- Strong quarter, broad-based growth: Revenue rose 26.5% YoY to ₹1,554 crores, driven by favorable mix and execution, while orders grew 11.7% YoY led by renewables and power quality.
- Data center and renewables are breakout segments: Data center revenue surged 346% YoY and renewables 135% YoY, confirming the energy transition and digital infrastructure themes are converting into material revenue.
- Margins are recovering on schedule: Operational EBITDA margin reached 8.1%, up from the prior quarter, with material costs and other expenses both improving; management reaffirmed the double-digit exit target.
- The HVDC catalyst is approaching: Management expects at least one of the two remaining HVDC tenders to be finalized this financial year, a potential step-change for the order book.
- What to watch next quarter: Whether the double-digit margin target stays on track as the dual IT system costs persist, the pace of HVDC order finalization, and any stabilization in the rail and metro segment.
Demand Environment
- Order intake driven by energy transition: Orders of ₹1,952 crores were led by renewable studies from utilities, power quality and substation projects; expansion, upgrade and efficiency improvements at existing power plants also contributed.
- Segment-level momentum is broad: Industries grew 78% YoY, transmission 34% YoY, while data center and renewable posted triple-digit growth; rail and metro was the only decliner at 11% YoY.
- Products and utilities led the mix: Products took the lead among segments, while utilities and direct end users were the clearer winners among sectors and channels respectively.
- Service and export streams are diversifying revenue: Services contributed 12% of orders, primarily from industries, renewable and transportation; exports accounted for 22% of orders, with significant share from high-voltage products and grid integration orders from European and African markets.
- Rail and metro expected to recover: Management cited electrification of railways and growing metro networks as drivers that will push these segments in the near future.
Margin Trajectory & Cost Structure
- Sequential margin improvement: Operational EBITDA margin reached 8.1%, reflecting continuous efforts toward improving margins and enhancing operational efficiency.
- Cost lines moved favorably: Material cost improved to 61.7% from 62.8% in the prior quarter; personnel expenses were lower at 8.8%; other operational expenses improved to 20.9% from 23.6%. Exchange rate variance was 1.5%.
- Other expenses are normalizing: Management sees no one-offs in the current quarter and expects other expenses to be "more or less consistent in this particular range" going forward, with variable expenses fluctuating with growth.
- Dual IT system costs persist: The company is still running a dual IT system as part of the transition to a new S4/HANA ERP implemented in the previous quarter; IT costs are in the 2.7% to 3% range, and efficiency gains are expected to take two to three quarters to materialize.
- Cash flow timing impact: Operating cash flow was negative in Q2 because a large HVDC project had higher payouts in the quarter, though collections were good; borrowings increased by approximately ₹45 crore QoQ.
Ajay Singh: "If you see the table, it is a clear picture how the relentless pursuit for improving the bottom line and the progressive margin basically recovery that we are able to see."
Order Book & Key Projects
- Backlog provides multi-year visibility: The order backlog stands at ₹8,910 crores, providing visibility of approximately 26 months for execution.
- HVDC catalyst approaching: Management expects at least one of the two remaining HVDC tenders to be finalized in this financial year; the Leh Ladakh HVDC bid has not yet been submitted, with discussions ongoing about suitability.
- Related-party orders are material but uncertain: Of the ₹1,200 crore related-party approval taken, approximately ₹300+ crore had been received by 30th September; management cautioned that approvals are taken in anticipation of joint bidding and not all approved amounts are guaranteed to materialize.
- High-speed rail orders still in play: Conversations are ongoing but not yet concluded.
- Key commissioned projects: A 400 kV 600 MW substation at Jaisalmer, a 110 kV transformer base for an industrial plant in Trichy, and a 220/130/33 kV substation for intrastate transmission projects in Madhya Pradesh were all commissioned during the quarter.
N. Venu: "Whatever we take the approval, there's no guarantee that we will get everything. We take in approval in anticipation of some of the projects we are bidding together with those companies..."
