Power Grid Corporation of India Ltd Q3 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/994j9v5trf6u24rad1l95h0q.pdf

Key Takeaways


Execution Turnaround & Project Delivery

Dr. R.K. Tyagi: "With the support of Government of India, with the support of our stakeholders, we have been able to resolve many of the issues. And now, our execution of projects, our performance is improving in all areas, unlike last year wherein we had number of challenges in commissioning our projects."

The Multi-Year Capex Cycle

Dr. R.K. Tyagi: "RE projects are very critical projects which are commissioned and we don't want that any power RE power, Green power, which is almost free given by nature. So, it should not be curtailed at any cost. So, we want to focus on these projects so that no power is curtailed in India."

HVDC & Major Project Pipeline


Supply Chain: The Critical Constraint

Dr. R.K. Tyagi: "unless until the Chinese companies available in India, if relaxation by Government of India is given, then it is going to boost the transmission sector. So, it should be a good move for everybody."

New Business & Diversification


Financial & Operational Performance


ESG & Technology Milestones

Dr. R.K. Tyagi: "It is a vegetable oil. It can be easily decomposed unlike mineral oil. So, it is a step towards ESG."

Guidance & Commitments

CommitmentSpecificsTimeline
FY26 CapEx₹32,000 crores (raised from ₹28,000 cr)By March 2026
FY26 Capitalization₹22,000 crores (raised from ₹20,000 cr)By March 2026
FY27 CapEx₹37,000 croresFY27
FY28 CapEx₹45,000 croresFY28
FY27 Capitalization₹30,000 croresFY27
FY28 Capitalization₹35,000 croresFY28
Barmer II to South Kala Amb HVDC award~₹35,000 crore project, OBD1st April 2026
Bikaner V to Begunia HVDC awardExpected to be awardedFY27
Paradeep to Andaman HVDC commissioning320 kV, 500 MW, ~₹31,000 cr2031-2032
Annual transmission line targetClose to 5,500 ckmBy March 2026
Annual transformer capacity targetClose to 60,000 MVABy March 2026
Project pipeline commissioning₹1,95,000 crores (works in hand + WIP)Next 3-4 years

Key Metrics

MetricQ3 FY26
Total Income (standalone)₹12,436 cr, +7% YoY
Total Income (consolidated)₹12,599 cr, +7% YoY
EBITDA (9M)₹29,846 cr
Profit After Tax (standalone)₹4,160 cr, +7% YoY
Profit After Tax (consolidated)₹4,185 cr, +8% YoY
Earnings Per Share₹12.24, vs ₹12.23 YoY
Gross Fixed Assets (consolidated)₹3,04,336 cr, crossed ₹3 lakh crore for the first time
Net Worth₹98,906 cr, vs ₹91,000 cr YoY
Debt/Equity Ratio59:41
Return on Net Worth11.51%, vs 12.42% YoY
Trade Receivable Days24.65 days, lowest ever at end of Q3
CapEx (9M)₹26,761 cr, vs ₹17,651 cr YoY
Capitalization (9M)₹12,915 cr, vs ₹7,423 cr YoY
Works in Hand₹1,45,513 cr, plus ₹50,000 cr work in progress
Transmission System Availability99.84%
Telecom Income₹879 cr, vs ₹825 cr YoY
Consultancy Income₹1,173 cr, vs ₹427 cr YoY
FY26 CapEx Guidance (revised)₹32,000 cr, raised from ₹28,000 cr
FY26 Capitalization Guidance (revised)₹22,000 cr, raised from ₹20,000 cr
FY27 CapEx Guidance₹37,000 cr
FY28 CapEx Guidance₹45,000 cr
FY27 Capitalization Guidance₹30,000 cr
FY28 Capitalization Guidance₹35,000 cr
TBCB Market Share Guidance50–60% of new interstate projects
Renewable Power Consumption50% of total power consumption met through renewable in Dec 2025