Power Grid Corporation of India Ltd Q1 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/hhwz9pqyqirqgjm2217tu3z6.pdf

Key Takeaways


Capex Inflection & Growth Visibility

Tyagi: "Interregional capacity means power generated in one corner of the country can be transmitted to any other part of the country... So, there is no constraints in transmission of power across the country. So, it is the strongest grid 'One Frequency, One Nation, One Grid'."

Order Pipeline & Project Wins

The bidding engine is delivering: 6 out of 10 TBCB projects won so far this year, with a 70% share of total tariff value. Three wins came in Q1 and three more in July, spanning reactive compensation, RE evacuation, and HVDC.

ProjectDetails
Q1 TBCB wins (3 projects)Rajasthan RE Phase IV Part B & D, Fatehpur-Badla HVDC Phase III Part I; combined NCT ₹37,064 crores (Power Grid share ₹24,855 crores), tariff ₹7,045 crores (Power Grid share ₹4,935 crores)
July: Khavda reactive compensationDynamic Reactive Power Compensation at KPS 1 & KPS 3; NCT ₹501 crores, tariff ₹107 crores
July: Bhadla III & Bikaner IIITransmission for RE parks; NCT ₹1,382 crores, tariff ₹97 crores
July: South Olpad 765kVNCT ₹4,766 crores, tariff ₹556 crores
Offshore wind (cost-plus)First-of-its-kind ₹13,000 crore order for 1 GW evacuation (500 MW Gujarat + 500 MW Tamil Nadu); cost benchmark to be established from this project
Ravisankar: "IRR will be good. Otherwise, I can win all the 100%. So, be sure that we have an internal hurdle rate within the board and then we take a call cautiously. We don't play blind and then win all the projects."

Equipment Supply & Cost Pressures


New Business Diversification

Mohan: "We find that this is a natural progression for us to put in the data centers. We find a good amount of traction in this."

Operational Performance & Profitability

Tyagi: "Our availability of 99.80 is best as compared to other utilities, whether it is SGC China or it is AEP USA or Furnas Brazil or Eskom South Africa or NGC UK."

Sustainability & Technology Initiatives

Tyagi: "SF6 gas is almost 23,000 times harmful as compared to CO2. That means 1kg of SF6 gas, if it goes to atmosphere, it is equivalent to 23,000 times of CO2 and it remains in the environment for almost 3,000 yrs. So it is very harmful gas for environment. So we have to look for alternatives to this SF6 gas."

Guidance & Commitments

CommitmentSpecificsTimeline
Capex₹18,000 crores; could increase if more projects wonFY25
Capex₹25,000+ croresFY26
Capex₹30,000+ croresFY27
Capitalization~₹18,000 croresFY25
Capitalization~₹25,000-30,000 crores eachFY26 & FY27
Project commissioning₹70,000-80,000 crores of works (ex-HVDC Leh-Kaithal & Fatehpur-Bhadla)Next 24-30 months
Leh-Kaithal HVDCCommercial bids by December, award by January/February; commissioning in 5 yearsAward by Feb 2025
Fatehpur-Bhadla HVDCFirst Bipole in 48 months, second in 54 months4-4.5 years from award
Data center Phase 1Commercially availableQ4 FY25
SPV dividendAll board meetings to conclude, amounts drawnBefore Q2 FY25
Bidding pipeline clearance70-80% of ₹1 lakh crore+ transmission projectsFY25

Key Metrics

MetricQ1 FY25
Total Income (consolidated)₹11,280 cr, up from ₹11,258 cr YoY
Profit After Tax (consolidated)₹3,724 cr, up ~4% YoY from ₹3,597 cr
Earnings Per Share₹4 per share
Gross Fixed Assets₹2,77,000 cr as on 30th June
Work in Progress₹21,758 cr
Debt₹1,23,465 cr
Net Worth₹90,913 cr
Debt-to-Equity ratio58:42, improved from 59:41 YoY
Return on Net Worth4.10 (Q1 only)
Average cost of borrowing7.76%
CapEx (consolidated)₹4,615 cr; standalone RTM ₹1,711 cr
Capitalization (consolidated)₹2,320 cr; standalone ₹1,348 cr
Transmission system availability99.80%, above 99.75% incentive cap
Tripping per line0.09, improved from 0.28 in FY24
Commercial realization rate91.87%; billing ₹9,262 cr, realization ₹8,509 cr
Outstanding dues₹5,548 cr, down from ₹7,140 cr YoY
Telecom income₹219 cr, up from ₹191 cr YoY
TBCB wins (Q1 + July) — POWERGRID share of tariff₹4,935 cr, 70% of total ₹7,045 cr bid out
TBCB wins (Q1 + July) — POWERGRID share of NCT cost₹24,855 cr, out of total ₹37,064 cr
Work in hand₹1,14,139 cr; RTM ongoing ₹10,318 cr, new RTM + TBCB + other ₹66,811 cr
FY25 CapEx plan (revised)₹18,000 cr, upgraded from ₹15,000 cr; RTM ₹5,000 cr, other ₹13,000 cr
FY26 CapEx target₹25,000+ cr (per management outlook)
FY27 CapEx target₹30,000+ cr (per management outlook)
Data center Phase 1 cost (Manesar)₹700+ cr, 1,000 racks, expected Q4 FY25