Key Takeaways
- Volume up, revenue down: Revenue fell 9.94% YoY as raw material costs softened, but volume grew to 9,150 MT and management insists volume, not revenue, is the correct performance barometer.
- Balance sheet strengthened: Working capital reduced by ₹85 crores QoQ and net debt declined to ₹260 crores (0.83x equity), aided by easing supply chains and robust cash generation.
- Order book building, but timelines are fluid: New EV Letters of Intent, a $10 mn North American shaft order, and the Siemens 9000 hp locomotive award all landed, though supply chain crystallization and customer development timelines remain uncertain.
- Margin mix shift underway: Assembled and value-added volumes grew 14% YoY while loose laminations declined 8%, and management targets EBITDA per ton moving closer to ₹45,000 over two to three years as the machine components business scales.
- What to watch next quarter: Whether the ₹30 crore Q4 incentive materializes, any further push-out in automotive development timelines, and the pace at which shorter lead-time orders like Vande Bharat allocations convert into the order book.
Volume & Revenue Dynamics
- Volume is the metric: Management explicitly stated revenue has no meaning because it is determined by raw material prices; nine-month year-on-year volume growth was 14.63%, which management corrected an analyst for understating.
- Revenue degrowth explained: The 9.94% YoY revenue decline was driven entirely by softening raw material costs, which lowered blended sales realization in absolute terms, even as sales volume grew from 8,500 MT to 9,150 MT.
- Gross profit per ton declined: Fell from ₹92,200 to ₹83,200 QoQ; management deflected on a specific reason, calling it a blend of all products and services that will keep changing, with flow-through to EBITDA varying by product type and value-add.
- Inventory insulation: The nature of client contracts insulates the company from inventory gains or losses, so steel price movements do not create inventory profit or loss.
Akshay Pitti: "Revenue for us has no meaning at the end of the day, because it is determined by the raw material prices. In fact, if the revenue grows say inflation, we are actually deploying more working capital for the same amount of profit. The correct barometer for our performance is the volume growth."
Product Mix & Margin Trajectory
- Shift toward value-added products: Assembled and value-added volumes grew 14% YoY while loose laminations volumes declined 8% YoY, reflecting a deliberate mix shift toward higher-realization products.
- Realization spread by complexity: Simple welded lamination stacks carry realization similar to loose laminations, but highly value-added assembled stacks can command sales realization that is a multiple of loose laminations.
- EBITDA per ton ambition: Management expects EBITDA per ton to move closer to ₹45,000 and upwards over the next two to three years, driven by increasing contribution from the machine and machine components business, which carries higher profit margins.
- Machine components focus: The company will continue focusing on the machine components business, which is expected to see sizeable growth from the next financial year.
Akshay Pitti: "If it's a simple welded lamination stack, it is not going to be much different from a loose lamination sales realization. However, if it's the highly value-added assembled stack, then the sales realization can be multiple excess of loose laminations."
Order Book & New Business Wins
- Shaft order win: Bagged a prestigious order for manufacturing shafts for freight locomotives manufactured by a North American client; business potential of approximately $10 million in the first phase over the next 10 years, translating to roughly $1 million per year, with more orders expected depending on success.
- EV Letters of Intent: Received new LoIs for manufacturing parts used in electric vehicles during the quarter; the current opportunity is mainly stator and rotors going into EV motors, with further opportunities dependent on how customers develop their platforms.
- Siemens locomotive opportunity: Siemens was awarded the 9000 hp locomotive contract less than a month ago; the company is in discussions with clients on supplying components and will try to bid for all products including motors, castings, and axle shafts, but supply chain crystallization will take time.
- Order book health: Received healthy order flows during the end of the quarter, which continued to boost the order book; management declined to split the ₹884 crores order book into railway and non-railway on the call.
- New product development: Developed laminations for electric mobility platforms, large hydro customers, and laminations for 1,200 MW and 1,400 MW pump storage applications during the quarter.
Akshay Pitti: "Siemens has been awarded this contract less than a month ago. For the supply chain to crystallize, it's going to take time. So, I can't comment on how they're going to structure their supply chain."
End-Market Demand & Segment Trends
- Railways and non-railways both strong: Going forward, management sees equally good demand from both railways and non-railways business.
- Renewable energy gaining share: Contribution moved from low single digits or zero to almost 5% of revenue over the past two and a half to three years, with opportunities already flowing, though moving large supply chains out of China takes time.
- Windmill components potential: Revenue potential close to ₹100 crores per annum over the next three years, focusing on generator parts, shafts, and smaller castings.
- Automotive development slow: Development from the customer end is going quite slow; while there is now quarter-on-quarter growth as of Q3, the original revenue timeline is seeing a push-out of six to eight months at the very minimum.
