Key Takeaways
- Capitalization miss, execution rebound promised: FY25 capitalization reached only ~INR 9,000 crores against a INR 16,000-17,000 crore target due to ROW, supply and skilled manpower challenges, but management expects much faster execution in FY26 now that ROW compensation guidelines are settled.
- TBCB wins dominate the growth story: POWERGRID won 24 TBCB projects costing ~INR 92,000 crores in FY25, capturing over 54% market share by project count, including its first TBCB HVDC project (Khavda to Nagpur).
- Capex trajectory steepens sharply: FY26 capex is guided at INR 28,000-30,000+ crores, rising to INR 35,000 crores in FY27 and INR 45,000 crores in FY28, with the bulk of HVDC spend landing after FY28.
- Dividend may compress further: Payout already reduced by ~INR 2-2.25 per share, and management flagged it may fall further from INR 9 as equity requirements rise to fund the capex cycle.
- What to watch next quarter: Whether Q1 FY26 actually delivers the promised capitalization catch-up from delayed projects, the pace of HVDC award decisions (Leh-Ladakh, South Olpad), and any dividend clarity as the INR 28,000-30,000 crore capex plan firms up.
Capitalization & Execution
- FY25 fell well short: Capitalization of INR 9,014 crores missed the INR 16,000-17,000 crore target, with management citing ROW issues, supply chain constraints, skilled manpower shortages, and Central Government elections as the drag. Delays concentrated in Rajasthan, Haryana, Delhi and Gujarat.
- ROW compensation was the bottleneck: New Government of India guidelines in June 2024 and March 2025 changed land compensation methodology, requiring two valuers (one from the developer, one from farmers) to determine market rates. State governments were slow to adopt the new framework, stalling project execution.
- Change of law claims to follow: Management expects to claim differential compensation amounts under change of law provisions since policies shifted from the October 2015 baseline, and also expects to claim increased IDC from project overruns caused by these delays.
- Spillover now targeted for Q1 and Q2 FY26: Delayed projects are planned for commissioning in Q1 FY26, with some potentially slipping to Q2. Management expects execution to be "much faster" in FY26 now that ROW guidelines are settled.
- Operational excellence intact despite delays: System availability hit 99.82% (above the 99.75% incentive cap), tripping performance improved to 0.27 per line per year, and the company commissioned a Sikar 765 kV substation in 9-10 months from land acquisition, which management called a potential world record.
Tyagi: "because of this, there are challenges of RoW and supply issues and skill manpower, we are facing problems of skilled manpower. And then there was election also in Central Government. So because of that, there have been some delays especially RoW issues in Rajasthan, Haryana, Delhi and Gujarat, so that led to some delays in this capitalization of or commissioning of some projects"
TBCB Wins & Bid Pipeline
- FY25 was a record win year: POWERGRID won 24 TBCB projects with an NCT cost of ~INR 92,000 crores, capturing 57.34% market share by NCT cost and 54.55% by project count.
- Flagship wins include first TBCB HVDC: Key projects won include the Rajasthan Phase IV Part 4 Part A system (Bikaner to Siwani), the Khavda to Nagpur HVDC (6,000 MW, NCT INR 24,000 crores vs actual ~INR 33,000-34,000 crores), Kurnool area Phase I (4.5 GW), and Khavda Phase IV Part B (7 GW).
- Bid pipeline remains deep: Current visible pipeline stands at ~INR 45,000-46,000 crores, with more projects expected to become visible in 2-3 months. Management noted ~INR 6 lakh crore of TBCB projects still to be allocated by 2032, with all balanced projects likely allocated in the next 4 years given 2-3 year execution timelines.
- Competitive discipline holding: Management stated it does not bid below a fixed ROE threshold (more than 12-13%) and maintains that discipline, with a "very good" win rate evidenced by the INR 92,000 crore haul.
- Intra-state TBCB is the next frontier: Uttar Pradesh, Madhya Pradesh, Rajasthan, Odisha and Maharashtra have already launched intra-state TBCB projects, with NEP indicating ~INR 3 lakh crore+ of intra-state capex. Management expects to win some of these and sees no difference in interest versus inter-state TBCB.
Tyagi: "This is as of now, but more projects are in pipeline, visibility of those projects will be seen after maybe 2, 3 months."
Capex Trajectory & HVDC Outlook
- Capex scales up materially: FY26 target is INR 28,000 crores, likely rising above INR 30,000 crores (exact figure after 3 months), with FY27 at INR 35,000 crores and FY28 at INR 45,000 crores. FY25 actual capex was INR 26,255 crores, exceeding the ~INR 20,000 crore target.
