Power Grid Corporation of India Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/xdbqousobv3tx924wq263is5.pdf

Key Takeaways


Capex Trajectory & the Transmission Super-Cycle

Ravisankar: "company there is no change in the basics and the operational maintenance and the availability continue to be above 99.75 and then the lot of CapEx is on the growing side and we hope that it crosses at least 15,000 next year. This is what is our aspiration and then a lot of outlook is bright"

Leh Ladakh: The Marquee Project with Real Constraints

Ravisankar: "It envisages 40% of the financial assistance in the form of grant, and it has a timeline of 5 years for completion. And, being a difficult terrain at a high altitude of 4,700 mts above sea level with sub-zero temperatures, the working conditions there are hardly 5-6 months in a year."

TBCB Wins & the Competitive Position

Ravisankar: "if the normally, when the timeline is 18 months and above, there are players who can supply the equipment. This is one part and as far as TBCB and most of our contracts are on firm price, we are somewhat insulated from the price escalations"

New Business Diversification

Ravisankar: "As regards this undersea cable, it is in a very preliminary stage. There are talks about connecting Oman or connecting Singapore or connecting Maldives, Sri Lanka. So, there are some inter-country connections, sea cable projects are understudy. As of now, there is no concrete agreement or order from any of the countries."

Financial Health & Dues Resolution

Ravisankar: "we have again requested them to make the payment of whatever the adjustment and Telangana will be paying now. So, they have adjusted around 450 crores which they will be paying now and Tamil Nadu also has to pay... As of now, we feel that yes, it should see an end."

Regulatory & Structural Watchpoints

Ravisankar: "As of now, the NMP guidelines doesn't permit to transfer the shares permanently to an SPV, not only PG InvIT to any anyone. So, this is what the NMP guideline says."

Guidance & Commitments

CommitmentSpecificsTimeline
FY24 capex~₹10,000 crores (up from ₹8,800 crores guided)FY24
FY24 capitalization₹10,000 crores (₹4,000 crores already done in H1)FY24
FY25 capex₹12,500 crores, with aspiration to cross ₹15,000 crores if HVDC projects wonFY25
FY25 capitalizationAbove ₹15,000 crores, projecting ~₹17,000 croresFY25
Leh Ladakh Phase-I studyFirst phase report from HVDC playersMarch-April 2024
Leh Ladakh project awardTargeting awardFY25 Q4 to FY26 Q1
Manesar data centerCompletion12-15 months
Nagda 85 MW solar plantCommissioning~12 months
Smart meter supply startSupply from Gujarat orders to beginEnd of December 2023 / early January 2024
CERC draft tariff regulationsPublication expectedNovember/December 2023
InvIT balance stake transferDecision on 26% stake transfer for 4 eligible projectsQ4 FY24
Bidding pipeline conversion₹59,700 crores under bidding to be bid out12-18 months
9-year capex target₹1,80,000 crores totalBy 2032
9-year intra-state TBCB target₹30,000-35,000 crores (assuming 50% strike rate)By 2032

Key Metrics

MetricQ2 FY24
Standalone revenue₹11,206 cr, up from ₹11,004 cr QoQ
Standalone PAT₹3,834 cr, up 5% QoQ from ₹3,651 cr
Consolidated income₹11,530 cr, up from ₹11,349 cr QoQ
Consolidated PAT₹3,781 cr, up 4% QoQ from ₹3,650 cr
H1 standalone revenue₹22,094 cr, vs ₹22,094 cr in H1 FY23
H1 standalone PAT₹7,377 cr, vs ₹7,417 cr in H1 FY23 (prior year had one-time income)
H1 consolidated income₹22,788 cr, vs ₹22,788 cr in H1 FY23
H1 consolidated PAT₹7,379 cr, vs ₹7,452 cr in H1 FY23
H1 capex₹4,246 cr, against full-year target of ₹8,800 cr; full-year now expected ~₹10,000 cr
H1 capitalisation₹4,000 cr, ₹1,600 cr in Q1 plus ₹2,400 cr in Q2; full-year target ₹10,000 cr
FY25 capex target₹12,500 cr, initial target as of now, could rise with HVDC wins
FY25 capitalisation target~₹17,000 cr, above ₹15,000 cr projected
System availability99.85% for H1 FY24, above 99.75%
Tripping rate0.16, improved from 0.20 in previous half year
Debt-to-equity ratio58:42, improved from 59:41 last quarter and 61:39 last year
Borrowing cost average7.61%, up from 7.59% last quarter on hardening rates
Realisation rate92.37%, up from last quarter
Work in hand~₹60,000-65,000 cr, including recently won projects; base ₹50,500 cr plus ₹8,000-9,000 cr
Projects under bidding pipeline₹59,700 cr, expected to be bid out in 12-18 months
TBCB projects won in FY24 (up to Q2)4 projects, annual tariff ₹703 cr, NCT cost ₹6,393 cr; plus one subsequent win of ₹4,700 cr NCT
TBCB half-yearly revenue (standalone)₹1,300 cr, with profit of ₹413 cr
Cumulative equity infused in TBCB₹4,100 cr, up from ₹3,600 cr in Q2 FY23
Regulated equity (RTM)~₹82,000 cr, reserves and surplus ₹86,000 cr less ₹4,100 cr TBCB equity
Telecom income₹202 cr in Q2, cumulative H1 ₹393 cr; full-year target ₹800 cr
Consultancy income₹155 cr in Q2, declining as NERPSIP scheme winds down
LPS rule collections₹1,383 cr received against ₹2,400 cr from six discoms
Return on net worth8.51%
Book value per share₹93.22, post bonus issue; was ₹114 previously
Gross fixed assets (consolidated)₹2.73 lakh cr, standalone ₹2.57 lakh cr
Capital work-in-progress (consolidated)₹14,900 cr, closely ₹15,000 cr
Data center investment approval₹713 cr for Manesar pilot, completion in 12-15 months; ₹1,000 cr projected till 2032
Smart metering contracts69 lakh meters from two Gujarat discoms; ₹15,000 cr projection over 9 years
Leh Ladakh project cost₹20,700 cr total, includes ₹8,000 cr grant; PowerGrid capex portion ₹13,000 cr