NTPC Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/h34ze2eatx6gjhmuzjd5xjv5.pdf

Key Takeaways


Thermal: The Backing-Down Buffer

Management: "if I have declared a certain capacity higher than the technical minimum or let us say 85% or 100% and the scheduling comes below 55% for some reason, I'm not obliged to run this plant, I can take a reserve shutdown and whatever is the comfortable time required for ramping up it later on, I'll do that."

Renewables: Scaling Fast, Managing Friction

CEO (NGEL): "NGEL always has its threshold levels, when we do not find merit in the competitive bid, we stay away. So, we are always keenly looking at the various opportunities that come by. And we would continue to participate, and we will have the business at our terms."

Nuclear: From Studies to Steel in the Ground


Storage: The Multi-Technology Build-Out


Financial Health & Cost Levers


Guidance & Commitments

CommitmentSpecificsTimeline
FY27 capacity addition9,557 MW (thermal 1,070 MW, hydro 250 MW, renewable 8,237 MW)FY27
FY28 capacity addition10,039 MW (thermal 1,460 MW, hydro 444 MW, renewable 8,135 MW); TTPS Stage 3 Unit 1 in Q3, Patratu Unit 3 in Q1FY28
FY29 capacity addition11,478 MW (thermal 3,070 MW, renewable 8,408 MW); TTPS Stage 3 Unit 2 in Q1, Lara Stage 2 Units 1 and 2, Sinnar Units 3, 4, and 5FY29
Mahi Banswara first concreteFirst pour of concrete anticipatedAugust 2027
Mahi Banswara first synchronizationFirst unit synchronization plannedNovember 2032
Nuclear Island Mega EPC NITNIT issuance expected15 June 2026
TG Island EPC NITNIT issuance expected30 March 2027
Renewable capacity target60 GWBy 2032 (expected much ahead)
PSP commercialization3 GW to 5 GW operationalBy 2032-33
Rajasthan 1.5 GW solarProject to move aheadConditional on offtake agreement settlement with Rajasthan government

Key Metrics

MetricQ4 FY26
Standalone total income₹44,030 cr, vs ₹45,813 cr in Q4 FY25
Standalone PAT₹8,747 cr, +51.4% YoY
Consolidated group total income (FY26)₹1,89,799 cr, vs ₹1,90,862 cr in FY25
Consolidated group PAT (FY26)₹27,546 cr, +15% YoY
Adjusted PAT (FY26)₹19,530 cr, +8% YoY
NGEL consolidated revenue (FY26)₹2,858 cr, +29% YoY
NGEL Q4 revenue from operations₹913 cr, +47% YoY
NGEL Q4 operating EBITDA₹775 cr, +38% YoY
NGEL EBITDA margin (FY26)87%, flat YoY
Group installed capacity89,108 MW as on 31 Mar 2026; crossed 90 GW as on date
Capacity added during FY269,618 MW, highest ever annual addition
RE capacity added during FY264,738 MW; NGEL added 4,225 MW vs 2,977 MW in FY25
NTPC coal station PLF (FY26)72.04%, vs all-India average of 63.20%
Group generation (FY26)43,220 crore units, vs 43,870 crore units in FY25
NGEL generation (FY26)1,460 crore units, +114% YoY
Outstanding receivable days15 days as on 31 Mar 2026, improved from 29 days
Captive coal production (FY26)4.79 crore metric ton, +8.5% YoY
Weighted average interest rate on borrowings (FY26)5.98%, vs 6.61% in FY25
Group capex (FY26)₹49,068 cr, vs ₹44,636 cr in FY25
Standalone capex (FY26)₹28,462 cr, vs ₹22,965 cr in FY25
Gross property, plant and machinery (group)₹4,70,618 cr as on 31 Mar 2026, +16% YoY
Standalone regulatory equity₹94,631 cr as on 31 Mar 2026, up from ₹90,902 cr
Consolidated regulated equity (group)₹1,20,319 cr as on 31 Mar 2026, up from ₹1,08,791 cr
Total dividend for FY26₹9 per share, final ₹3.50 plus interim ₹5.50
Capacity under construction (group)Over 34 GW: 16.5 GW coal, ~2.6 GW hydro, 15 GW renewable
FY27 planned capacity addition9,557 MW: 1,070 MW thermal, 250 MW hydro, 8,237 MW renewable
FY28 planned capacity addition10,039 MW: 1,460 MW thermal, 444 MW hydro, 8,135 MW renewable
NGEL curtailment (FY26)314 MUs, plus TRAS loss of 135 MUs; grid curtailment impact ~₹90 cr
NGEL FY27 firm connectivity57% firm, 38% T-GNA
NGEL FY28 firm connectivity88% firm, 3% T-GNA, 9% yet to tie-up
NGEL PPA coverage FY2779%
NGEL PPA coverage FY2871% for 8,069 MW CODs
NGEL capex guidance FY27₹35,800 cr
NGEL capex guidance FY28₹46,000 cr
Pump storage projects (group)18,010 MW broad plan; 1 GW already commissioned
Battery storage under execution/planning (renewables)1,320 MW under execution/tendering; ~4 GW more under planning
Coal gasification pilot project4 lakh tonnes per annum capacity at Talaipalli mine