- HVDC capex is back-end loaded: For the two large HVDC projects (Kaithal to Pang and Khavda to Nagpur), only 20-30% of capex falls up to FY28, with the majority coming after that.
- HVDC award pipeline taking shape: Leh-Ladakh HVDC (land acquired, infrastructure work ongoing, bids under evaluation) is expected to be awarded in Q2 FY26. South Olpad HVDC RFP is issued with bids due soon. Barmer to Maharashtra and Kurnool to Vizag are likely LCC technology, while VSC is reserved for cross-border links (India-Oman, Oman-UAE, Singapore-India).
- Paradeep-Andaman-Singapore visibility still low: Government of India is still working out capacity and methodology; management expects clearer visibility in Q2.
- Bulk procurement strategy deployed: Given huge demand and 18-21 month lead times for transformers, POWERGRID is procuring strategic equipment (transformers, GIS, conductor, insulator, tower material) in advance.
Tyagi: "you will appreciate that height is about 4,500 meters to 5,000 meters. So, there are technological challenges. And worldwide, there is no experience at this height."
Technology & Operational Innovation
- World-first 765 kV digital substation: Commissioned at Navsari, reducing CO2 footprint, enabling remote testing, cutting downtime, and minimizing maloperation risk from EMI/EMC interference.
- Insulated cross arm technology ready for deployment: For 400 kV lines, developed by two parties with supply expected by May-end; reduces ROW from ~46 meters to ~36 meters using compact horizontal B-strings. Deployment expected in FY26.
- Construction records set: One 37.4 metric ton 765 kV DA-type tower erected in a single day (vs normal 8-10 MT/day) on the Banaskantha to Ahmedabad line. Six 400/220 kV 500 MVA transformers commissioned at Bikaner II in a single financial year.
- Advanced techniques now standard: Crane-based tower erection at 400 kV and 765 kV, drone-based stringing for power line crossings and hilly areas, prefabricated firewalls and cable trenches, Porta Decks for heavy equipment movement in rainy season, and centralized camera-based monitoring of all sites from Gurgaon.
- Technology pipeline advancing: SF6 circuit breakers at 145 kV (pilot), with 220 kV and 400 kV under consideration; super-hydrophobic insulator coating; non-destructive testing of tower members; mobile GIS Bay for 400/132/220 kV; wireless strain gauge technology; heavy lift programmable drones for remote areas.
- Zojila pass underground cable: A 12-km underground cable being laid between Minamarg and Zojila top to bypass an avalanche-prone overhead line, securing power supply to Leh.
Tyagi: "I think, which may be world record that in 9 months or 10 months, any 765 kV substation can be commissioned that, but our project management has shown that it is possible that we can commission in 9 to 10 months."
Financial Health & Shareholder Returns
- ROE dipped ~100 bps in FY25: Consolidated ROE declined due to capitalization delays and other issues. Management did not directly answer whether ROE has stabilized, pivoting instead to dividend and equity requirement discussions.
- Dividend under pressure from capex needs: Payout reduced by ~INR 2-2.25 per share, and may fall further from INR 9 as more equity is required to fund the INR 28,000-30,000 crore capex plan.
- Telecom segment crossed INR 1,000 crores: Income reached INR 1,128 crores (vs INR 910 crores last year), with backbone availability at 100%.
- Consultancy revenue grew strongly: Revenue from operations rose to INR 799 crores from INR 553 crores last year, with 16 international and 80 domestic assignments ongoing.
- RE project risk contained: Management clarified that transmission lines are not dependent on PPA signing; projects get separate timelines and tariffs start upon commissioning, so POWERGRID is not affected by RE delays or PPA issues.
- 85 MW solar PV project at Nagda: Commissioned in April 2025, selling 70-80% of electricity through GDAM and real-time markets on power exchanges.
Tyagi: "Our transmission line is not dependent on whether PPA is signed or not. Normally, we are given any project for which a separate timeline is given. Once we commission any RE project or any project for that matter, we start getting our tariffs. So, we are not having any risk of whether RE is delayed or PPA is signed or not. POWERGRID as such will not be affected by any of these issues."
ESG & Sustainability
- Net Zero by 2047: A dedicated ESG and Net Zero group has been formed. Interim targets include 50% of electricity consumption from RE before December 2025 (currently 36%), Net Water Positive by 2030, and Zero Waste to Landfill by 2030.
