Pace Digitek Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/nbk54dbrd061acx8p8p4okpz.pdf

Key Takeaways


Revenue & Margin Dynamics

Rajavendhan P: "the current number of 13.61% will get stabilized at 11.5% for the complete financial year."

Order Book & Revenue Conversion


BESS: The Growth Engine & Its Margins

Rajiv Maddisetty: "We are trying to, you know, further cut down on cost and do backward integration to increase this because the battery energy storage system business is a little demanding and the margins are a little lesser at this point."

Annuity / Developer Model: The Long-Dated Prize

Rajavendhan P: "the overall EBITDA margin will be about 25% to 30%, wherein after the depreciation and the interest portion, it will be about 11% of PAT."

Guidance & Commitments

CommitmentSpecificsTimeline
Energy order book additionAdd ₹8,000 to ₹10,000 crores to the energy order bookBefore end of FY26 (by 31 March 2026)
FY26 revenueTop-line of ₹2,600 to ₹2,700 croresFY26 full year
FY26 PAT marginPAT margin of about 11% to 12%FY26 full year
FY27 revenue targetTop-line of about ₹3,100 to ₹3,200 croresFY27 full year
MSEDCL site execution40 sites (20 MWh each) executed out of total 75 sitesBy end of FY26 (by 31 March 2026)
Net working capital reductionNWC to come down as projects complete and retentions releaseBy 31 March 2026
High-margin project completionProject completing in Q3; Q3 will have a similar PAT margin to H1Q3 FY26
BESS capacity expansionSecond facility of 5 GWh commissioned, taking total to 10 GWhQ3 or Q4 of next financial year (FY27)
Annuity revenue startAbout ₹150 crores in annuity revenueNext financial year (FY27)
Full depreciation on annuity assetsDepreciation of ₹200–250 crores per yearFY28 onward
BSNL 4G order bookBalance ₹1,200 crores booked for O&M portionOver next 3–4.5 years

Key Metrics

MetricQ2 FY26
H1 Revenue₹900 cr, vs ₹1,188 cr in H1 FY25
H1 PAT₹122 cr, vs ₹152 cr in H1 FY25
H1 PAT margin13.61%, vs 12.79% in H1 FY25; expected to stabilize at 11.5% for full year
H1 EBITDA margin21%
Total order book₹9,135 cr, comprising energy ₹5,869 cr and telecom ₹3,266 cr
Energy order book₹5,869 cr, expected to increase by ₹8,000–10,000 cr before FY26 end
Telecom order book₹3,266 cr
Net worth₹1,331 cr as on 30 Sep 2025, vs ₹1,209 cr on 31 Mar 2025
Total debt₹150 cr, debt-equity ratio of 0.11x
Cash and FD balances₹213 cr
Fixed assets₹273 cr as on 30 Sep 2025, vs ₹178 cr on 31 Mar 2025; includes ₹95 cr from MSEDCL project
Net current assets₹970 cr as on 30 Sep 2025, expected to decline as projects complete
FY26 revenue guidance₹2,600–2,700 cr, with PAT margin of 11–12%
FY27 revenue target₹3,100–3,200 cr
Developer model project value₹3,300 cr across four projects, expected annual revenue of ₹420 cr without GST at ~85% EBITDA margin
BESS manufacturing capacity5 GWh operational, expansion to 10 GWh underway at capex of ₹100 cr
BESS orders secured4.0–4.3 GWh, expected to cross 6–7 GWh by FY26 end
Energy segment FY26 revenue target₹500–550 cr, vs ₹160 cr in FY25
ICT segment FY26 revenue target~₹250 cr
Telecom O&M annual revenue₹200–250 cr
Annuity business order book₹3,300 cr, expected to generate ~₹412 cr annual revenue, growing to ₹1,000 cr
SECI BESS project value₹1,159 cr for 600/1,200 MWh supply and installation
MAHAGENCO solar EPC project value₹920 cr
TTL O&M contract value₹185 cr over three years
BSNL 4G order book₹2,573 cr, with ₹1,300–1,400 cr to be booked in FY26 and balance ₹1,200 cr as O&M over 3–4.5 years
MSEDCL project tariff₹2,19,000 per MW per month
KPTCL project tariff₹2,49,900 per MW per month
Import content of BESS50–60% of total cost, from lithium-ion cells