Key Takeaways
- Steady quarter, capex inflection ahead: PAT rose a modest ~4% YoY to ₹3,724 crores, but the real story is capex: FY25 plan revised up to ₹18,000 crores and FY26/27 targets of ₹25,000+ and ₹30,000+ crores signal a multi-year growth cycle.
- The order pipeline is the strongest in years: A ₹2.07 lakh crore total pipeline, ₹1.14 lakh crores work-in-hand, and 6 of 10 TBCB projects won this year give visibility that management calls unprecedented.
- Equipment supply is the bottleneck to watch: GIS, transformers and reactors face severe supply constraints and have seen ~70-80% cost inflation since 2017-18; the company is mitigating this with advanced procurement and longer supplier timelines.
- New businesses are taking shape: A first-of-its-kind ₹13,000 crore offshore wind order, a data center in Manesar, and smart metering mark a diversification beyond pure-play transmission.
- What to watch next quarter: Whether the ₹18,000 crore capex target is met or raised further, the pace of TBCB project awards from the ₹1 lakh crore bidding pipeline, and any resolution on equipment supply tightness.
Capex Inflection & Growth Visibility
- Capex is scaling sharply: FY25 plan raised from ₹15,000 to ₹18,000 crores, with RTM at ₹5,000 crores and other projects at ₹13,000 crores. FY26 is targeted at ₹25,000+ crores and FY27 at ₹30,000+ crores, driven by a surge in project wins.
- What is driving the upgrade: Six new projects won with 18-21 month completion schedules require spending in the current year. Management flagged that if more projects are won in FY25, the ₹18,000 crore figure could rise further.
- Capitalization to follow with a lag: FY25 capitalization is expected at ~₹18,000 crores, rising to ₹25,000-30,000 crores each in FY26 and FY27. Works worth ₹70,000-80,000 crores (excluding two large HVDC projects) are to be commissioned in the next 24-30 months.
- Debt headroom is ample: Shareholder approval exists for ₹1.8 lakh crore of debt against ₹1.2 lakh crore currently. The debt-equity ratio, now improved to 58:42, is expected to rise as capex picks up and new borrowings outpace scheduled repayments of ₹12,000-13,000 crores.
- Dividend policy supports growth: The current 67% payout leaves ~₹5,000 crores retained, which management says is sufficient to fund capex of ~₹20,000 crores easily, with debt available for the balance.
Tyagi: "Interregional capacity means power generated in one corner of the country can be transmitted to any other part of the country... So, there is no constraints in transmission of power across the country. So, it is the strongest grid 'One Frequency, One Nation, One Grid'."
Order Pipeline & Project Wins
The bidding engine is delivering: 6 out of 10 TBCB projects won so far this year, with a 70% share of total tariff value. Three wins came in Q1 and three more in July, spanning reactive compensation, RE evacuation, and HVDC.
| Project | Details |
|---|---|
| Q1 TBCB wins (3 projects) | Rajasthan RE Phase IV Part B & D, Fatehpur-Badla HVDC Phase III Part I; combined NCT ₹37,064 crores (Power Grid share ₹24,855 crores), tariff ₹7,045 crores (Power Grid share ₹4,935 crores) |
| July: Khavda reactive compensation | Dynamic Reactive Power Compensation at KPS 1 & KPS 3; NCT ₹501 crores, tariff ₹107 crores |
| July: Bhadla III & Bikaner III | Transmission for RE parks; NCT ₹1,382 crores, tariff ₹97 crores |
| July: South Olpad 765kV | NCT ₹4,766 crores, tariff ₹556 crores |
| Offshore wind (cost-plus) | First-of-its-kind ₹13,000 crore order for 1 GW evacuation (500 MW Gujarat + 500 MW Tamil Nadu); cost benchmark to be established from this project |
- Pipeline depth: Total pipeline stands at ₹2,07,500 crores, with ₹1,90,500 crores in transmission (ISTS, intra-state, cross-border, international) and ₹17,000 crores in other businesses. More than ₹1 lakh crore of transmission projects are in sight, with 70-80% expected to be cleared this financial year.
