Power Grid Corporation of India Ltd Q3 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/19s4klznzlv4er6wo7qtk5qr.pdf

Key Takeaways


Capex Trajectory & Execution

R. K. Tyagi: "If we look at this outlook upto 2032, we have interstate intrastate cross border. If we add all the sectors and possible capex, so we are touching somewhere 200,000+ capex in the next 7-8 years."

TBCB Wins & Competitive Positioning

Ravindra Kumar Tyagi: "Now we are more aggressive because we had to compete. If we have to survive, if we have to take care of the interest of our investors, so definitely we had to….growth has to be maintained."

Balance Sheet & Capital Management


Regulatory & Policy Environment

Ravindra Kumar Tyagi: "Discussions are going on and we are hopeful that whatever regulations and norms were there, they will continue. So there will not be any impact on Power Grid, revenue or profitability."

New Initiatives & Diversification


Operational Performance


Guidance & Commitments

CommitmentSpecificsTimeline
FY24 CapEx₹10,000 crore plus (raised from ₹8,800 crore)FY24
FY25 CapEx₹15,000 crore plusFY25
FY26 CapEx₹20,000 crore plusFY26
FY24 Capitalization~₹8,500 croreFY24
FY25 Capitalization~₹16,000-17,000 croreFY25
Nagda Solar Plant85 MW commissionedQ3 CY24 (Aug-Sep)
Leh Ladakh FEED completionFEED studies completeMarch 2024
Leh Ladakh FEED2 outcomeOutcome of FEED2December 2024
Leh Ladakh NITNotice inviting tenderJanuary 2025
Leh Ladakh order placementOrder placedMarch 2025
Leh Ladakh project completionProject realityFY30
Fatehpur-Badla HVDC awardAwardedWithin FY24
Fatehpur-Badla HVDC capex startReal capex beginsLast quarter FY25
Fatehpur-Badla HVDC completionBipole 1: 48 months, Bipole 2: 54 months~4.5 years from start
FY25-26 capex true-upPossible guidance revision after 6 monthsMid-CY24

Key Metrics

MetricQ3 FY24
Consolidated revenue₹11,820 cr, vs ₹11,281 cr in Q3 FY23
Standalone revenue₹11,468 cr, vs ₹11,281 cr in Q3 FY23
Consolidated PAT₹4,028 cr, vs ₹3,702 cr in Q3 FY23
Standalone PAT₹3,970 cr, vs ₹3,702 cr in Q3 FY23
Consolidated EBITDA margin80% plus, for 9M FY24
9M FY24 consolidated revenue₹34,608 cr
9M FY24 consolidated PAT₹11,407 cr
9M FY24 EPS₹12.26, vs ₹11.93 as on 31-12-22
Q3 CapEx (consolidated)₹3,444 cr; 9M FY24: ₹7,690 cr
Q3 capitalization₹1,784 cr; 9M FY24: ₹5,780 cr
FY24 CapEx guidance₹10,000 cr plus, hopeful; by Jan'24 already achieved ~₹8,700 cr
FY25 CapEx guidance₹15,000 cr plus, close to $2 billion
FY26 CapEx guidance₹20,000 cr plus, close to $3 billion
FY24 capitalization guidance₹8,000-8,500 cr
FY25 capitalization guidance₹16,000-17,000 cr
Work in hand₹77,770 cr: ongoing RTM ₹11,450 cr, new RTM ₹24,800 cr (incl. Leh-Kaithal HVDC ₹20,000 cr+), TBCB ₹41,450 cr
TBCB projects won in Q3 FY246 projects, NCT cost ~₹20,000 cr, annual tariff ₹1,636 cr
TBCB projects won in 9M FY24₹26,000 cr worth, annual tariff ₹2,340 cr; winnability ~67% tariff-wise
Transmission system availability99.86% in FY24 so far, vs 99.81% in 9M FY23
Tripping rate0.22 per line in FY24 so far, vs 0.27 per line last year
Gross fixed assets₹2,74,000 cr; CWIP ~₹16,600 cr
Loan/Debt₹1,19,000 cr, reduced from ₹1,28,000 cr
Net worth₹87,194 cr, vs ₹82,226 cr last year
Debt-equity ratio58:42, improved from 61:39 last year
Return on net worth13.08%, vs 13.50% last year
Receivables >45 days₹4,181 cr; TNEB/TANGEDCO ~₹2,200 cr, plus J&K, M.P., U.P.
Consultancy income₹116 cr in 9M FY24
PowerTel first-quarter income (from Oct'23)₹201 cr; 17 new customers, ₹362 cr multi-year orders
Securitization in FY24₹5,700 cr loan taken, vs ₹3,400 cr last year
Q3 transmission capacity added3,100 MVA transformation capacity, 834 circuit km of lines
Nagda Solar Plant capacity85 MW, expected Q3 FY25 (Aug/Sep 2024)
Ladakh RDSS project cost₹862 cr, agreement signed in Q3
ISTS pipeline (CEA plan)₹2,44,000 cr total; ₹96,000 cr awarded, ₹84,000 cr under bidding, ₹64,000 cr yet to be bid
NEP ISTS target (FY22-27)₹3,10,000 cr
Capex visibility up to 2032₹200,000 cr plus
ROE on new assets (draft CERC)15% indicated for projects commissioned after Apr 1, 2024; old assets grandfathered at 15.5%