Supply Chain & Input Costs
- CRGO supply is secure, pricing is managed: Hitachi Energy globally is one of the largest consumers of CRGO electrical steel; the company has robust frame agreements with global suppliers and has not faced supply problems. Prices are fluctuating but more than 60% of contracts have price escalation clauses allowing transparent pass-through.
- Priority is supply over pricing: Management explicitly stated that ensuring supply takes precedence over pricing concerns, given the company's scale as a global consumer.
- Realizations are stable: Management declined to discuss realizations on a product-line basis but noted that high demand creates upward margin tendency while costs are also rising; the net view is "stable."
N. Venu: "We are giving priority to ensuring the supply over the pricing."
Strategic Initiatives & Capabilities
- Capacity expansion underway: Expansion work has started on transformers and interrupter facilities in Maneja.
- Battery storage capability being built: Hitachi Energy globally acquired EKS, which specializes in grid-scale battery energy storage applications; Hitachi Energy India will leverage EKS's solutions and products to offer to Indian customers as the market matures.
- New ERP system live: The company implemented S4/HANA in the previous quarter; efficiency gains are expected in two to three quarters.
- Sustainability program realigned: Globally realigning the sustainability 2030 program to focus on three strands: planet, people and principles, with the core idea to "move beyond the realm of our products and services offering and deliver for a greater good of the society."
- Market opportunity sizing: Green hydrogen expected to attract investments of ₹10.6 lakh crore as the country targets 0.5 crore tons of hydrogen by 2030; the Indian data center market is estimated to reach ₹85,000 crores by 2027; India plans to increase power transmission capacity by 35% by 2032 with expected investment of ₹9.15 lakh crore.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Margin target | Double-digit operational EBITDA margin | By end of FY25 |
| HVDC order finalization | At least one of two remaining HVDC tenders finalized | This financial year |
| ERP efficiency gains | Efficiency gains from new S4/HANA system | Two to three quarters |
| Other expenses range | Consistent around current range, fluctuating with growth | Ongoing |
| Rail and metro recovery | Electrification and metro networks to push segments | Near future |
| Related-party orders | Larger contribution expected, but no guarantee on full approved amount | Second half of FY25 |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Revenue | ₹1,553.8 cr, +26.5% YoY and +17.1% QoQ |
| Operational EBITDA | ₹126.3 cr, margin of 8.1% |
| Profit before tax | ₹70.6 cr, +118% YoY; grew 3x QoQ |
| Profit after tax | ₹52.3 cr, +111.4% YoY; grew 4x QoQ |
| Material cost | 61.7% of revenue, vs 62.8% in Q1 FY25 |
| Personnel expenses | 8.8% of revenue, lower than Q1 FY25 |
| Other operational expenses | 20.9% of revenue, vs 23.6% in Q1 FY25 |
| Order intake | ₹1,952 cr, +11.7% YoY |
| Order backlog | ₹8,910 cr, record high; revenue visibility of approx. 26 months |
| Service share of orders | 12% of total order intake |
| Export share of orders | 22% of total order intake |
| Data center segment growth | +346% YoY |
| Renewable segment growth | +135% YoY |
| Industries segment growth | +78% YoY |
| Transmission segment growth | +34% YoY |
| Rail and metro segment growth | -11% YoY |
| Related-party orders received | ~₹300 cr cumulatively as of Sep 30, against ₹1,200 cr approval |
| Short-term borrowings | Increased by ~₹45 cr QoQ |
| Working capital increase | ₹365 cr jump, driven by timing of HVDC project payouts |
| Contracts with price escalation | More than 60% of contracts |
| IT cost | 2.7% to 3% of revenue |
| CO2 emissions reduction | 88% achieved (FY 2023-24) |
| Waste reduction | 97% achieved (FY 2023-24) |
| Freshwater usage reduction | 18% vs 2030 target of 25% (FY 2023-24) |
| Female diversity | Approaching 8%, target of 8% to 10% by 2025 |