- HVDC projects advancing: Leh-Kaithal HVDC (5 GW) was tendered on 17th July with commercial bids expected by December and award by January/February. Fatehpur-Bhadla HVDC is almost ready for award. Khavda HVDC bid submission is expected in ~10 days.
- Bidding discipline intact: Management emphasized an internal board-mandated hurdle rate and stated it does not bid blindly to win all projects, implying returns are protected even as volumes grow.
Ravisankar: "IRR will be good. Otherwise, I can win all the 100%. So, be sure that we have an internal hurdle rate within the board and then we take a call cautiously. We don't play blind and then win all the projects."
Equipment Supply & Cost Pressures
- Where the bottlenecks are: Circuit breakers, current transformers, surge arresters and tower structures face no supply challenge. GIS, transformers and reactors are a big challenge. For GIS, equipment is available in India but the GIB part remains a constraint being taken up with manufacturers.
- Cost inflation is structural: Transformers, reactors and GIS cost ~70-80% more than in 2017-18, compounding at ~10% per year. The company is managing this by giving suppliers 24-30 month schedules versus the typical 15-18 months, locking in costs earlier.
- Mitigation through procurement: Advanced and bulk procurement of constrained items is underway. The longer supply timelines are designed to give manufacturers visibility and contain further escalation.
New Business Diversification
- Data center entry: A 1,000-rack facility at Manesar is under construction. Phase 1 capex is ~₹700+ crores, Phase 2 ~₹2,000 crores, with Phase 1 expected commercially available in Q4 of this financial year. The company is evaluating expansion to Bangalore, Hyderabad, Chennai and other metros, positioning to fill a gap in government-owned data centers.
- Offshore wind transmission: The ₹13,000 crore cost-plus order is India's first offshore power evacuation project. Management acknowledged the first project may have higher costs than routine projects, with future costs optimizable once a benchmark is established.
- Green hydrogen grid buildout: Hubs are being developed at Gopalpur & Paradeep (Odisha), Kakinada (Andhra Pradesh), Khandala & Gujarat (two hubs), and Tuticorin (Tamil Nadu) to support the National Green Hydrogen Mission's ~125 GW evacuation requirement.
- Telecom recovery: Income rose to ₹219 crores from ₹191 crores YoY, with 35 new customers added and network capacity enhanced by 1.8 Tbps. The legacy telecom business has been carved into a separate SPV (PTSL).
Mohan: "We find that this is a natural progression for us to put in the data centers. We find a good amount of traction in this."
Operational Performance & Profitability
- Transmission availability: Maintained at 99.80%, the regulatory cap for incentives, which the company has achieved for five consecutive years. Tripping per line improved to 0.09 (one trip in four years) from 0.28 last year.
- Standalone profit was flattish due to three one-off factors: lower dividend drawn from SPVs (~₹80 crore less vs Q1 FY24), a prior-year one-time order impact of ~₹150 crore, and the discontinued telecom operations impact of ₹58 crore. Underlying growth was ~₹70 crore.
- SPV dividend timing: The Q1 decline in dividends from TBCB subsidiaries reflects a timing difference: in FY23, not everything was drawn in Q4, so more was drawn in Q1 FY24. Management stated all SPV board meetings will conclude and amounts will be drawn before Q2, with no purpose in keeping money in subsidiaries.
- Commercial health: Realization stood at 91.87%, and outstanding dues reduced from ₹7,140 crores last year to ₹5,548 crores.
Tyagi: "Our availability of 99.80 is best as compared to other utilities, whether it is SGC China or it is AEP USA or Furnas Brazil or Eskom South Africa or NGC UK."
Sustainability & Technology Initiatives
- SF6 gas replacement challenge: SF6 is 23,000 times more harmful than CO2 and persists in the environment for ~3,000 years. Management acknowledged this as a critical challenge, noting that innovations are ongoing worldwide and that finding an alternative would simplify the net-zero journey.
