, FGD | Next 2-3 years |
| Standalone CAPEX FY25 | ₹22,700 crore | FY25 |
| Coal mining production | 5 crore tonnes annual production | In 3 years |
| NGEL IPO | DRHP activities post-June; IPO tentatively October/November | FY25 |
| Renewable capacity target | 60 GW | By FY32 |
| Nuclear (ASHVINI JV) | Mahi Banswara project FPC in FY26, commissioning by FY32 | FY26 / FY32 |
Key Metrics
| Metric | Q4 FY24 |
|---|---|
| Total Income (Group) | ₹1,81,166 cr for FY24, vs ₹177,977 cr in FY23 |
| PAT (Standalone) | ₹18,079 cr for FY24, +5% YoY |
| PAT (Group) | ₹21,332 cr for FY24, +25% YoY |
| Reported PAT (Standalone, Q4) | ₹5,556 cr |
| Adjusted PAT (Standalone, Q4) | ₹5,107 cr, +6% YoY |
| Adjusted PAT (Standalone, FY24) | ₹16,405 cr, +2% YoY |
| Standalone Regulated Equity | ₹87,713 cr as on 31.03.2024, +13% YoY |
| Consolidated Regulated Equity | ₹104,331 cr as on 31.03.2024, +11% YoY |
| Group CAPEX | ₹34,943 cr for FY24, vs ₹35,204 cr in FY23 |
| Standalone CAPEX | ₹19,319 cr for FY24, vs ₹24,597 cr in FY23 |
| Standalone Capital Outlay (FY25E) | ₹22,700 cr |
| Group CAPEX Guidance (next 2-3 years) | ₹35,000 to ₹50,000 cr per annum |
| Rate of Interest on Borrowings | 6.67% for FY24, vs 6.40% in FY23 |
| Total Dividend per Share | ₹7.75 for FY24, vs ₹7.25 in FY23 |
| Group Commercial Capacity | 75,958 MW as on 31.03.2024 |
| Group Generation | 42,200 crore Units for FY24, +6% YoY |
| Average PLF (Coal Stations) | 77.25% for FY24, vs National Average of 69.49% |
| Coal Supply | 241.21 MMT for FY24, including 9.57 MMT imported |
| Captive Coal Production | 34.39 MMT for FY24, +48% YoY |
| Trade Receivables | 31 days of sales as on 31.03.2024, vs 36 days as on 31.03.2023 |
| Under Recovery (Disincentive) | ₹36 cr for Q4; ₹776 cr for FY24 |
| Surcharge Income | ₹118 cr for Q4; ₹303 cr for FY24 |
| Share of Profit from JVs and Subsidiaries | ₹5,533 cr for FY24, vs ₹2,246 cr in FY23 |
| Dividend Income from Subsidiaries and JVs | ₹1,630 cr for FY24, vs ₹2,336 cr in FY23 |
| NGEL EBITDA | ₹1,820 cr for FY24 |
| NGEL PAT | ₹343 cr for FY24 |
| Renewable Capacity Commissioned (Cumulative) | 3.6 GW |
| Renewable Capacity Under Construction | 8.4 GW |
| Renewable Capacity Under Tendering | 11.2 GW |
| Renewable Auctions Won in FY24 | More than 5 GW |
| Renewable Capacity Addition Target (FY25E) | 3 GW |
| Thermal Capacity Under Construction (Group) | 9.6 GW |
| Thermal Capacity Planned for Award | 15.2 GW in near future |
| Thermal Capacity Planned for Tendering (FY25E) | 10,400 MW |
| Group Capacity Addition Expected (FY25E) | 6,780 MW (thermal 2,780 MW, hydro 1,000 MW, renewable 3,000 MW) |
| Group Capacity Addition Expected (FY26E) | 6,460 MW (thermal 1,460 MW, renewable 5,000 MW) |
| Group Capacity Addition Expected (FY27E) | 9,244 MW (thermal 800 MW, hydro 444 MW, renewable 8,000 MW) |
| FGD Capacity Undertaken | 66.8 GW, with 8.9 GW commissioned |
| Gas Capacity Without PPA | 908 MW |