- EV competition still nascent: All products are currently in the developmental stage, so there is not really any competition for orders yet; it is more product development that is going on.
- Budget impact neutral: Management stated nothing much changes post the budget; the government has allocated money to projects already under discussion, so projects are going ahead rather than just being discussed.
Akshay Pitti: "So, far, all the products are in the developmental stage. So, there's not really any competition for orders, it's more of product development that is going on right now."
CAPEX & Capacity Expansion
- Phase-I CAPEX on track: Construction of new sheds and expansion-related work is on track to meet the earlier announced deadline of completion by the end of Q2 FY24; the remaining ₹60 crore spend relates predominantly to the lamination side, including transfer of lamination capacities from Hyderabad to Aurangabad and expanding the machining facility.
- Long lead-time machines ordered: Orders for longer lead-time machines have already been placed; machines with less than six months lead time have not been ordered yet because capacity is expected to come in by Q2 FY24.
- Phase-II CAPEX planned: The second CAPEX phase of ₹197 crores is planned to be covered starting 1st October 2023 through the end of 2024, involving modernization of the existing lamination facility in Hyderabad and expansion of machining facilities at both Hyderabad and Aurangabad.
- Current CAPEX sufficient for Siemens: Management stated the current CAPEX in process is more than sufficient to take care of requirements if a Siemens order is received; machining capacity will keep getting added further beyond Q2 FY24 as machines are required.
Balance Sheet & Working Capital
- Working capital reduced: Working capital outlay reduced by ₹85 crores QoQ because of softening raw material prices and easing supply chain bottlenecks, allowing the company to maintain optimal raw material and finished goods stocks.
- Net debt improvement: Net debt declined from ₹336 crores to ₹260 crores, with net debt-to-equity at 0.83x, alongside net worth improvement to ₹315 crores.
- Debt target: Targeted debt by end of FY23 should hover around the same level as Q3 end, about ₹260 crore to ₹280 crore, with management seeing no negative impact on the net debt side going forward as cash generation is robust.
- Q4 incentive: ₹30 crore expected in Q4.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Volume growth | Expect about 20% volume growth | FY24 |
| CAPEX completion (Phase-I) | Construction and expansion complete | End of Q2 FY24 |
| Phase-II CAPEX start | ₹197 crores modernization and expansion | 1st October 2023 through end of 2024 |
| EBITDA per ton | Move closer to ₹45,000 and upwards | Over the next two to three years |
| Windmill components revenue | Close to ₹100 crores per annum | Over the next three years |
| EV business opportunity | ₹30 crore to ₹40 crore per year | By two years from now, subject to development |
| Shaft business | Approximately $1 million per year in first phase | Over the next 10 years |
| Targeted debt | ₹260 crore to ₹280 crore | End of FY23 |
| Q4 incentive | ₹30 crore | Q4 FY23 |
Key Metrics
| Metric | Q3 FY23 |
|---|---|
| Revenue from operations | ₹239 cr, down 9.94% YoY from ₹265 cr |
| Sales volume | 9,150 MT, up from 8,500 MT YoY |
| Blended sale realization | ₹260,000 per MT |
| Blended EBITDA margin | ₹42,428 per MT |
| Net profit | ₹12.13 cr, up 5% YoY from ₹11.60 cr |
| Capacity utilization | 66.25% for Q3; 70% for 9M FY23 |
| Net worth | ₹315 cr as of December 2022 |
| Net debt | ₹260 cr, declined from ₹336 cr; net debt to equity at 0.83x |
| Working capital reduction | ₹85 cr on a QoQ basis |
| Five-year revenue CAGR | 20% |
| Five-year PAT CAGR | 35% |
| Assembled and value-added volumes growth | 14% YoY; loose laminations down 8% YoY |
| Order book | ₹884 cr as of December 31, 2022 |
| FY24 volume growth guidance | ~20% expected |
| EV business opportunity | ₹30–40 cr per year expected by two years from now |
| Windmill components revenue potential | ~₹100 cr per annum over the next three years |
| Shaft order business potential | ~$10 million over 10 years in first phase, ~$1 million per year |
| CAPEX incurred in 9M FY23 | ₹75 cr |
| Remaining CAPEX to be spent | ₹257 cr over the next two years; ₹60 cr from Phase I, ₹97 cr from Phase II pending |
| Machine hours | 4,00,000 as of December 2022; target 6,48,000 by end of December 2024 |
| Maharashtra government incentives expected in Q4 FY23 | ₹30 cr; FY22 received ₹12 cr, current year nil so far |
| Blended cost of finance | ~8% |
| Cold rolled silicon steel as share of total RM consumed | ~70% by value |
| Renewable energy revenue share | ~5% of revenue, up from low single digits or zero 2.5–3 years ago |