- Satellite-based monitoring: An MoU with ISRO has been signed to create a spatial decision support system for transmission tower management, particularly in hills, riverside and landslide-prone areas.
- AI-enabled substation inspection: A robot developed with IIT-Kanpur is deployed at Kanpur for inspection of transformers, breakers, CT and CVTs, using AI/ML to improve efficiency, with plans to replicate at other stations.
- Sustainability targets: 50% electricity consumption from RE by 2025, net water positive by 2030, zero waste to landfill by 2030, and net zero by 2047.
Tyagi: "SF6 gas is almost 23,000 times harmful as compared to CO2. That means 1kg of SF6 gas, if it goes to atmosphere, it is equivalent to 23,000 times of CO2 and it remains in the environment for almost 3,000 yrs. So it is very harmful gas for environment. So we have to look for alternatives to this SF6 gas."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capex | ₹18,000 crores; could increase if more projects won | FY25 |
| Capex | ₹25,000+ crores | FY26 |
| Capex | ₹30,000+ crores | FY27 |
| Capitalization | ~₹18,000 crores | FY25 |
| Capitalization | ~₹25,000-30,000 crores each | FY26 & FY27 |
| Project commissioning | ₹70,000-80,000 crores of works (ex-HVDC Leh-Kaithal & Fatehpur-Bhadla) | Next 24-30 months |
| Leh-Kaithal HVDC | Commercial bids by December, award by January/February; commissioning in 5 years | Award by Feb 2025 |
| Fatehpur-Bhadla HVDC | First Bipole in 48 months, second in 54 months | 4-4.5 years from award |
| Data center Phase 1 | Commercially available | Q4 FY25 |
| SPV dividend | All board meetings to conclude, amounts drawn | Before Q2 FY25 |
| Bidding pipeline clearance | 70-80% of ₹1 lakh crore+ transmission projects | FY25 |
Key Metrics
| Metric | Q1 FY25 |
|---|---|
| Total Income (consolidated) | ₹11,280 cr, up from ₹11,258 cr YoY |
| Profit After Tax (consolidated) | ₹3,724 cr, up ~4% YoY from ₹3,597 cr |
| Earnings Per Share | ₹4 per share |
| Gross Fixed Assets | ₹2,77,000 cr as on 30th June |
| Work in Progress | ₹21,758 cr |
| Debt | ₹1,23,465 cr |
| Net Worth | ₹90,913 cr |
| Debt-to-Equity ratio | 58:42, improved from 59:41 YoY |
| Return on Net Worth | 4.10 (Q1 only) |
| Average cost of borrowing | 7.76% |
| CapEx (consolidated) | ₹4,615 cr; standalone RTM ₹1,711 cr |
| Capitalization (consolidated) | ₹2,320 cr; standalone ₹1,348 cr |
| Transmission system availability | 99.80%, above 99.75% incentive cap |
| Tripping per line | 0.09, improved from 0.28 in FY24 |
| Commercial realization rate | 91.87%; billing ₹9,262 cr, realization ₹8,509 cr |
| Outstanding dues | ₹5,548 cr, down from ₹7,140 cr YoY |
| Telecom income | ₹219 cr, up from ₹191 cr YoY |
| TBCB wins (Q1 + July) — POWERGRID share of tariff | ₹4,935 cr, 70% of total ₹7,045 cr bid out |
| TBCB wins (Q1 + July) — POWERGRID share of NCT cost | ₹24,855 cr, out of total ₹37,064 cr |
| Work in hand | ₹1,14,139 cr; RTM ongoing ₹10,318 cr, new RTM + TBCB + other ₹66,811 cr |
| FY25 CapEx plan (revised) | ₹18,000 cr, upgraded from ₹15,000 cr; RTM ₹5,000 cr, other ₹13,000 cr |
| FY26 CapEx target | ₹25,000+ cr (per management outlook) |
| FY27 CapEx target | ₹30,000+ cr (per management outlook) |
| Data center Phase 1 cost (Manesar) | ₹700+ cr, 1,000 racks, expected Q4 FY25 |