Hitachi Energy India Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/cf167leo3r0je0dd6vf3jkx1.pdf

Key Takeaways


The Grid Super-Cycle: From Planning to Approvals

Nuguri: "We always take a lot of investment ahead of the curve, and one such example was the 1150 kV AC, and we are the only company today in India fully tested transformer, design tested, and we did it seven years ago, but the projects are coming in now, which is approved just now."

Order Intake: Broad-Based Momentum

Nuguri: "Our portfolio is a bridge between the generation and the consumption. We have a play in every part, including the transportation segment, which many people do not have."

Data Centers: A Positive Surprise, Just Starting

Nuguri: "My take was clear. As I said, data center has come as a positive surprise, it is only just started. We were not looking at a data center opportunity in U.S. anyway from the beginning, because that was not our mandate."

Margins: Holding Steady, Normalization Expected

Singh: "As per the accounting policy, at each period end close, we must evaluate the open purchase order. It is not impacting per se operationally, it is just an accounting policy that we must follow. So, we call it a notional loss."

Execution & Cash Flow


Capacity Expansion & Capex


Guidance & Commitments

CommitmentSpecificsTimeline
Sustainability targetsAchieve most of 2030 sustainability targetsBy end of FY27
Majority of capex projects completeSpanning transformers, high voltage products, grid automationBy end of CY2027
Large power transformer facilityNew facility targeted2028
HVDC project pipelineAt least four to five HVDC projects expected; one already approved (NCT), others expected approvalNext 12-24 months; approvals in next 3-6 months
Material cost normalizationExports, services, and other factors to normalize material cost toward FY26 levelsNo specific timeline given
Margin improvementVolume leverage, export and service mix to work in favour; fixed costs to even out"At some point in time"

Key Metrics

MetricQ2 FY27
Revenue₹2,996.5 cr, up 63.5% YoY and 20.2% QoQ
H1 FY27 revenue₹5,490.2 cr, up 65.8% YoY
Operational EBITDA margin16.5%
EBITDA (absolute)₹494.4 cr, up 69.5% YoY and 23.6% QoQ
PBT₹430.4 cr, up 22% YoY and 10.5% QoQ
PAT₹318.5 cr, up 20.5% YoY
PBT margin14.4%
PAT margin10.6%
Order intake₹4,120.8 cr
Order intake growth (ex-HVDC)85.9% YoY and 21.8% QoQ
H1 FY27 order intake₹9,217.3 cr
H1 FY27 order intake growth (ex-HVDC)53.1% YoY
Order backlog₹33,335.4 cr, double-digit growth YoY
Service order intake growth77.1% YoY
Export order growth41% YoY
Material cost61.7% of revenue
Personnel expenses6.2% of revenue
Other expenses (operational)16.6% of revenue
Notional forex exchange loss₹88.1 cr, non-operational, excluded from EBITDA
Exchange and commodity loss (P&L)₹56.1 cr, 1.9% of revenue
Other income₹56.8 cr, interest income on bank deposits
Net cash flow from operating activities (H1 FY27)₹91 cr, versus ₹874 cr in H1 FY26
HVDC project Bhadla cumulative revenue recognition~10%
HVDC project Khavda cumulative revenue recognition4–5%
Export share of revenue25–30%, range-bound
HVDC market share50%
CRISIL ESG score69 in 2026, improved from 61 in 2025