- Green Hydrogen pilot: At Neemrana Substation, likely to be awarded in June 2025 with ~12-month implementation schedule.
- Natural ester oil adoption: First 132/33 kV, 10 MVA ICT at HVDC Pusauli successfully charged after retrofilling with natural ester oil. A 400/220 kV, 315 MVA ICT with natural ester oil is likely to be commissioned in FY26.
- Skill development expanding: Three centers operational (Malda, Banka, Bassi), with two more being worked on at Rajgad and Rourkela in Odisha.
- International benchmarking confirms efficiency: In ITOMS 2025 by UMS Group (U.S.), POWERGRID ranked in quadrant 1 (low cost, high performance) and was rated best performer in transmission lines, transformers, circuit breakers, and control and protection.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capex | INR 28,000 crores, likely rising above INR 30,000 crores (exact figure after 3 months) | FY26 |
| Capex | INR 35,000 crores | FY27 |
| Capex | INR 45,000 crores | FY28 |
| Capitalization catch-up | Delayed projects from FY25 to be commissioned | Q1 FY26, some possibly Q2 |
| HVDC Leh-Ladakh award | Bid under evaluation, award expected | Q2 FY26 |
| Green Hydrogen pilot award | At Neemrana Substation | June 2025 |
| RE consumption target | 50% of electricity consumption from RE | Before December 2025 |
| Net Water Positive | Company-wide | By 2030 |
| Zero Waste to Landfill | Company-wide | By 2030 |
| Net Zero emissions | Company-wide | By 2047 |
| Dividend | May reduce further from INR 9 depending on capex requirements | No fixed timeline |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Standalone revenue | ₹12,482 cr |
| Standalone PAT | ₹4,336 cr |
| Consolidated revenue | ₹12,591 cr |
| Consolidated PAT | ₹4,143 cr |
| FY25 consolidated total income | ₹47,459 cr, vs ₹46,913 cr last year |
| FY25 consolidated PAT | ₹15,521 cr |
| FY25 standalone total income | ₹46,325 cr, profit ₹15,354 cr |
| EPS | ₹16.69 (FY25) |
| Book value per share | ₹99.63 (FY25) |
| Return on net worth | 16.75% (FY25) |
| Debt-to-equity ratio | 59:41 (FY25) |
| Gross fixed assets | ₹290,715 cr (FY25) |
| Capital work in progress | ₹36,341 cr (FY25) |
| Net worth | ₹92,663 cr, up from ₹87,145 cr |
| Total debt | ₹130,965 cr (FY25) |
| Capex achieved | ₹26,255 cr (FY25), vs target of ~₹20,000 cr |
| Capitalization | ₹9,014 cr (FY25), up from ₹7,618 cr; plan was ₹16,000–17,000 cr |
| Capex guidance FY26 | ₹28,000 cr, likely to exceed ₹30,000 cr |
| Capex guidance FY27 | ₹35,000 cr |
| Capex guidance FY28 | ₹45,000 cr |
| Works in hand | ₹154,680 cr, TBCB ₹105,000 cr, new RTM ₹37,000 cr, ongoing RTM ₹9,580 cr, others ₹2,785 cr |
| Business outlook 2032 | ₹306,600 cr, ISTS ₹270,000 cr, other business ₹7,500 cr |
| TBCB projects won in FY25 | 24 projects, cost ~₹92,000 cr, market share 57.34% by NCT cost, 54.55% by project wins |
| TBCB bid pipeline FY26 | ₹45,000–46,000 cr, ₹34,000 cr under bidding, ₹10,000–11,000 cr yet to be bid |
| System availability | 99.82% (FY25), incentive cap at 99.75% |
| Tripping per line per year | 0.27 (FY25) |
| Telecom segment income | ₹1,128 cr (FY25), vs ₹910 cr last year |
| Consultancy segment revenue | ₹799 cr (FY25), vs ₹553 cr last year |
| Commercial billing | ₹36,877 cr (FY25), realization ₹38,284 cr, 103.8% |
| Outstanding receivables | ₹3,388 cr at quarter end |
| Dividend per share | ₹10.5 (FY25, cash basis); payout reduced by ₹2–2.25, may reduce further from ₹9 |
| Market capitalization | ₹270,136 cr at FY25 end, share price ₹290.35 |
| ROE dip | ~100 bps at consolidated level in FY25 |
| Scope 1 emissions reduction | 40.61% (FY25) |
| Scope 2 emissions reduction | 5.23% (FY25) |
| RE share of electricity consumption | 36% achieved, target 50% before Dec 2025 |